CLaaS — March 2027 roadmap

5 main items and 78 supporting prerequisites, of which 46 features of 16 notes, observed . 28 items dated.

Where this comes from
Source note
CLaaS — March 2027 roadmap CLaaS/roadmap.md
Observed as of
, the snapshot date written in the source
Planning anchor
Rolling: no start date is agreed, so unstarted work is planned from today in Europe/Amsterdam (the next working day at a weekend), currently . Prerequisites and earliest-start constraints still apply.
Build revision
a3203210221340f80866b0462f4d63b49ebc5aea
Method
Dates are whole working days, weekends excluded. Duration and remaining hours are scheduling working hours, 8 per working day; a part day counts as a whole day. No time of day, holidays, capacity or resource model; engineering effort never sets duration. A forecast is arithmetic on authored estimates and recorded dates, not a commitment or approval.
Features
A feature item is one capability of a note, addressed as note-id#feature-key. Its readiness is the author's dated assessment of what exists for a stated scope; its delivery is the next increment of work. A scenario moves delivery dates and never changes readiness.

Target against forecast

Fixed targetWritten in the source; never moved by a forecast.
Baseline forecastIncomplete55 of 83 items cannot be dated

Rolling forecast · calculated 26 Nov 2026 when this page was built · no agreed start date · Europe/Amsterdam

Source effort estimates82/83 outcomes estimated; 1 missing
  • Conditional completion · 79 outcomes5,118 h working estimate2,383–9,944 h low–high
  • Remaining work · 3 outcomes176 h working estimate84–360 h low–high

Full roadmap baseline, including shared prerequisites once. Bases stay separate; filtering and timing scenarios do not change these source totals. Conditional estimates are not verified remaining work. Engineering effort hours do not determine dates; scheduling duration hours are separate.

Baseline from source

Dependency order

Left to right is what must come first, not when. Overview shows the whole graph; selecting an item centres it at readable size. Drag to pan or use the ordered list below.

The interactive map needs JavaScript. The ordered list below carries every item and dependency.

Main delivery workSupporting foundationFinal outcomeDoneBlockedState unknownFeature of a notePrerequisite to dependentIcons identify documented products or Archy-drawn capabilities, not readiness or delivery state. Node colours and shapes show roles and delivery state.

Items in dependency order Keyboard and screen reader list
  1. No prerequisites recorded

  2. Depends on earlier work

    • Needs DNS/DHCP/IPAM

    • Needs Installation

    • Needs IPMI access and configuration

    • Needs NetBox base install

    • Needs VRF setup and separation details

  3. Depends on earlier work

    • Needs Basic Setup

    • Needs NetBox base install; NetBox base data model

  4. Depends on earlier work

    • Needs Fabric Management

    • Needs NetBox base install; NetBox base data model; Initial DC 3.0 hardware import

  5. Depends on earlier work

    • Needs Installation; Basic Setup; Fabric Management; Manage

    • Needs DCIM; IPMI access and configuration

  6. Depends on earlier work

    • Needs DC 3.0 hardware provisioned in OneView

    • Needs DC 3.0 hardware provisioned in OneView

    • Needs 100 pre-provisioned VLANs; Cisco Nexus Dashboard

  7. Depends on earlier work

    • Needs DC 3.0 hardware and firmware profiles

    • Needs DNS/DHCP/IPAM; VRF setup and separation details; 100 pre-provisioned VLANs; Integration into the fabric orchestrator

  8. Depends on earlier work

    • Needs DC 3.0 hardware and firmware profiles; All DC 3.0 hardware firmware updated

    • Needs Allocated non-production test substrate; EVPN/VXLAN; DNS/DHCP/IPAM

    • Needs DC 3.0 hardware provisioned in OneView; IPMI access and configuration; DC 3.0 hardware and firmware profiles; All DC 3.0 hardware firmware updated

  9. Depends on earlier work

    • Needs HPE OneView; BMC management and IPMI access; Firmware management and role-optimal configuration; HPE OneView enrolment

  10. Depends on earlier work

    • Needs Datacenter hardware; 100 pre-provisioned VLANs

  11. Depends on earlier work

    • Needs Base install

  12. Depends on earlier work

    • Needs Setup and tuning

    • Needs Setup and tuning

    • Needs Setup and tuning

    • Needs 100 pre-provisioned VLANs; OpenBao; Setup and tuning

  13. Depends on earlier work

    • Needs Base install; Setup and tuning; Ceph RBD availability; CephFS availability; RadosGW availability

    • Needs Allocated non-production test substrate; External Ceph bootstrap access contract; Ceph RBD availability

    • Needs EVPN/VXLAN; External Ceph bootstrap access contract; OpenBao; DNS/DHCP/IPAM; Datacenter hardware

    • Needs 100 pre-provisioned VLANs; DNS/DHCP/IPAM; RadosGW availability

  14. Depends on earlier work

    • Needs Allocated non-production test substrate; OpenShift platform; Operational Git (GitLab); Datacenter hardware

  15. Depends on earlier work

    • Needs Provider bootstrap; RBD block-volume integration; Reusable MetalLB BGP and address-pool pattern

    • Needs Provider bootstrap; DNS/DHCP/IPAM

    • Needs Provider bootstrap; OpenBao

    • Needs Provider bootstrap; DNS/DHCP/IPAM; Tenant zone creation and delegation

  16. Depends on earlier work

    • Needs cert-manager

    • Needs DCS hosting foundations; ExternalDNS; cert-manager; External Secrets

  17. Depends on earlier work

    • Needs DCS hosting foundations; DCS service-platform Operators

  18. Depends on earlier work

    • Needs DCS service-platform Operators; DCS minimal local VM hosting; RBD block-volume integration

  19. Depends on earlier work

    • Needs Provider bootstrap; Keycloak; RBD block-volume integration

    • Needs DCS service-platform Operators; Keycloak; DCS minimal local VM hosting

  20. Depends on earlier work

    • Needs ACM hub management and governance

    • Needs Provider bootstrap; ACM hub management and governance

    • Needs Provider bootstrap; ACM hub management and governance; RBD block-volume integration

    • Needs DCS service-platform Operators; DCS service-team access and governance; DCS minimal local VM hosting; Certificate lifecycle

    • Needs DCS service-platform Operators; DCS service-team access and governance; DCS minimal local VM hosting; Operational Git (GitLab)

    • Needs ACM hub management and governance; Operational Git (GitLab)

  21. Depends on earlier work

    • Needs MCE managed-fleet integration

    • Needs Base Quay install; Keycloak

    • Needs Base Quay install

  22. Depends on earlier work

    • Needs MCE hosted-control-plane capability; OpenShift Virtualization; ACM hub management and governance

    • Needs Quay authentication and authorization config

  23. Depends on earlier work

    • Needs ACM hub management and governance; Hosted control planes

    • Needs Hosted control planes

    • Needs Keycloak; Hosted control planes

    • Needs Hosted control planes

    • Needs Hosted control planes

    • Needs Allocated non-production test substrate; Hosted control planes

    • Needs Hosted control planes; CephFS availability

    • Needs Reusable MetalLB BGP and address-pool pattern; Hosted control planes; DNS/DHCP/IPAM

    • Needs Base Quay install; Quay authentication and authorization config; Quay mirror sync — OpenShift installers, Operators and marketplace; Quay image scanning

  24. Depends on earlier work

    • Needs Hosted control planes; Cohesity DataProtect; CephFS shared-filesystem integration; Ceph RGW

    • Needs cert-manager; Red Hat Quay; ExternalDNS; External Secrets; Ansible Automation Platform; OpenShift GitOps (provider); MCE hosted-control-plane capability; OpenShift Virtualization

    • Needs Hosted control planes; OpenShift GitOps (tenant); OpenShift Logging and Loki tenant access; External Splunk audit forwarding; Tenant image source (Harbor candidate)

    • Needs ACM hub management and governance; DCS service-team access and governance; Ansible Automation Platform; Red Hat Quay

    • Needs Representative qualification environment acceptance

  25. Depends on earlier work

    • Needs Workload protection

    • Needs DCS hosting foundations; DCS service-platform Operators; DCS service-team access and governance; DCS ACM integration and independent operation; DCS minimal local VM hosting

  26. Depends on earlier work

    • Needs OpenShift GitOps (tenant); Ceph RGW; Hosted control planes; Coordinated recovery

    • Needs Intent-to-runtime automation; Hosted control planes; Datacenter Services Cluster (DCS); MetalLB; Ceph RGW; Ceph clusters; CephFS shared-filesystem integration; Certificate lifecycle; Red Hat Quay; NetScaler; Tenant image source (Harbor candidate); Workload egress; Cluster metrics and ACM roll-up; OpenShift Logging and Loki tenant access; External Splunk audit forwarding; Global Hub coordination; Tenant administration and provider-control isolation; OpenShift GitOps (tenant)

  27. No further dependents

    • Needs OpenShift service boundaries; Federated authentication; Coordinated recovery; CLaaS production assurance; Tenant retirement

Timeline by domain

Working days of 8 scheduling hours, weekends excluded. Undated rows have no position; select an item to see why it starts when it does.

datacenter

  1. 26 Nov 2026 – 26 Nov 2026
  2. 26 Nov 2026 – 26 Nov 2026
  3. 26 Nov 2026 – 27 Nov 2026
  4. 30 Nov 2026 – 2 Dec 2026
  5. 3 Dec 2026 – 4 Dec 2026
  6. 4 Dec 2026 – 4 Dec 2026
  7. 7 Dec 2026 – 8 Dec 2026
  8. 8 Dec 2026 – 8 Dec 2026
  9. 9 Dec 2026 – 11 Dec 2026
  10. 14 Dec 2026 – 15 Dec 2026
  11. 15 Dec 2026 – 15 Dec 2026
  12. 15 Dec 2026 – 15 Dec 2026
  13. 15 Dec 2026 – 15 Dec 2026
  14. 16 Dec 2026 – 18 Dec 2026
  15. 21 Dec 2026 – 25 Dec 2026
  16. 28 Dec 2026 – 29 Dec 2026
  17. 28 Dec 2026 – 29 Dec 2026
  18. 28 Dec 2026 – 1 Jan 2027
  19. 1 Jan 2027 – 1 Jan 2027
  20. Not dated
  21. Not dated
  22. Not dated
  23. Not dated

