A roadmap reads delivery blocks on notes or named features inside them, and a roadmap note that selects those outcomes by ID with a target date. The site derives the timeline; nothing is written back. The examples on this page are invented illustrations, not architecture or delivery commitments.

One delivery block on an ordinary note

Any note with a stable id can carry one delivery block, whatever itskind. The note stays the single description of the work: an SBB or HLD that is also a deliverable gets the block in its own frontmatter. Do not create a second “roadmap copy” of a design to hold the dates; the roadmap points at the note that already exists.

---
id: example-object-storage
kind: sbb
realizes: [example-storage-capability]
delivery:
  state: proposed
  domain: Storage
  owner: Example platform team
  duration_hours: 96
  effort_hours: 40
  earliest_start: 2027-04-05
  requires:
    - id: example-identity-federation
      reason: Bucket policies need the federated service accounts this design defines.
---
# Object storage for example workloads
FieldMeaning
stateRequired. unknown, proposed, in-progress, blocked or done: your statement about the work, separate from document status or approval. Unknown means unreconciled, not “not started”; it permits no actual dates and is never forecast even with an estimate. Blocked work is also never forecast until resolved in the source.
domainOptional authored architecture-domain label. Use the agreed RWS vocabulary, not a subject folder or inferred product owner. The authoritative domain list has not yet been supplied, so this first version checks nonempty text, not corporate allocation. Items without it are Unassigned.
ownerOptional free text, shown as the recorded assignment. It does not record that the owner agreed.
duration_hoursScheduling working hours on the calendar, 8 per Monday–Friday working day, from the item’s start; weekends are skipped, holidays, time of day and capacity are not modelled. Dates stay whole days: 8 h takes one working day, 16 h two, and any positive part day (for example 9 h) takes a whole extra day. 0 is a milestone. Finite, nonnegative, fractions allowed, at most 20800 (2600 working days). Without it a proposed item has no forecast. This is elapsed schedule, not engineering effort or headcount.
effort_hoursEngineering hours, independent of duration. Forty engineering hours over a 96-hour (twelve working day) duration is a normal, partly-allocated item. Effort never moves a date and is never converted into duration.
remaining_hoursFor an in-progress item: the scheduling working hours still needed, counted from the roadmap’s as_of date, with the same 8-hour working-day rounding. The original duration_hours is no longer used once work has started.
duration_days, remaining_daysLegacy whole working days, still read unchanged and shown with their hour equivalent (one day = 8 h). Use the hour fields for new notes. A day field and its hour field on the same outcome fail validation rather than one silently winning.
earliest_startOptional date before which the item cannot start, for example a contract or budget date. The forecast starts at the latest of this, the roadmap start, the observation date and the finish of its prerequisites.
actual_start, actual_finishRecorded dates. actual_start is required when in progress; actual_finish is required when done. Actuals are never re-forecast or editable in a scenario.
assessed_onOptional date on which the estimate or remaining days were last judged, shown in the inspector.
targetOptional date the item itself aims for, shown beside its forecast. The roadmap’s target is separate.
requiresA list of {id, reason} pairs: the items that must finish before this one starts, each with a readable reason. The reason is shown wherever the dependency is shown, so write it for a reader, not a parser.

Prerequisites are schedule dependencies between deliveries, so they are deliberately separate from the architecture relationships realizes, describes and depends_on. A design can depend on a building block architecturally without that block being work on a roadmap.

Provisional effort belongs on the roadmap

Use delivery.effort_estimate on the note or feature that owns the work. This invented example shows hours even while progress is unknown; it does not create timeline dates.

delivery:
  state: unknown
  effort_estimate:
    low_hours: 60
    working_hours: 144
    high_hours: 288
    basis: conditional-completion
    confidence: low
    assessed_on: 2026-10-11
    assumptions: effort-assumptions

All seven fields are required. Hours must be finite, nonnegative and ordered low ≤ working ≤ high. basis is conditional-completion or remaining-work; confidence is low, medium or high. Supply a real assessment date and an assumptions heading in the owning note with the breakdown, scope and exclusions. None of these labels means approval.

The roadmap shows ranges, coverage and source totals by basis, counting shared prerequisites once. Conditional budgets are not combined with remaining-work ranges; legacy effort_hours values have no recorded basis and stay separate. A range and a scalar cannot coexist on one outcome. Unknown progress still prevents an asserted date forecast; it does not prevent showing engineering estimates.

Map nodes show working hours and basis; the inspector links to assumptions and shows confidence/date. Timing scenarios preserve structured source ranges and their provenance. Edit ranges in Markdown; the existing scalar-only scenario controls remain available for older notes. Hours never imply duration or a seven-engineer allocation.

