Roadmaps

Each roadmap is a note in the vault that names a target date and the delivery items it counts. The dates here are arithmetic on authored estimates and recorded actuals, calculated for the date shown on each roadmap in Europe/Amsterdam; they are not commitments or approval. Without an agreed start date a roadmap is a rolling forecast from today.

  • Roadmap for CLaaS — Clusters-as-a-Service: first production offering

    CLaaS — March 2027 roadmap

    • 5 main items
    • 78 supporting prerequisites
    • 46 feature items
    • 3 assigned domains, plus unassigned work
    • Observed
    • 28 of 83 dated.

    Rolling forecast · calculated 26 Nov 2026 when this page was built · no agreed start date · Europe/Amsterdam

    Fixed target
    Baseline forecast
    Incomplete55 items cannot be dated

    35 proposed · 48 unknown27 steps of dependency order, first to last

    Source effort estimates82/83 outcomes estimated; 1 missing
    • Conditional completion · 79 outcomes5,118 h working estimate2,383–9,944 h low–high
    • Remaining work · 3 outcomes176 h working estimate84–360 h low–high

    Full roadmap baseline, including shared prerequisites once. Bases stay separate; filtering and timing scenarios do not change these source totals. Conditional estimates are not verified remaining work. Engineering effort hours do not determine dates; scheduling duration hours are separate.

Whole working days only, weekends excluded; duration hours are scheduling working hours at 8 per working day, not engineering effort. No time of day, holidays, capacity or resource model. A forecast finishing after its target is shown as late by the derived number of calendar days; the target itself is never moved. Items with no estimate, a blocked state or an undated prerequisite leave a forecast incomplete rather than guessed. Build revision a3203210221340f80866b0462f4d63b49ebc5aea. Writing delivery metadata