IAM

  1. Not dated

Networking

  1. 26 Nov 2026 – 26 Nov 2026
  2. 26 Nov 2026 – 2 Dec 2026
  3. 26 Nov 2026 – 1 Dec 2026
  4. 27 Nov 2026 – 27 Nov 2026
  5. 30 Nov 2026 – 30 Nov 2026
  6. 1 Dec 2026 – 2 Dec 2026
  7. 2 Dec 2026 – 2 Dec 2026
  8. 2 Dec 2026 – 2 Dec 2026
  9. 3 Dec 2026 – 9 Dec 2026
  10. Not dated
  11. Not dated

Unassigned

  1. Not dated
  2. Not dated
  3. Not dated
  4. Not dated
  5. Not dated
  6. Not dated
  7. Not dated
  8. Not dated
  9. Not dated
  10. Not dated
  11. Not dated
  12. Not dated
  13. Not dated
  14. Not dated
  15. Not dated
  16. Not dated
  17. Not dated
  18. Not dated
  19. Not dated
  20. Not dated
  21. Not dated
  22. Not dated
  23. Not dated
  24. Not dated
  25. Not dated
  26. Not dated
  27. Not dated
  28. Not dated
  29. Not dated
  30. Not dated
  31. Not dated
  32. Not dated
  33. Not dated
  34. Not dated
  35. Not dated
  36. Not dated
  37. Not dated
  38. Not dated
  39. Not dated
  40. Not dated
  41. Not dated
  42. Not dated
  43. Not dated
  44. Not dated
  45. Not dated
  46. Not dated
  47. Not dated
  48. Not dated

ProposedIn progressDone (actual)Not dated, blocked or state unknownReadyFeature readiness as assessed, independent of the barBaseline under a scenarioTargetSource observedRolling planning anchor (today)Icons name the product a note documents, or an Archy-drawn capability icon where no product applies. They never show delivery state or readiness.

Features by owning note 46 features across 16 notes

Which note each feature item belongs to, with its own readiness and its next delivery increment. Grouping is for finding your way: a note's features are scheduled and assessed one by one, and listing them together does not make every sibling a prerequisite of the others.

  • ACM and Global Hub Fleet/acm-global-hub.md

    • Readiness unknownInitial provider estate enrollment and governanceNext: unknown, Not datedSection
    • Readiness unknownMarch hub-coordination role in the agreed supported topologyNext: unknown, Not datedSection
  • Ceph clusters Storage/ceph-clusters.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownUpstream Ceph installed and basically configured for the Phase 1 backend; existing reports do not establish completion of this proposed installation scope.Next: proposed, 16 Dec 2026 – 18 Dec 2026Section
    • Readiness unknownProduction-ready Ceph RBD backend capability, separate from ceph-csi installation and Kubernetes consumer qualification.Next: proposed, 28 Dec 2026 – 29 Dec 2026Section
    • Readiness unknownProduction-ready CephFS backend capability, separate from ceph-csi mounts and tenant shared-filesystem integration.Next: proposed, 28 Dec 2026 – 29 Dec 2026Section
    • Readiness unknownRadosGW set up and prepared for multisite and multiregion use; active additional sites, replication and tenant S3 acceptance are not established.Next: proposed, 28 Dec 2026 – 1 Jan 2027Section
    • Readiness unknownBasic Ceph pools and rights configured, with performance tuning for the allocated hardware; performance targets remain to agree.Next: proposed, 21 Dec 2026 – 25 Dec 2026Section
  • Ceph CSI Storage/external-ceph-csi.md

    • Readiness unknownFirst CLaaS tenant shared-filesystem consumersNext: unknown, Not datedSection
    • Readiness unknownAuthorized storage access before provider-cluster installationNext: unknown, Not datedSection
    • Readiness unknownFirst CLaaS provider and tenant block-volume consumersNext: unknown, Not datedSection
  • Cisco Nexus Dashboard Network/nexus-fabric-orchestrator.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownBasic Cisco Nexus Dashboard settings and operator authentication configured on the installed instance.Next: proposed, 27 Nov 2026 – 27 Nov 2026Section
    • Readiness unknownThe integrated fabric-management function enabled and set up in Cisco Nexus Dashboard, ready for fabric onboarding; onboarding the AM4 fabric is not included.Next: proposed, 30 Nov 2026 – 30 Nov 2026Section
    • Readiness unknownAn installed Cisco Nexus Dashboard instance in the selected placement; release, hosting and recovery are not yet established.Next: proposed, 26 Nov 2026 – 26 Nov 2026Section
    • Readiness unknownManage API access enabled with authentication and scoped roles, with representative allowed and denied requests qualified; not every VLAN/VRF operation, per-VLAN authorization or tenant network automation.Next: proposed, 1 Dec 2026 – 2 Dec 2026Section
  • CLaaS observability Observability/platform-observability.md

    • Not assessedNext: unknown, Not datedSection
    • Not assessedNext: unknown, Not datedSection
    • Not assessedNext: unknown, Not datedSection
  • Datacenter hardware Hardware/datacenter-hardware.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownBMC configuration and permitted IPMI access for all 64 Phase 1 nodes in AM4; role counts/configurations are reported, but per-node identities and accepted coverage remain unconfirmed.Next: proposed, 26 Nov 2026 – 26 Nov 2026Section
    • Readiness unknownFirmware baselines and role-specific configuration for all 64 Phase 1 nodes in AM4; per-node inventory and accepted profile coverage remain unconfirmed.Next: proposed, 15 Dec 2026 – 15 Dec 2026Section
    • Readiness unknownEnrolment of all 64 Phase 1 nodes in AM4 in HPE OneView with a working support process; per-node identities and accepted enrolment remain unconfirmed.Next: proposed, 8 Dec 2026 – 8 Dec 2026Section
  • Datacenter Services Cluster (DCS) Platform/datacenter-services-cluster.md

    The note as a whole is also an item: , unknown.

    • Readiness unknownImported DCS and every installed workload continuing operation during ACM unavailabilityNext: unknown, Not datedSection
    • Readiness unknownDCS bare-metal hosting, exposure and RBD consumers in the project estatesNext: unknown, Not datedSection
    • Readiness unknownSupported local Virtualization with one representative synthetic VM, not appliance onboardingNext: unknown, Not datedSection
    • Readiness unknownDCS-local DNS, both certificate issuers and platform secret-delivery integrationNext: unknown, Not datedSection
    • Readiness unknownService-team namespace/instance control without full-cluster authorityNext: unknown, Not datedSection
  • DCIM DCIM/dcim-service.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownAll hardware for the DC 3.0 setup imported into NetBox using the defined base model.Next: proposed, 3 Dec 2026 – 4 Dec 2026Section
    • Readiness unknownA defined base data model for the Phase 1 DC 3.0 hardware inventory.Next: proposed, 30 Nov 2026 – 2 Dec 2026Section
    • Readiness unknownExternally hosted NetBox installed and basically configured with authentication.Next: proposed, 26 Nov 2026 – 27 Nov 2026Section
  • DNS/DHCP/IPAM Network/dns-dhcp-ipam.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownAuthorized platform engineers and a scoped service account can create tenant DNS zones and delegations in the existing organizational service, with each tenant limited to its own zone.Next: proposed, 26 Nov 2026 – 2 Dec 2026Section
  • EVPN/VXLAN Network/evpn-vxlan.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownAn available set of 100 pre-provisioned VLANs within the agreed tenant, platform and storage separation boundaries.Next: proposed, 2 Dec 2026 – 2 Dec 2026Section
    • Readiness unknownThe Phase 1 fabric integrated into the separately available Cisco Nexus Dashboard service as the foundation for future network automation.Next: proposed, 3 Dec 2026 – 9 Dec 2026Section
    • Readiness unknownDocumented and qualified separation of tenant, platform and storage traffic in the Phase 1 fabric.Next: proposed, 26 Nov 2026 – 1 Dec 2026Section
  • Hosted control planes Platform/hosted-control-planes.md

    The note as a whole is also an item: , unknown.

    • Readiness unknownTailored tenant administrators and controllers in the first offeringNext: unknown, Not datedSection
  • HPE OneView DCIM/hpe-oneview.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownFirmware updated for the components of all 64 Phase 1 nodes in AM4, with observed versions reconciled to the selected baselines.Next: proposed, 14 Dec 2026 – 15 Dec 2026Section
    • Readiness unknownFirmware and configuration profiles covering the models and roles of all 64 Phase 1 nodes in AM4, with the appropriate role-specific settings.Next: proposed, 9 Dec 2026 – 11 Dec 2026Section
    • Readiness unknownAll 64 Phase 1 nodes in AM4 provisioned in the existing HPE OneView service; per-node identities and accepted coverage remain unconfirmed.Next: proposed, 7 Dec 2026 – 8 Dec 2026Section
    • Readiness unknownComplete permitted IPMI access and BMC configuration for all 64 Phase 1 nodes in AM4.Next: proposed, 26 Nov 2026 – 26 Nov 2026Section
  • MCE cluster Fleet/mce-management-cluster.md

    • Readiness unknownFirst CLaaS hosted tenant control planes on the MCE clusterNext: unknown, Not datedSection
    • Readiness unknownFirst CLaaS MCE cluster within the provider managed estateNext: unknown, Not datedSection
  • MetalLB Network/metallb-bgp.md

    The note as a whole is also an item: , unknown.

    • Readiness unknownCommon controlled MetalLB pattern reusable by provider roles and tenant ingressNext: unknown, Not datedSection
  • Qualification environment Platform/qualification-environment.md

    • Not assessedNext: unknown, Not datedSection
    • Not assessedNext: unknown, Not datedSection
  • Red Hat Quay Registry/red-hat-quay.md

    The note as a whole is also an item: , proposed.