While work runs, and when it is done

When work starts, change the state, record the start and replace the duration with what remains. Updateremaining_hours as the estimate changes; the roadmap note’s as_of is the date the whole picture was observed, so move both together. The recorded remaining hours are counted from the planning anchor (today for a rolling forecast) and are not reduced automatically as days pass.

delivery:
  state: in-progress
  domain: Identity
  actual_start: 2027-03-08
  remaining_hours: 44
  effort_hours: 30
  assessed_on: 2027-03-15

When the item finishes, record the finish. Its dates are then fixed and the rest of the roadmap is forecast from them.

delivery:
  state: done
  domain: Identity
  actual_start: 2027-02-02
  actual_finish: 2027-02-20

Features inside their owning architecture note

Keep the feature definition, evidence and metadata together in the existing SBB, HLD or other note. A feature is independently addressable, not a mandatory new file or note kind. Its stable key is a lower-case slug; title and section are required, and the section must match a real heading in that note.

---
id: example-storage
kind: sbb
features:
  rbd:
    title: Block-volume service
    section: block-volumes
    readiness:
      state: ready
      scope: Example lab consumers on the recorded baseline
      assessed_on: 2027-03-05
      evidence: block-volume-evidence
    delivery:
      state: in-progress
      actual_start: 2027-03-06
      remaining_hours: 32
  cephfs:
    title: Shared-filesystem service
    section: shared-filesystems
    delivery:
      state: unknown
---
# Example storage solution

## Block volumes
Describe the existing contract and the next increment separately.

### Block volume evidence
Illustration only. Real evidence identifies environment, versions,
criteria, observations, limitations and supporting references.

## Shared filesystems
Describe this independent feature and its qualification needs.

This is an invented example, not a real assessment. The block-volume feature is already assessed ready for its stated scope while the next increment is in progress. One does not overwrite or imply the other. With no readiness block, the reader says Not assessed. With no delivery block, the feature remains visible but is not a scheduling item.

Feature fieldMeaning
title, sectionRequired title and owning-note heading slug. The feature key remains stable if the heading is renamed and section updated.
depends_onOptional architectural note/feature references, separate from scheduling. Cycles are permitted; missing, duplicate or self references are not.
readinessOptional assessment: required state (unknown, not-ready, ready) and nonempty scope. Assessed states require an ISO assessed_on date and evidence heading slug in the same note. Put baseline, environment, criteria and findings in that section. The validator checks the reference, not the truth of the evidence.
deliveryOptional next bounded increment, with the same fields as note-level delivery. Never inherits the owning note’s estimate or state.

Use example-storage#rbd in depends_on, delivery.requires.id or roadmap.items. The suffix is the feature key, not its heading. Bare example-storage selects only a note-level delivery block, never all features. Scheduling references must have a delivery block; architectural references need not. realizes, describes and roadmap.offering remain note-only.

A scheduling edge waits for the named delivery increment. It does not infer a gate from current readiness: a consumer of an already available capability need not wait for an unrelated enhancement. Only add a scheduling prerequisite where that increment is genuinely needed. Siblings do not implicitly depend on each other.

The reader lists every feature and links to its section, evidence and participating roadmaps. The roadmap’s Features by owning note navigator groups related items without inventing aggregate readiness or dates. Its inspector separates Readiness now from Next delivery. The general relationships graph remains an owning-note overview with precise feature links.

One roadmap note that selects items by ID

A roadmap is an ordinary note whose id is a lower-case slug (it becomes the address/roadmaps/<id>/) and whose roadmap block lists the note or feature delivery IDs it counts. Write the reasoning in the body: why these items, what the target date commits to and who set it.

---
id: example-platform-2027
roadmap:
  as_of: 2027-03-15
  target: 2027-06-30
  offering: example-platform-offering
  items:
    - example-object-storage
    - example-cluster-lifecycle
---
# Example platform roadmap, first half of 2027

Why these items, what the target means and who decided it, in prose.
FieldMeaning
startOptional agreed planning start. Omit it for a rolling forecast: unstarted work is planned from today in Europe/Amsterdam (the next working day at a weekend), and the dates move with the calendar until a start is agreed. Give a real date to fix the plan: today’s date then never moves it, and unstarted work whose planned start has passed is flagged for replanning rather than silently shifted.
as_ofRequired. The date on which the states, actuals and remaining estimates were observed. It is not the calculation date: the clock never rewrites it, burns down remaining work or creates progress. Actual dates after it are reported as inconsistent, and nothing is planned before it.
targetThe fixed date the roadmap aims at. The forecast is compared with it and reported as early, on time or late by calendar days; the target is never moved.
itemsNote IDs or qualified note-id#feature-key delivery references, in any order. Prerequisites are included automatically and marked Supporting prerequisite. Both listed items and their prerequisites constrain the forecast; omitting a prerequisite from this list does not remove the obligation.
offeringOptional ID of the note that describes the product or service the roadmap delivers, linked from the roadmap header.

