Roadmaps
Each roadmap is a note in the vault that names a target date and the delivery items it counts. The dates here are arithmetic on authored estimates and recorded actuals, calculated for the date shown on each roadmap in Europe/Amsterdam; they are not commitments or approval. Without an agreed start date a roadmap is a rolling forecast from today.
Roadmap for CLaaS — Clusters-as-a-Service: first production offering
CLaaS — March 2027 roadmap
- 5 main items
- 78 supporting prerequisites
- 46 feature items
- 3 assigned domains, plus unassigned work
- Observed
- 28 of 83 dated.
Rolling forecast · calculated 26 Nov 2026 when this page was built · no agreed start date · Europe/Amsterdam
- Fixed target
- Baseline forecast
- Incomplete55 items cannot be dated
35 proposed · 48 unknown27 steps of dependency order, first to last
Source effort estimates82/83 outcomes estimated; 1 missing- Conditional completion · 79 outcomes5,118 h working estimate2,383–9,944 h low–high
- Remaining work · 3 outcomes176 h working estimate84–360 h low–high
Full roadmap baseline, including shared prerequisites once. Bases stay separate; filtering and timing scenarios do not change these source totals. Conditional estimates are not verified remaining work. Engineering effort hours do not determine dates; scheduling duration hours are separate.
Whole working days only, weekends excluded; duration hours are scheduling working hours at 8 per working day, not engineering effort. No time of day, holidays, capacity or resource model. A forecast finishing after its target is shown as late by the derived number of calendar days; the target itself is never moved. Items with no estimate, a blocked state or an undated prerequisite leave a forecast incomplete rather than guessed. Build revision a3203210221340f80866b0462f4d63b49ebc5aea. Writing delivery metadata