    • Readiness unknownPlatform-only Quay instances in both datacenters.Next: proposed, Not datedSection
    • Readiness unknownPlatform-engineer login and separate service accounts/tokens for every consuming cluster.Next: proposed, Not datedSection
    • Readiness unknownVulnerability findings for the Phase 1 platform image content.Next: proposed, Not datedSection
    • Readiness unknownRequired platform lifecycle content available from both datacenter registries.Next: proposed, Not datedSection
Forecast incomplete: 55 items cannot be dated
  • OpenShift service boundaries: Prerequisite automation-flow is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite datacenter-services-cluster is unknown or inconsistent. Prerequisite metallb-bgp is unknown or inconsistent. Prerequisite tenant-object-storage is unknown or inconsistent. Prerequisite external-ceph-csi#cephfs is unknown or inconsistent. Prerequisite certificate-lifecycle is unknown or inconsistent. Prerequisite red-hat-quay is unknown or inconsistent. Prerequisite external-netscaler is unknown or inconsistent. Prerequisite tenant-image-source is unknown or inconsistent. Prerequisite organizational-egress is unknown or inconsistent. Prerequisite platform-observability#metrics is unknown or inconsistent. Prerequisite platform-observability#logs is unknown or inconsistent. Prerequisite platform-observability#audit is unknown or inconsistent. Prerequisite acm-global-hub#global-hub is unknown or inconsistent. Prerequisite hosted-control-planes#tenant-controls is unknown or inconsistent. Prerequisite tenant-gitops is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Federated authentication: Prerequisite keycloak is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Coordinated recovery: Prerequisite tenant-workload-protection is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • CLaaS production assurance: Prerequisite qualification-environment#representative is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • CLaaS: Prerequisite openshift-service-boundaries is unknown or inconsistent. Prerequisite federated-authentication is unknown or inconsistent. Prerequisite coordinated-recovery is unknown or inconsistent. Prerequisite caas-production-assurance is unknown or inconsistent. Prerequisite tenant-retirement is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Intent-to-runtime automation: Prerequisite cert-manager is unknown or inconsistent. Prerequisite red-hat-quay is unknown or inconsistent. Prerequisite external-dns is unknown or inconsistent. Prerequisite external-secrets is unknown or inconsistent. Prerequisite ansible-automation-platform is unknown or inconsistent. Prerequisite openshift-gitops is unknown or inconsistent. Prerequisite mce-management-cluster#hcp-hosting is unknown or inconsistent. Prerequisite openshift-virtualization is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Hosted control planes: Prerequisite mce-management-cluster#hcp-hosting is unknown or inconsistent. Prerequisite openshift-virtualization is unknown or inconsistent. Prerequisite acm-global-hub#hub is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Datacenter Services Cluster (DCS): Prerequisite datacenter-services-cluster#hosting is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite datacenter-services-cluster#acm-management is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • MetalLB: Prerequisite metallb-bgp#pattern is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Ceph RGW: Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • CephFS shared-filesystem integration (feature of Ceph CSI): Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Certificate lifecycle: Prerequisite cert-manager is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Red Hat Quay: Prerequisite red-hat-quay#base-install is unknown or inconsistent. Prerequisite red-hat-quay#authentication-authorization is unknown or inconsistent. Prerequisite red-hat-quay#mirror-sync is unknown or inconsistent. Prerequisite red-hat-quay#image-scanning is unknown or inconsistent.
  • NetScaler: Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Tenant image source (Harbor candidate): Delivery state is unknown; reconcile it before forecasting.
  • Workload egress: Delivery state is unknown; reconcile it before forecasting.
  • Cluster metrics and ACM roll-up (feature of CLaaS observability): Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • OpenShift Logging and Loki tenant access (feature of CLaaS observability): Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • External Splunk audit forwarding (feature of CLaaS observability): Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Global Hub coordination (feature of ACM and Global Hub): Prerequisite acm-global-hub#hub is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Tenant administration and provider-control isolation (feature of Hosted control planes): Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite tenant-gitops is unknown or inconsistent. Prerequisite platform-observability#logs is unknown or inconsistent. Prerequisite platform-observability#audit is unknown or inconsistent. Prerequisite tenant-image-source is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • OpenShift GitOps (tenant): Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Keycloak: Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Workload protection: Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite cohesity-backup-service is unknown or inconsistent. Prerequisite external-ceph-csi#cephfs is unknown or inconsistent. Prerequisite tenant-object-storage is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Representative qualification environment acceptance (feature of Qualification environment): Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Tenant retirement: Prerequisite tenant-gitops is unknown or inconsistent. Prerequisite tenant-object-storage is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite coordinated-recovery is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • cert-manager: Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • ExternalDNS: Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • External Secrets: Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite openbao is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Ansible Automation Platform: Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Prerequisite operational-git is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • OpenShift GitOps (provider): Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite operational-git is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • MCE hosted-control-plane capability (feature of MCE cluster): Prerequisite mce-management-cluster#fleet-integration is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • OpenShift Virtualization: Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • ACM hub management and governance (feature of ACM and Global Hub): Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite keycloak is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • DCS hosting foundations (feature of Datacenter Services Cluster (DCS)): Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Prerequisite metallb-bgp#pattern is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • DCS service-platform Operators (feature of Datacenter Services Cluster (DCS)): Prerequisite datacenter-services-cluster#hosting is unknown or inconsistent. Prerequisite external-dns is unknown or inconsistent. Prerequisite cert-manager is unknown or inconsistent. Prerequisite external-secrets is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • DCS service-team access and governance (feature of Datacenter Services Cluster (DCS)): Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite keycloak is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • DCS ACM integration and independent operation (feature of Datacenter Services Cluster (DCS)): Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite ansible-automation-platform is unknown or inconsistent. Prerequisite red-hat-quay is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • DCS minimal local VM hosting (feature of Datacenter Services Cluster (DCS)): Prerequisite datacenter-services-cluster#hosting is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Reusable MetalLB BGP and address-pool pattern (feature of MetalLB): Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite evpn-vxlan is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • DNS/DHCP/IPAM: Duration is not estimated.
  • Base Quay install (feature of Red Hat Quay): Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Prerequisite certificate-lifecycle is unknown or inconsistent.
  • Quay authentication and authorization config (feature of Red Hat Quay): Prerequisite red-hat-quay#base-install is unknown or inconsistent. Prerequisite keycloak is unknown or inconsistent.
  • Quay mirror sync — OpenShift installers, Operators and marketplace (feature of Red Hat Quay): Prerequisite red-hat-quay#authentication-authorization is unknown or inconsistent.
  • Quay image scanning (feature of Red Hat Quay): Prerequisite red-hat-quay#base-install is unknown or inconsistent.
  • RBD block-volume integration (feature of Ceph CSI): Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite external-ceph-csi#backend-access is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • Cohesity DataProtect: Delivery state is unknown; reconcile it before forecasting.
  • Allocated non-production test substrate (feature of Qualification environment): Delivery state is unknown; reconcile it before forecasting.
  • Provider bootstrap: Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite openshift-platform is unknown or inconsistent. Prerequisite operational-git is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • OpenBao: Delivery state is unknown; reconcile it before forecasting.
  • Operational Git (GitLab): Delivery state is unknown; reconcile it before forecasting.
  • MCE managed-fleet integration (feature of MCE cluster): Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite acm-global-hub#hub is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • EVPN/VXLAN: Prerequisite dns-dhcp-ipam is unknown or inconsistent.
  • External Ceph bootstrap access contract (feature of Ceph CSI): Prerequisite openbao is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
  • OpenShift platform: Prerequisite evpn-vxlan is unknown or inconsistent. Prerequisite external-ceph-csi#backend-access is unknown or inconsistent. Prerequisite openbao is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.

An item with no estimate, a blocked state or an undated prerequisite stays undated. Nothing is assumed in its place; add the missing value to the delivery block in its source note.

Source baseline — every item

Baseline dates, with each prerequisite and its authored reason. Scenario changes are shown in the map, timeline and comparison, not this source list. Printing includes every baseline item, regardless of the domain filter.