The build validates the blocks: unknown fields, impossible dates, missing IDs, a listed note without a delivery block, duplicated or self-referencing prerequisites and dependency cycles fail the build with a message naming the file. Several roadmaps may list the same delivery note; the note is still written once.

Reading the derived timeline

The workspace opens Dependencies when nothing is dated, showing prerequisite order rather than a time axis. Arrows run from a prerequisite to what needs it. Switch to Timeline for dated work, with fit, quarter, month and week scales; undated rows have no date coordinate. Its Lanes control shows either one row per item or one lane per domain, where each item is a compact card with its icon, product and feature name: dated cards sit at their forecast start with the true span drawn along the card's base, overlapping cards stack inside the lane, and undated cards stay in a separate "not dated" strip. Hover or focus a card for its facts in a popup you can move onto and read; select the card for the full details. Both views use the same selected item and scenario, and a close button gives space back to the visualization. The dependency map has fit/zoom and an equivalent keyboard-readable ordered list. Column order is not a corporate domain, project phase or approval.

A zero-hour item is an outcome milestone: it can occur on the working day its prerequisites finish, rather than requiring another delivery day. Missing estimates are not zero-hour milestones. A recorded actual finish without an actual start does not establish the actual duration.

  • Calculation date. The page states whether it is a rolling forecast (no agreed start; calculated today in Europe/Amsterdam) or a fixed plan (agreed start), and the date it was calculated. With JavaScript the browser recalculates with its own today, also when a page stays open past midnight; without JavaScript the page shows the date it was built, labelled as such. A downloaded scenario records that calculation date so it can be reproduced later.
  • Forecast. Each undone item starts at the latest of the planning anchor (the agreed start or today, never before the observation date), its earliest_start — a lower bound, not a booking — and the working day after its last prerequisite finishes; independent items start in parallel; it ends after its working days (scheduling hours divided by 8, rounded up to whole days). The roadmap forecast is the latest finish among the listed items and their prerequisites.
  • Incomplete. An item with no estimate, an unknown or blocked state, an actual date after as_of, or an undated prerequisite has no forecast. The page says which items and why, and the roadmap forecast is reported as incomplete rather than guessed.
  • Why these dates. The inspector names the prerequisite that actually drives an item’s start, with the authored reason, and the items that wait on it. Filtering the chart by domain keeps those cross-domain links visible in the inspector and the list.
  • Scenario. The timeline can be explored with different estimates, in the page’s memory only. Applying a change recalculates with the same rules; nothing is stored in the browser or sent anywhere, and reloading returns to the source. The download is a proposal of changes with the build revision and the pinned calculation date, to be applied by editing the Markdown and reviewing through Git.
  • Not a commitment. A derived date is arithmetic on authored estimates. It is not a capacity plan, an approval, or evidence that an item is accepted, compliant or resourced. Record those in prose with their evidence and authority.

Evolving an architecture without copying it

One delivery block describes one bounded outcome at note or feature level. Keep features with the architecture that explains them, using the body for scope and evidence. When splitting an aggregate delivery, remove or narrow its estimate rather than count the same work twice. This slice supports one next increment per feature, not a multi-release history engine. Preserve completed actuals and use distinct scoped outcome identities when another increment needs independent tracking. A separate note is for a genuinely separate subject, not a requirement of the planning engine.

What you can try in a scenario

The first version edits duration or remaining working hours, legacy scalar engineering hours and earliest start. A note still written in legacy days is shown in its hour equivalent; a changed value is proposed as the hour field, and the downloaded proposal names the legacy day field it replaces so both units never remain in the source. Unknown or blocked items, and their dependents, stay undated whatever is entered. It does not edit structured effort ranges or their basis, dependencies, scope, readiness/evidence, actuals, state, target or domain ownership, perform resource levelling, or create a PR. Export is a proposed change list, not a second roadmap source. Feature changes retain their owning note and feature key. Apply them manually to the named Markdown fields, compare the original values and source revision against the current branch, and review the diff. Do not apply an old proposal blindly. The item list and print view always show the source baseline.

The repository’s docs/roadmaps.md holds the durable description of this contract. TheRoadmaps page lists every roadmap note on the published branch, and a note that is counted by a roadmap links back to it under its title.