ItemDomainStateReadinessOwnerEffortEstimateStartFinishRequiresNeeded byNot dated because
OpenShift service boundariesPlatform/openshift-service-boundaries.mdUnassignedUnknown—not recorded120 h working · 60–240 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Intent-to-runtime automation: Final service acceptance must demonstrate the agreed authorized request-to-reviewed-revision provisioning journey; technical HCP realization can be qualified independently on the existing dev path.
  • Hosted control planes: Validate the complete service boundary using control planes on MCE and worker VMs on the separate Virtualization infrastructure.
  • Datacenter Services Cluster (DCS): Final hosting acceptance consumes the DCS milestone over its five feature outcomes, including the all-installed-workloads ACM-independence demonstration; applications use earlier scoped DCS features.
  • MetalLB: The offered application connectivity includes provider-operated BGP load-balancing integration for internal and internet-facing applications.
  • Ceph RGW: The first storage offer includes an S3 object-service contract in addition to RBD and CephFS volumes.
  • Ceph clusters: Final hosting acceptance consumes the complete five-feature upstream Ceph backend milestone; earlier storage consumers use their precise backend feature handoffs without waiting for the aggregate.
  • CephFS shared-filesystem integration: Final tenant hosting acceptance needs the separately qualified shared-filesystem contract; RBD readiness does not establish CephFS readiness.
  • Certificate lifecycle: The first service needs qualified internal-PKI and public certificate lifecycle and consumer trust.
  • Red Hat Quay: The selected operational registry is Quay on DCS; initial bootstrap image supply is a separate prerequisite, not supplied retroactively by this service.
  • NetScaler: Internet-facing application acceptance requires a qualified handoff to the existing external perimeter, without exposing private management endpoints.
  • Tenant image source (Harbor candidate): Tenant workloads need an agreed usable image-source contract distinct from platform-only Quay; Harbor remains the candidate to confirm.
  • Workload egress: Tenant runtime outbound access must follow the existing organizational egress service and its qualified policy and support contract.
  • Cluster metrics and ACM roll-up: Final hosting acceptance consumes qualified metrics, roll-up and tenant query isolation.
  • OpenShift Logging and Loki tenant access: The offered shared application logging capability needs its own qualified collection and access boundary.
  • External Splunk audit forwarding: Audit-source forwarding and receiving-service handoff are distinct from metrics and application logging.
  • Global Hub coordination: Global Hub is mandatory in the March scope without making it the prerequisite for every ACM or HCP consumer.
  • Tenant administration and provider-control isolation: Usable tenant administration must preserve provider controls through direct API, Argo and Operator paths.
  • OpenShift GitOps (tenant): The first offering includes tenant-facing OpenShift GitOps with repository onboarding and bounded application reconciliation.
  • CLaaS: The hosting, tenant and shared-management boundaries must support the agreed first service scope.
Prerequisite automation-flow is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite datacenter-services-cluster is unknown or inconsistent. Prerequisite metallb-bgp is unknown or inconsistent. Prerequisite tenant-object-storage is unknown or inconsistent. Prerequisite external-ceph-csi#cephfs is unknown or inconsistent. Prerequisite certificate-lifecycle is unknown or inconsistent. Prerequisite red-hat-quay is unknown or inconsistent. Prerequisite external-netscaler is unknown or inconsistent. Prerequisite tenant-image-source is unknown or inconsistent. Prerequisite organizational-egress is unknown or inconsistent. Prerequisite platform-observability#metrics is unknown or inconsistent. Prerequisite platform-observability#logs is unknown or inconsistent. Prerequisite platform-observability#audit is unknown or inconsistent. Prerequisite acm-global-hub#global-hub is unknown or inconsistent. Prerequisite hosted-control-planes#tenant-controls is unknown or inconsistent. Prerequisite tenant-gitops is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Federated authenticationIdentity/federated-authentication.mdUnassignedUnknown—not recorded136 h working · 56–272 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Keycloak: Demonstrate the first CLaaS tenant and administrator authentication boundary against the proposed common IAM identity provider.
  • Hosted control planes: Final tenant group mapping, access refusal and revocation evidence requires an actual hosted tenant; Keycloak service setup alone does not establish the consumer boundary.
  • CLaaS: The first offering needs an agreed and demonstrated tenant and administrator authentication boundary.
Prerequisite keycloak is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Coordinated recoveryRecovery/coordinated-recovery.mdUnassignedUnknown—not recorded200 h working · 88–400 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Workload protection: Final service-recovery acceptance includes the requested platform-provided tenant workload backup/restore mechanism.
  • CLaaS: Recovery responsibilities and an executable recovery path must match the first offering's promises.
  • Tenant retirement: Retirement must use the agreed data and backup retention/recovery contract before demonstrating destructive lifecycle operations.
Prerequisite tenant-workload-protection is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
CLaaS production assuranceCLaaS/production-assurance.mdUnassignedUnknown—not recorded176 h working · 80–352 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • CLaaS: Production use requires explicit scope, operating responsibilities and assessment of applicable requirements; a successful deployment is insufficient.
Prerequisite qualification-environment#representative is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
CLaaSCLaaS/index.mdUnassignedUnknown—not recorded0 h working · 0–0 h · Conditional completion
high confidence; assessed 11 Oct 2026; Estimate assumptions
0 working hours (milestone)——
  • OpenShift service boundaries: The hosting, tenant and shared-management boundaries must support the agreed first service scope.
  • Federated authentication: The first offering needs an agreed and demonstrated tenant and administrator authentication boundary.
  • Coordinated recovery: Recovery responsibilities and an executable recovery path must match the first offering's promises.
  • CLaaS production assurance: Production use requires explicit scope, operating responsibilities and assessment of applicable requirements; a successful deployment is insufficient.
  • Tenant retirement: The first service must support approved complete tenant retirement, including external handoffs and policy-governed data and backup disposition.
—Prerequisite openshift-service-boundaries is unknown or inconsistent. Prerequisite federated-authentication is unknown or inconsistent. Prerequisite coordinated-recovery is unknown or inconsistent. Prerequisite caas-production-assurance is unknown or inconsistent. Prerequisite tenant-retirement is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Intent-to-runtime automationSupporting prerequisiteAutomation/intent-to-runtime.mdUnassignedUnknown—not recorded200 h working · 80–408 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • cert-manager: Qualify the provider-managed certificate automation pattern before including it in tenant-cluster provisioning.
  • Red Hat Quay: The operational provisioning flow needs the selected platform-content registry; this is separate from the approved external sources used for initial provider bootstrap.
  • ExternalDNS: Tenant onboarding includes the qualified provider-managed DNS pattern and an Infoblox subzone delegated to that tenant.
  • External Secrets: Qualify the platform workload secret-delivery pattern used by provisioning without exposing provider secret paths to tenants.
  • Ansible Automation Platform: Qualify the full request-to-cluster journey using the chosen AAP service on DCS.
  • OpenShift GitOps (provider): The provisioning flow needs its centrally operated GitOps controllers and explicit resource ownership.
  • MCE hosted-control-plane capability: Qualify the approved-request provisioning workflow against the intended hosted-control-plane management target.
  • OpenShift Virtualization: Demonstrate provisioning of the fixed tenant worker allocation on the intended Virtualization infrastructure.
  • OpenShift service boundaries: Final service acceptance must demonstrate the agreed authorized request-to-reviewed-revision provisioning journey; technical HCP realization can be qualified independently on the existing dev path.
Prerequisite cert-manager is unknown or inconsistent. Prerequisite red-hat-quay is unknown or inconsistent. Prerequisite external-dns is unknown or inconsistent. Prerequisite external-secrets is unknown or inconsistent. Prerequisite ansible-automation-platform is unknown or inconsistent. Prerequisite openshift-gitops is unknown or inconsistent. Prerequisite mce-management-cluster#hcp-hosting is unknown or inconsistent. Prerequisite openshift-virtualization is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Hosted control planesSupporting prerequisitePlatform/hosted-control-planes.mdUnassignedUnknown—not recorded120 h working · 52–248 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • OpenShift service boundaries: Validate the complete service boundary using control planes on MCE and worker VMs on the separate Virtualization infrastructure.
  • Federated authentication: Final tenant group mapping, access refusal and revocation evidence requires an actual hosted tenant; Keycloak service setup alone does not establish the consumer boundary.
  • MetalLB: Demonstrate the chosen application entry-point integration against a representative hosted tenant cluster.
  • CephFS shared-filesystem integration: Qualify tenant shared-filesystem access and refusal against a representative hosted tenant, not just the external Ceph service.
  • Cluster metrics and ACM roll-up: Verify isolated own-cluster queries and alert routing on an actual representative tenant.
  • OpenShift Logging and Loki tenant access: Qualify platform and application log collection and tenant-scoped access against the representative tenant estate.
  • External Splunk audit forwarding: Demonstrate audit-source coverage, isolation and forwarding behaviour for actual provider and hosted-tenant sources.
  • Tenant administration and provider-control isolation: Demonstrate effective permission boundaries on a representative tenant cluster.
  • OpenShift GitOps (tenant): Qualify the tenant-facing application reconciliation service and its permitted targets against a representative hosted cluster.
  • Workload protection: Qualify workload backup and restore using a representative hosted tenant cluster, not only a backup job status.
  • Representative qualification environment acceptance: Verify representativeness against an actual provider/hosted-tenant topology before the acceptance campaign.
  • Tenant retirement: Demonstrate controlled retirement against a representative provisioned tenant cluster, rather than treating object deletion as complete service retirement.
Prerequisite mce-management-cluster#hcp-hosting is unknown or inconsistent. Prerequisite openshift-virtualization is unknown or inconsistent. Prerequisite acm-global-hub#hub is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Datacenter Services Cluster (DCS)Supporting prerequisitePlatform/datacenter-services-cluster.mdUnassignedUnknown—not recorded0 h working · 0–0 h · Conditional completion
high confidence; assessed 12 Oct 2026; Estimate assumptions
0 working hours (milestone)——
  • OpenShift service boundaries: Final hosting acceptance consumes the DCS milestone over its five feature outcomes, including the all-installed-workloads ACM-independence demonstration; applications use earlier scoped DCS features.
Prerequisite datacenter-services-cluster#hosting is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite datacenter-services-cluster#acm-management is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
MetalLBSupporting prerequisiteNetwork/metallb-bgp.mdUnassignedUnknown—not recorded64 h working · 24–128 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • Reusable MetalLB BGP and address-pool pattern: Reuse the qualified common packaging and controlled BGP/address-pool pattern before the tenant-specific worker-path demonstration.
  • Hosted control planes: Demonstrate the chosen application entry-point integration against a representative hosted tenant cluster.
  • DNS/DHCP/IPAM: Service-address pools and DNS publication need the agreed organizational allocation and delegated-access contract.
  • OpenShift service boundaries: The offered application connectivity includes provider-operated BGP load-balancing integration for internal and internet-facing applications.
Prerequisite metallb-bgp#pattern is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Ceph RGWSupporting prerequisiteStorage/tenant-object-storage.mddatacenterUnknown—not recorded128 h working · 52–256 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • 100 pre-provisioned VLANs: Qualify the tenant object endpoint over established connectivity and consumable VLANs; Nexus Dashboard onboarding is not a storage-service prerequisite.
  • DNS/DHCP/IPAM: Object-service endpoint addressing and naming must use the agreed organizational allocation and DNS contract.
  • RadosGW availability: Tenant S3 integration consumes the separately prepared RadosGW backend, without waiting for RBD or CephFS consumer qualification.
  • OpenShift service boundaries: The first storage offer includes an S3 object-service contract in addition to RBD and CephFS volumes.
  • Workload protection: Establish how the offered S3 data is protected or delegated; a volume backup result is not evidence for object data.
  • Tenant retirement: The complete retirement procedure includes the selected S3 tenant account and data disposition, separately from CSI volumes.
Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Ceph clustersSupporting prerequisiteStorage/ceph-clusters.mddatacenterProposed—not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 19 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • OpenShift service boundaries: Final hosting acceptance consumes the complete five-feature upstream Ceph backend milestone; earlier storage consumers use their precise backend feature handoffs without waiting for the aggregate.
—
CephFS shared-filesystem integrationFeature of Ceph CSISupporting prerequisiteStorage/external-ceph-csi.md #cephfs-shared-filesystem-integrationdatacenterUnknownReadiness unknown for First CLaaS tenant shared-filesystem consumersnot recorded96 h working · 44–176 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Hosted control planes: Qualify tenant shared-filesystem access and refusal against a representative hosted tenant, not just the external Ceph service.
  • CephFS availability: The shared-filesystem consumer qualification needs the available CephFS backend; this is distinct from configuring its CSI class and mounts.
  • OpenShift service boundaries: Final tenant hosting acceptance needs the separately qualified shared-filesystem contract; RBD readiness does not establish CephFS readiness.
  • Workload protection: Tenant filesystem recovery needs an established CephFS consumer path as well as the inherited RBD path.
Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Certificate lifecycleSupporting prerequisiteCertificates/certificate-lifecycle.mdUnassignedUnknown—not recorded96 h working · 44–184 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • cert-manager: Demonstrate the selected cert-manager/internal-PKI/Let's-Encrypt path together with consumer trust and certificate activation.
  • OpenShift service boundaries: The first service needs qualified internal-PKI and public certificate lifecycle and consumer trust.
  • Base Quay install: Qualify registry and actual blob-delivery endpoint trust before accepting operational image pulls.
Prerequisite cert-manager is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Red Hat QuaySupporting prerequisiteRegistry/red-hat-quay.mdUnassignedProposed—not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
0 working hours (milestone)——
  • OpenShift service boundaries: The selected operational registry is Quay on DCS; initial bootstrap image supply is a separate prerequisite, not supplied retroactively by this service.
  • Intent-to-runtime automation: The operational provisioning flow needs the selected platform-content registry; this is separate from the approved external sources used for initial provider bootstrap.
  • DCS ACM integration and independent operation: Include the selected operational registry and its usable local service contract in that demonstration; application-local tests remain Quay-owned.
Prerequisite red-hat-quay#base-install is unknown or inconsistent. Prerequisite red-hat-quay#authentication-authorization is unknown or inconsistent. Prerequisite red-hat-quay#mirror-sync is unknown or inconsistent. Prerequisite red-hat-quay#image-scanning is unknown or inconsistent.
NetScalerSupporting prerequisiteNetwork/external-netscaler.mdUnassignedUnknown—not recorded64 h working · 28–128 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • DNS/DHCP/IPAM: The public application publication contract must coordinate approved names and address allocations with the organizational service authority.
  • OpenShift service boundaries: Internet-facing application acceptance requires a qualified handoff to the existing external perimeter, without exposing private management endpoints.
Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Tenant image source (Harbor candidate)Supporting prerequisiteRegistry/tenant-image-source.mdUnassignedUnknown—not recorded100 h working · 40–200 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated———Delivery state is unknown; reconcile it before forecasting.
Workload egressSupporting prerequisiteNetwork/organizational-egress.mdUnassignedUnknown—not recorded80 h working · 32–152 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated———
  • OpenShift service boundaries: Tenant runtime outbound access must follow the existing organizational egress service and its qualified policy and support contract.
Delivery state is unknown; reconcile it before forecasting.
Cluster metrics and ACM roll-upFeature of CLaaS observabilitySupporting prerequisiteObservability/platform-observability.md #metrics-and-alerting-qualificationUnassignedUnknownReadiness not assessednot recorded120 h working · 52–240 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
OpenShift Logging and Loki tenant accessFeature of CLaaS observabilitySupporting prerequisiteObservability/platform-observability.md #logging-qualificationUnassignedUnknownReadiness not assessednot recorded136 h working · 60–272 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Hosted control planes: Qualify platform and application log collection and tenant-scoped access against the representative tenant estate.
Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
External Splunk audit forwardingFeature of CLaaS observabilitySupporting prerequisiteObservability/platform-observability.md #audit-forwarding-qualificationUnassignedUnknownReadiness not assessednot recorded92 h working · 36–176 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Hosted control planes: Demonstrate audit-source coverage, isolation and forwarding behaviour for actual provider and hosted-tenant sources.
Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Global Hub coordinationFeature of ACM and Global HubSupporting prerequisiteFleet/acm-global-hub.md #global-hub-coordinationUnassignedUnknownReadiness unknown for March hub-coordination role in the agreed supported topologynot recorded80 h working · 32–160 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——Prerequisite acm-global-hub#hub is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Tenant administration and provider-control isolationFeature of Hosted control planesSupporting prerequisitePlatform/hosted-control-planes.md #tenant-control-qualificationUnassignedUnknownReadiness unknown for Tailored tenant administrators and controllers in the first offeringnot recorded216 h working · 84–432 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite tenant-gitops is unknown or inconsistent. Prerequisite platform-observability#logs is unknown or inconsistent. Prerequisite platform-observability#audit is unknown or inconsistent. Prerequisite tenant-image-source is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
OpenShift GitOps (tenant)Supporting prerequisiteAutomation/tenant-gitops.mdUnassignedUnknown—not recorded128 h working · 52–256 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Hosted control planes: Qualify the tenant-facing application reconciliation service and its permitted targets against a representative hosted cluster.
Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
KeycloakSupporting prerequisiteIdentity/keycloak.mdIAMUnknown—not recorded168 h working · 72–320 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • DCS service-platform Operators: Accepted Keycloak service use needs the locally configured DCS DNS, both certificate issuers and secret-delivery platform, installed under controlled engineer bootstrap access.
  • DCS minimal local VM hosting: The agreed first DCS service-use baseline includes qualified minimal local Virtualization; this is a project capability gate, not a claim that Keycloak runs in a VM.
  • RBD block-volume integration: Qualify the selected DCS persistent-volume contract for the stateful IAM consumer before treating its service as ready; this follows initial bootstrap.
Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Workload protectionSupporting prerequisiteRecovery/tenant-workload-protection.mdUnassignedUnknown—not recorded192 h working · 80–384 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Hosted control planes: Qualify workload backup and restore using a representative hosted tenant cluster, not only a backup job status.
  • Cohesity DataProtect: The chosen OADP/Velero route needs a qualified destination contract with the existing organizational Cohesity service.
  • CephFS shared-filesystem integration: Tenant filesystem recovery needs an established CephFS consumer path as well as the inherited RBD path.
  • Ceph RGW: Establish how the offered S3 data is protected or delegated; a volume backup result is not evidence for object data.
  • Coordinated recovery: Final service-recovery acceptance includes the requested platform-provided tenant workload backup/restore mechanism.
Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite cohesity-backup-service is unknown or inconsistent. Prerequisite external-ceph-csi#cephfs is unknown or inconsistent. Prerequisite tenant-object-storage is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Representative qualification environment acceptanceFeature of Qualification environmentSupporting prerequisitePlatform/qualification-environment.md #representative-environment-acceptanceUnassignedUnknownReadiness not assessednot recorded64 h working · 28–128 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • CLaaS production assurance: Production acceptance needs evidence from a separate representative non-production environment with an authorized test boundary.
Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Tenant retirementSupporting prerequisiteCLaaS/tenant-retirement.mdUnassignedUnknown—not recorded120 h working · 48–240 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • OpenShift GitOps (tenant): Verify removal of tenant reconciliation and repository access so retirement cannot recreate the resources it deletes.
  • Ceph RGW: The complete retirement procedure includes the selected S3 tenant account and data disposition, separately from CSI volumes.
  • Hosted control planes: Demonstrate controlled retirement against a representative provisioned tenant cluster, rather than treating object deletion as complete service retirement.
  • Coordinated recovery: Retirement must use the agreed data and backup retention/recovery contract before demonstrating destructive lifecycle operations.
  • CLaaS: The first service must support approved complete tenant retirement, including external handoffs and policy-governed data and backup disposition.
Prerequisite tenant-gitops is unknown or inconsistent. Prerequisite tenant-object-storage is unknown or inconsistent. Prerequisite hosted-control-planes is unknown or inconsistent. Prerequisite coordinated-recovery is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
cert-managerSupporting prerequisiteCertificates/cert-manager.mdUnassignedUnknown—not recorded136 h working · 64–272 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Provider bootstrap: Qualify certificate automation on an installed provider-cluster substrate rather than require its own controller before initial cluster creation.
  • DNS/DHCP/IPAM: Endpoint naming and any domain-validation operations must use the agreed organizational authority and access scope.
  • Intent-to-runtime automation: Qualify the provider-managed certificate automation pattern before including it in tenant-cluster provisioning.
  • Certificate lifecycle: Demonstrate the selected cert-manager/internal-PKI/Let's-Encrypt path together with consumer trust and certificate activation.
  • DCS service-platform Operators: Both internal-PKI and Let's-Encrypt paths must be supported and qualified in the common pattern before DCS-local issuance and renewal acceptance.
Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
ExternalDNSSupporting prerequisiteNetwork/external-dns.mdUnassignedUnknown—not recorded128 h working · 52–256 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Provider bootstrap: Qualify the reusable in-cluster DNS integration on an initial provider substrate, without requiring the controller to create its own cluster's bootstrap DNS.
  • DNS/DHCP/IPAM: Qualify the existing DNS/IPAM address, naming and access contract before automated tenant DNS integration; this baseline does not wait for the new tenant-zone grant.
  • Tenant zone creation and delegation: Automated tenant DNS qualification needs authorized platform-engineer/service-account zone creation and delegation with enforced tenant-scoped control.
Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
External SecretsSupporting prerequisiteSecrets/external-secrets.mdUnassignedUnknown—not recorded104 h working · 48–200 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • Provider bootstrap: Qualify the reusable in-cluster secret-delivery pattern after initial provider installation rather than require its own controller for bootstrap credentials.
  • OpenBao: Platform secret delivery needs independently qualified external OpenBao access and narrowly scoped consumer identities.
  • Intent-to-runtime automation: Qualify the platform workload secret-delivery pattern used by provisioning without exposing provider secret paths to tenants.
  • DCS service-platform Operators: Reuse the common protected external-OpenBao delivery pattern before configuring its DCS-local consumer identities and stores.
Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite openbao is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Ansible Automation PlatformSupporting prerequisiteAutomation/ansible-automation-platform.mdUnassignedUnknown—not recorded112 h working · 48–224 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • DCS service-platform Operators: Accepted AAP use needs the locally configured DCS DNS, both issuer paths and protected external-OpenBao delivery platform, not just an installed cluster.
  • DCS service-team access and governance: Service-team handover needs the agreed identity-mapped namespace and protected shared-resource boundary.
  • DCS minimal local VM hosting: The agreed DCS service-use baseline includes qualified local VM capability; this is a project baseline gate, not a claim that AAP needs VM placement.
  • Operational Git (GitLab): AAP needs the protected operational Git source and approved-revision activation contract.
Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Prerequisite operational-git is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
OpenShift GitOps (provider)Supporting prerequisiteAutomation/openshift-gitops.mdUnassignedUnknown—not recorded96 h working · 44–184 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite operational-git is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
MCE hosted-control-plane capabilityFeature of MCE clusterSupporting prerequisiteFleet/mce-management-cluster.md #hosted-control-plane-capabilityUnassignedUnknownReadiness unknown for First CLaaS hosted tenant control planes on the MCE clusternot recorded112 h working · 48–240 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——Prerequisite mce-management-cluster#fleet-integration is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
OpenShift VirtualizationSupporting prerequisitePlatform/openshift-virtualization.mdUnassignedUnknown—not recorded128 h working · 52–288 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • Provider bootstrap: The initial OpenShift installation is bootstrapped externally before the Virtualization worker-hosting role is configured and qualified.
  • ACM hub management and governance: Its managed worker-hosting role needs the agreed central ACM governance and enrollment boundary.
  • RBD block-volume integration: Worker-VM disk consumers need post-bootstrap RBD qualification, not merely the external Ceph access contract.
  • Intent-to-runtime automation: Demonstrate provisioning of the fixed tenant worker allocation on the intended Virtualization infrastructure.
  • Hosted control planes: Tenant workers need the separate Virtualization infrastructure and its supported lifecycle integration.
Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
ACM hub management and governanceFeature of ACM and Global HubSupporting prerequisiteFleet/acm-global-hub.md #acm-hub-managementUnassignedUnknownReadiness unknown for Initial provider estate enrollment and governancenot recorded88 h working · 36–184 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite keycloak is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
DCS hosting foundationsFeature of Datacenter Services Cluster (DCS)Supporting prerequisitePlatform/datacenter-services-cluster.md #hosting-foundationsUnassignedUnknownReadiness unknown for DCS bare-metal hosting, exposure and RBD consumers in the project estatesnot recorded68 h working · 26–148 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • Provider bootstrap: Initial installation and controlled engineer access are bootstrap-owned; this increment qualifies the resulting DCS hosting role rather than installing the cluster again.
  • RBD block-volume integration: Apply the qualified common block-volume contract before accepting DCS-local persistent consumers.
  • Reusable MetalLB BGP and address-pool pattern: Reuse the controlled common MetalLB packaging and pool/peer pattern for DCS-local exposure, not the later hosted-tenant ingress demonstration.
Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite external-ceph-csi#rbd is unknown or inconsistent. Prerequisite metallb-bgp#pattern is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
DCS service-platform OperatorsFeature of Datacenter Services Cluster (DCS)Supporting prerequisitePlatform/datacenter-services-cluster.md #service-platform-operatorsUnassignedUnknownReadiness unknown for DCS-local DNS, both certificate issuers and platform secret-delivery integrationnot recorded68 h working · 24–152 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • DCS hosting foundations: The local controllers need installed, exposed hosting with the qualified network and persistence contract.
  • ExternalDNS: Reuse the common supported Infoblox controller, ownership and permission contract before the local rollout.
  • cert-manager: Both internal-PKI and Let's-Encrypt paths must be supported and qualified in the common pattern before DCS-local issuance and renewal acceptance.
  • External Secrets: Reuse the common protected external-OpenBao delivery pattern before configuring its DCS-local consumer identities and stores.
  • Datacenter Services Cluster (DCS): Services require the locally configured DNS, certificate and secret-delivery platform, with both issuer paths qualified.
  • Keycloak: Accepted Keycloak service use needs the locally configured DCS DNS, both certificate issuers and secret-delivery platform, installed under controlled engineer bootstrap access.
  • Ansible Automation Platform: Accepted AAP use needs the locally configured DCS DNS, both issuer paths and protected external-OpenBao delivery platform, not just an installed cluster.
  • DCS service-team access and governance: Test the namespace boundary with the actual protected DNS, issuer and secret-controller resources in place.
  • DCS minimal local VM hosting: Apply the agreed local service-platform minimum before qualifying VM-hosting consumers under controlled engineer access.
  • Base Quay install: Accepted registry use needs qualified local DNS, issuer paths and protected secret delivery at each hosting datacenter.
Prerequisite datacenter-services-cluster#hosting is unknown or inconsistent. Prerequisite external-dns is unknown or inconsistent. Prerequisite cert-manager is unknown or inconsistent. Prerequisite external-secrets is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
DCS service-team access and governanceFeature of Datacenter Services Cluster (DCS)Supporting prerequisitePlatform/datacenter-services-cluster.md #service-team-access-and-governanceUnassignedUnknownReadiness unknown for Service-team namespace/instance control without full-cluster authoritynot recorded66 h working · 24–148 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • DCS service-platform Operators: Test the namespace boundary with the actual protected DNS, issuer and secret-controller resources in place.
  • Keycloak: Final identity-mapped team access follows the usable IdP; engineer-run bootstrap and Keycloak installation do not wait for this later handover.
  • DCS minimal local VM hosting: Include the installed privileged Virtualization components in the local shared-resource permission boundary before team handover.
Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite keycloak is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
DCS ACM integration and independent operationFeature of Datacenter Services Cluster (DCS)Supporting prerequisitePlatform/datacenter-services-cluster.md #acm-integration-and-independent-operationUnassignedUnknownReadiness unknown for Imported DCS and every installed workload continuing operation during ACM unavailabilitynot recorded54 h working · 22–124 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • ACM hub management and governance: Import and reconnect DCS against the intended available ACM hub; this is a delivery prerequisite, not a permitted runtime availability dependency.
  • DCS service-team access and governance: The independence demonstration must include the real delegated access and protected local platform, not only running Pods.
  • Ansible Automation Platform: Include the selected AAP workload and its usable local service contract in the all-installed-workloads ACM-outage demonstration.
  • Red Hat Quay: Include the selected operational registry and its usable local service contract in that demonstration; application-local tests remain Quay-owned.
Prerequisite acm-global-hub#hub is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite ansible-automation-platform is unknown or inconsistent. Prerequisite red-hat-quay is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
DCS minimal local VM hostingFeature of Datacenter Services Cluster (DCS)Supporting prerequisitePlatform/datacenter-services-cluster.md #minimal-local-vm-hostingUnassignedUnknownReadiness unknown for Supported local Virtualization with one representative synthetic VM, not appliance onboardingnot recorded62 h working · 23–148 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • DCS hosting foundations: Local VM disks and connectivity use the qualified DCS hosting foundation and accepted host allocation.
  • DCS service-platform Operators: Apply the agreed local service-platform minimum before qualifying VM-hosting consumers under controlled engineer access.
  • Datacenter Services Cluster (DCS): The agreed DCS capability includes qualified minimal local VM hosting, distinct from tenant-worker infrastructure.
  • Keycloak: The agreed first DCS service-use baseline includes qualified minimal local Virtualization; this is a project capability gate, not a claim that Keycloak runs in a VM.
  • Ansible Automation Platform: The agreed DCS service-use baseline includes qualified local VM capability; this is a project baseline gate, not a claim that AAP needs VM placement.
  • DCS service-team access and governance: Include the installed privileged Virtualization components in the local shared-resource permission boundary before team handover.
  • Base Quay install: The selected DCS service-use baseline includes local VM hosting; this existing project gate does not require placing Quay in a VM.
Prerequisite datacenter-services-cluster#hosting is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Reusable MetalLB BGP and address-pool patternFeature of MetalLBSupporting prerequisiteNetwork/metallb-bgp.md #reusable-metallb-patternUnassignedUnknownReadiness unknown for Common controlled MetalLB pattern reusable by provider roles and tenant ingressnot recorded64 h working · 28–128 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • Allocated non-production test substrate: Qualify the common pattern with authorized access to an installed test substrate; it does not wait for HCP or DCS service readiness.
  • EVPN/VXLAN: The common advertisement and refusal checks need the agreed fabric routing and separation contract.
  • DNS/DHCP/IPAM: The pattern must use approved address allocations and their authority boundary.
  • MetalLB: Reuse the qualified common packaging and controlled BGP/address-pool pattern before the tenant-specific worker-path demonstration.
  • DCS hosting foundations: Reuse the controlled common MetalLB packaging and pool/peer pattern for DCS-local exposure, not the later hosted-tenant ingress demonstration.
Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite evpn-vxlan is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
DNS/DHCP/IPAMSupporting prerequisiteNetwork/dns-dhcp-ipam.mdNetworkingProposed—not recordedEffort not estimatednot estimated———
  • MetalLB: Service-address pools and DNS publication need the agreed organizational allocation and delegated-access contract.
  • Ceph RGW: Object-service endpoint addressing and naming must use the agreed organizational allocation and DNS contract.
  • NetScaler: The public application publication contract must coordinate approved names and address allocations with the organizational service authority.
  • cert-manager: Endpoint naming and any domain-validation operations must use the agreed organizational authority and access scope.
  • ExternalDNS: Qualify the existing DNS/IPAM address, naming and access contract before automated tenant DNS integration; this baseline does not wait for the new tenant-zone grant.
  • Reusable MetalLB BGP and address-pool pattern: The pattern must use approved address allocations and their authority boundary.
  • EVPN/VXLAN: The deployed fabric/host-attachment qualification uses authorized address allocations, not a competing unapproved pool; design can proceed before allocations are finalized.
  • OpenShift platform: Bootstrap and operated cluster endpoints need the existing organizational DNS/IPAM allocation and access contract.
Duration is not estimated.
100 pre-provisioned VLANsFeature of EVPN/VXLANSupporting prerequisiteNetwork/evpn-vxlan.md #100-pre-provisioned-vlansNetworkingProposedReadiness unknown for An available set of 100 pre-provisioned VLANs within the agreed tenant, platform and storage separation boundaries.Quanza8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
8 working hours (1 working day)
  • VRF setup and separation details: The proposer explicitly sequences the 100-VLAN handoff after the VRF setup and separation details; this is not an inferred vendor prerequisite.
  • Ceph RGW: Qualify the tenant object endpoint over established connectivity and consumable VLANs; Nexus Dashboard onboarding is not a storage-service prerequisite.
  • Base install: Ceph installation and operation need established connectivity and consumable pre-provisioned VLANs after VRF separation; Nexus Dashboard onboarding is not required for this handoff.
  • EVPN/VXLAN: Phase 1 requires an available set of 100 pre-provisioned VLANs after the VRF work.
  • External Ceph bootstrap access contract: Verify the external storage endpoints over the established connectivity and consumable VLAN handoff; full fabric orchestration onboarding is not needed.
  • Integration into the fabric orchestrator: The proposer explicitly sequences fabric integration after the pre-provisioned VLAN outcome.
—
RadosGW availabilityFeature of Ceph clustersSupporting prerequisiteStorage/ceph-clusters.md #radosgw-availabilitydatacenterProposedReadiness unknown for RadosGW set up and prepared for multisite and multiregion use; active additional sites, replication and tenant S3 acceptance are not established.not recorded40 h working · 40–40 h · Conditional completion
low confidence; assessed 19 Oct 2026; Estimate assumptions
40 working hours (5 working days)
  • Setup and tuning: RadosGW setup and multisite/multiregion preparation use the configured backend, independently of the volume-service availability outcomes.
  • Ceph RGW: Tenant S3 integration consumes the separately prepared RadosGW backend, without waiting for RBD or CephFS consumer qualification.
  • Ceph clusters: Phase 1 includes RadosGW set up and prepared for multisite and multiregion use.
—
Base installFeature of Ceph clustersSupporting prerequisiteStorage/ceph-clusters.md #base-installdatacenterProposedReadiness unknown for Upstream Ceph installed and basically configured for the Phase 1 backend; existing reports do not establish completion of this proposed installation scope.not recorded16 h working · 16–16 h · Conditional completion
low confidence; assessed 19 Oct 2026; Estimate assumptions
24 working hours (3 working days)
  • Datacenter hardware: Preserve the hardware acceptance gate for the planned backend installation, with managed BMCs, a recorded firmware baseline and OneView support enrolment.
  • 100 pre-provisioned VLANs: Ceph installation and operation need established connectivity and consumable pre-provisioned VLANs after VRF separation; Nexus Dashboard onboarding is not required for this handoff.
  • Ceph clusters: The upstream Ceph backend must be installed and basically configured.
  • Setup and tuning: Pool, rights and hardware-performance configuration uses the installed upstream Ceph backend.
—
Setup and tuningFeature of Ceph clustersSupporting prerequisiteStorage/ceph-clusters.md #setup-and-tuningdatacenterProposedReadiness unknown for Basic Ceph pools and rights configured, with performance tuning for the allocated hardware; performance targets remain to agree.not recorded40 h working · 40–40 h · Conditional completion
low confidence; assessed 19 Oct 2026; Estimate assumptions
40 working hours (5 working days)
  • Base install: Pool, rights and hardware-performance configuration uses the installed upstream Ceph backend.
  • Ceph clusters: Backend pools, rights and hardware-specific tuning must be established.
  • RadosGW availability: RadosGW setup and multisite/multiregion preparation use the configured backend, independently of the volume-service availability outcomes.
  • Ceph RBD availability: Production RBD availability builds on the configured pools, rights and tuned backend, independently of CephFS and RadosGW readiness.
  • CephFS availability: Production CephFS availability uses the configured and tuned backend, without waiting for RBD or RadosGW qualification.
  • External Ceph bootstrap access contract: Consumer access uses the installed backend with pools and rights configured; it does not wait for unrelated CephFS or RadosGW availability.
—
Ceph RBD availabilityFeature of Ceph clustersSupporting prerequisiteStorage/ceph-clusters.md #ceph-rbd-availabilitydatacenterProposedReadiness unknown for Production-ready Ceph RBD backend capability, separate from ceph-csi installation and Kubernetes consumer qualification.not recorded16 h working · 16–16 h · Conditional completion
low confidence; assessed 19 Oct 2026; Estimate assumptions
16 working hours (2 working days)
  • Setup and tuning: Production RBD availability builds on the configured pools, rights and tuned backend, independently of CephFS and RadosGW readiness.
  • Ceph clusters: Phase 1 includes a production-ready RBD backend capability.
  • RBD block-volume integration: Qualify ceph-csi block consumers against the available RBD backend, without requiring CephFS or RadosGW readiness.
—
CephFS availabilityFeature of Ceph clustersSupporting prerequisiteStorage/ceph-clusters.md #cephfs-availabilitydatacenterProposedReadiness unknown for Production-ready CephFS backend capability, separate from ceph-csi mounts and tenant shared-filesystem integration.not recorded16 h working · 16–16 h · Conditional completion
low confidence; assessed 19 Oct 2026; Estimate assumptions
16 working hours (2 working days)
  • Setup and tuning: Production CephFS availability uses the configured and tuned backend, without waiting for RBD or RadosGW qualification.
  • Ceph clusters: Phase 1 includes a production-ready CephFS backend capability.
  • CephFS shared-filesystem integration: The shared-filesystem consumer qualification needs the available CephFS backend; this is distinct from configuring its CSI class and mounts.
—
Base Quay installFeature of Red Hat QuaySupporting prerequisiteRegistry/red-hat-quay.md #base-quay-installUnassignedProposedReadiness unknown for Platform-only Quay instances in both datacenters.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
16 working hours (2 working days)——Prerequisite datacenter-services-cluster#service-platform is unknown or inconsistent. Prerequisite datacenter-services-cluster#service-access is unknown or inconsistent. Prerequisite datacenter-services-cluster#virtualization is unknown or inconsistent. Prerequisite certificate-lifecycle is unknown or inconsistent.
Quay authentication and authorization configFeature of Red Hat QuaySupporting prerequisiteRegistry/red-hat-quay.md #authentication-and-authorization-configUnassignedProposedReadiness unknown for Platform-engineer login and separate service accounts/tokens for every consuming cluster.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
16 working hours (2 working days)——
  • Base Quay install: Access must be qualified against the actual datacenter registry instances.
  • Keycloak: Qualify platform-engineer login through the selected shared identity service; this does not establish cluster robot authentication.
Prerequisite red-hat-quay#base-install is unknown or inconsistent. Prerequisite keycloak is unknown or inconsistent.
Quay mirror sync — OpenShift installers, Operators and marketplaceFeature of Red Hat QuaySupporting prerequisiteRegistry/red-hat-quay.md #mirror-syncUnassignedProposedReadiness unknown for Required platform lifecycle content available from both datacenter registries.not recorded16 h working · 16–16 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
32 working hours (4 working days)——
  • Red Hat Quay: The agreed OpenShift installer, Operator and marketplace content must be synchronized and consumable.
Prerequisite red-hat-quay#authentication-authorization is unknown or inconsistent.
Quay image scanningFeature of Red Hat QuaySupporting prerequisiteRegistry/red-hat-quay.md #image-scanningUnassignedProposedReadiness unknown for Vulnerability findings for the Phase 1 platform image content.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
8 working hours (1 working day)——
  • Base Quay install: Scanning must integrate with the operational Quay instances and their supported dependencies.
  • Red Hat Quay: Image scanning is required for the Phase 1 platform registry service.
Prerequisite red-hat-quay#base-install is unknown or inconsistent.
RBD block-volume integrationFeature of Ceph CSISupporting prerequisiteStorage/external-ceph-csi.md #rbd-block-volume-integrationdatacenterUnknownReadiness unknown for First CLaaS provider and tenant block-volume consumersnot recorded104 h working · 44–216 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • Keycloak: Qualify the selected DCS persistent-volume contract for the stateful IAM consumer before treating its service as ready; this follows initial bootstrap.
  • OpenShift Virtualization: Worker-VM disk consumers need post-bootstrap RBD qualification, not merely the external Ceph access contract.
  • ACM hub management and governance: Qualify the central role's selected persistent-volume consumer contract after bootstrap.
  • DCS hosting foundations: Apply the qualified common block-volume contract before accepting DCS-local persistent consumers.
Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite external-ceph-csi#backend-access is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Cohesity DataProtectSupporting prerequisiteRecovery/cohesity-backup-service.mdUnassignedUnknown—not recorded84 h working · 36–168 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated———
  • Workload protection: The chosen OADP/Velero route needs a qualified destination contract with the existing organizational Cohesity service.
Delivery state is unknown; reconcile it before forecasting.
Allocated non-production test substrateFeature of Qualification environmentSupporting prerequisitePlatform/qualification-environment.md #allocated-test-substrateUnassignedUnknownReadiness not assessednot recorded48 h working · 20–104 h · Remaining work
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated———Delivery state is unknown; reconcile it before forecasting.
Provider bootstrapSupporting prerequisitePlatform/provider-bootstrap.mdUnassignedUnknown—not recorded112 h working · 48–240 h · Remaining work
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • Allocated non-production test substrate: The selected separate non-production boundary must be allocated before executing the qualification installations covered by this bootstrap outcome.
  • OpenShift platform: Initial cluster installation uses the qualified shared network, storage and OpenShift baseline.
  • Operational Git (GitLab): Engineers need the reviewed operational source outside the clusters being created.
  • Datacenter hardware: New production installations run on accepted hosts that are reachable through managed BMCs, on a recorded firmware baseline and enrolled for support.
  • cert-manager: Qualify certificate automation on an installed provider-cluster substrate rather than require its own controller before initial cluster creation.
  • ExternalDNS: Qualify the reusable in-cluster DNS integration on an initial provider substrate, without requiring the controller to create its own cluster's bootstrap DNS.
  • External Secrets: Qualify the reusable in-cluster secret-delivery pattern after initial provider installation rather than require its own controller for bootstrap credentials.
  • OpenShift Virtualization: The initial OpenShift installation is bootstrapped externally before the Virtualization worker-hosting role is configured and qualified.
  • ACM hub management and governance: Install the hub role on an existing provider substrate.
  • DCS hosting foundations: Initial installation and controlled engineer access are bootstrap-owned; this increment qualifies the resulting DCS hosting role rather than installing the cluster again.
  • MCE managed-fleet integration: Initial MCE cluster installation precedes managed-role integration.
Prerequisite qualification-environment#substrate is unknown or inconsistent. Prerequisite openshift-platform is unknown or inconsistent. Prerequisite operational-git is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Tenant zone creation and delegationFeature of DNS/DHCP/IPAMSupporting prerequisiteNetwork/dns-dhcp-ipam.md #tenant-zone-creation-and-delegationNetworkingProposedReadiness unknown for Authorized platform engineers and a scoped service account can create tenant DNS zones and delegations in the existing organizational service, with each tenant limited to its own zone.not recorded16 h working · 16–16 h · Remaining work
low confidence; assessed 15 Oct 2026; Estimate assumptions
40 working hours (5 working days)—
  • ExternalDNS: Automated tenant DNS qualification needs authorized platform-engineer/service-account zone creation and delegation with enforced tenant-scoped control.
—
OpenBaoSupporting prerequisiteSecrets/openbao.mdUnassignedUnknown—not recorded80 h working · 32–152 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated———
  • External Secrets: Platform secret delivery needs independently qualified external OpenBao access and narrowly scoped consumer identities.
  • External Ceph bootstrap access contract: Initial Ceph consumer access needs independently available scoped credentials.
  • OpenShift platform: Establish authorized use of the existing external OpenBao service for platform bootstrap credentials before relying on it.
Delivery state is unknown; reconcile it before forecasting.
Operational Git (GitLab)Supporting prerequisiteAutomation/operational-git.mdUnassignedUnknown—not recorded52 h working · 24–104 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated———Delivery state is unknown; reconcile it before forecasting.
MCE managed-fleet integrationFeature of MCE clusterSupporting prerequisiteFleet/mce-management-cluster.md #managed-fleet-integrationUnassignedUnknownReadiness unknown for First CLaaS MCE cluster within the provider managed estatenot recorded56 h working · 24–112 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——Prerequisite provider-bootstrap is unknown or inconsistent. Prerequisite acm-global-hub#hub is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
EVPN/VXLANSupporting prerequisiteNetwork/evpn-vxlan.mdNetworkingProposed—Quanza0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)——
  • DNS/DHCP/IPAM: The deployed fabric/host-attachment qualification uses authorized address allocations, not a competing unapproved pool; design can proceed before allocations are finalized.
  • VRF setup and separation details: Phase 1 requires documented and qualified separation of tenant, platform and storage traffic.
  • 100 pre-provisioned VLANs: Phase 1 requires an available set of 100 pre-provisioned VLANs after the VRF work.
  • Integration into the fabric orchestrator: The reduced Phase 1 scope includes fabric integration into the separately available orchestration service.
Prerequisite dns-dhcp-ipam is unknown or inconsistent.
VRF setup and separation detailsFeature of EVPN/VXLANSupporting prerequisiteNetwork/evpn-vxlan.md #vrf-setup-and-separation-detailsNetworkingProposedReadiness unknown for Documented and qualified separation of tenant, platform and storage traffic in the Phase 1 fabric.Quanza32 h working · 32–32 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
32 working hours (4 working days)—
  • 100 pre-provisioned VLANs: The proposer explicitly sequences the 100-VLAN handoff after the VRF setup and separation details; this is not an inferred vendor prerequisite.
  • EVPN/VXLAN: Phase 1 requires documented and qualified separation of tenant, platform and storage traffic.
—
Datacenter hardwareSupporting prerequisiteHardware/datacenter-hardware.mddatacenterProposed—not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 13 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • Base install: Preserve the hardware acceptance gate for the planned backend installation, with managed BMCs, a recorded firmware baseline and OneView support enrolment.
  • Provider bootstrap: New production installations run on accepted hosts that are reachable through managed BMCs, on a recorded firmware baseline and enrolled for support.
  • OpenShift platform: The qualified baseline fixes role-suitable host inventory, which needs accepted hardware with managed BMCs, recorded firmware and support enrolment; design can start earlier and the existing dev estate is not reinstalled.
—
External Ceph bootstrap access contractFeature of Ceph CSISupporting prerequisiteStorage/external-ceph-csi.md #external-ceph-bootstrap-accessdatacenterUnknownReadiness unknown for Authorized storage access before provider-cluster installationnot recorded48 h working · 20–112 h · Conditional completion
low confidence; assessed 12 Oct 2026; Estimate assumptions
not estimated——
  • 100 pre-provisioned VLANs: Verify the external storage endpoints over the established connectivity and consumable VLAN handoff; full fabric orchestration onboarding is not needed.
  • OpenBao: Initial Ceph consumer access needs independently available scoped credentials.
  • Setup and tuning: Consumer access uses the installed backend with pools and rights configured; it does not wait for unrelated CephFS or RadosGW availability.
  • RBD block-volume integration: Reuse the independently qualified storage access contract before configuring the RBD consumers.
  • OpenShift platform: Initial installation needs the external storage access and allocation contract; live CSI/RBD consumer qualification follows bootstrap rather than blocking its own test substrate.
Prerequisite openbao is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
OpenShift platformSupporting prerequisitePlatform/openshift-platform.mdUnassignedUnknown—not recorded128 h working · 56–248 h · Conditional completion
low confidence; assessed 11 Oct 2026; Estimate assumptions
not estimated——
  • EVPN/VXLAN: The shared OpenShift baseline needs the selected fabric connectivity and separation.
  • External Ceph bootstrap access contract: Initial installation needs the external storage access and allocation contract; live CSI/RBD consumer qualification follows bootstrap rather than blocking its own test substrate.
  • OpenBao: Establish authorized use of the existing external OpenBao service for platform bootstrap credentials before relying on it.
  • DNS/DHCP/IPAM: Bootstrap and operated cluster endpoints need the existing organizational DNS/IPAM allocation and access contract.
  • Datacenter hardware: The qualified baseline fixes role-suitable host inventory, which needs accepted hardware with managed BMCs, recorded firmware and support enrolment; design can start earlier and the existing dev estate is not reinstalled.
  • Provider bootstrap: Initial cluster installation uses the qualified shared network, storage and OpenShift baseline.
Prerequisite evpn-vxlan is unknown or inconsistent. Prerequisite external-ceph-csi#backend-access is unknown or inconsistent. Prerequisite openbao is unknown or inconsistent. Prerequisite dns-dhcp-ipam is unknown or inconsistent. Delivery state is unknown; reconcile it before forecasting.
Integration into the fabric orchestratorFeature of EVPN/VXLANSupporting prerequisiteNetwork/evpn-vxlan.md #integration-into-the-fabric-orchestratorNetworkingProposedReadiness unknown for The Phase 1 fabric integrated into the separately available Cisco Nexus Dashboard service as the foundation for future network automation.Quanza40 h working · 40–40 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
40 working hours (5 working days)
  • 100 pre-provisioned VLANs: The proposer explicitly sequences fabric integration after the pre-provisioned VLAN outcome.
  • Cisco Nexus Dashboard: Fabric onboarding needs the available Cisco Nexus Dashboard service; installing and setting it up is a separate 40/40-hour outcome with its own features.
  • EVPN/VXLAN: The reduced Phase 1 scope includes fabric integration into the separately available orchestration service.
—
HPE OneViewSupporting prerequisiteDCIM/hpe-oneview.mddatacenterProposed—not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • Datacenter hardware: Final hardware acceptance includes the complete four-feature OneView Phase 1 milestone, not just individual consumer handoffs.
—
BMC management and IPMI accessFeature of Datacenter hardwareSupporting prerequisiteHardware/datacenter-hardware.md #bmc-management-and-ipmi-accessdatacenterProposedReadiness unknown for BMC configuration and permitted IPMI access for all 64 Phase 1 nodes in AM4; role counts/configurations are reported, but per-node identities and accepted coverage remain unconfirmed.Platform team0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • Datacenter hardware: Accepted hardware needs managed BMCs with the agreed IPMI access for the recorded inventory scope.
—
Firmware management and role-optimal configurationFeature of Datacenter hardwareSupporting prerequisiteHardware/datacenter-hardware.md #firmware-management-and-role-optimal-configurationdatacenterProposedReadiness unknown for Firmware baselines and role-specific configuration for all 64 Phase 1 nodes in AM4; per-node inventory and accepted profile coverage remain unconfirmed.Housing/infra team0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • Datacenter hardware: Accepted hardware needs role-appropriate firmware and configuration applied through a repeatable process.
—
HPE OneView enrolmentFeature of Datacenter hardwareSupporting prerequisiteHardware/datacenter-hardware.md #hpe-oneview-enrolmentdatacenterProposedReadiness unknown for Enrolment of all 64 Phase 1 nodes in AM4 in HPE OneView with a working support process; per-node identities and accepted enrolment remain unconfirmed.not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • Datacenter hardware: Accepted hardware needs HPE OneView enrolment so hardware management and the vendor support process work.
—
Cisco Nexus DashboardSupporting prerequisiteNetwork/nexus-fabric-orchestrator.mdNetworkingProposed—not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)
  • Installation: Phase 1 requires an installed Cisco Nexus Dashboard instance.
  • Basic Setup: Phase 1 requires the basic settings and authentication configured.
  • Fabric Management: Phase 1 requires the fabric-management function enabled and set up.
  • Manage: Phase 1 requires the scoped Manage API access and roles qualified.
—
DC 3.0 hardware provisioned in OneViewFeature of HPE OneViewSupporting prerequisiteDCIM/hpe-oneview.md #dc-30-hardware-provisioningdatacenterProposedReadiness unknown for All 64 Phase 1 nodes in AM4 provisioned in the existing HPE OneView service; per-node identities and accepted coverage remain unconfirmed.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
16 working hours (2 working days)
  • DCIM: Provisioned assets must reconcile with the curated DC 3.0 hardware inventory.
  • IPMI access and configuration: Preserve the agreed BMC/IPMI-before-enrolment sequence; OneView needs the configured management path.
  • HPE OneView: Phase 1 requires all DC 3.0 hardware provisioned in the existing OneView service.
  • HPE OneView enrolment: This stable hardware feature accepts the OneView-owned provisioning increment, which retains DCIM and configured IPMI prerequisites.
  • DC 3.0 hardware and firmware profiles: Preserve the agreed enrolment-before-role-assessment sequence when defining the hardware profiles.
—
IPMI access and configurationFeature of HPE OneViewSupporting prerequisiteDCIM/hpe-oneview.md #ipmi-access-and-configurationdatacenterProposedReadiness unknown for Complete permitted IPMI access and BMC configuration for all 64 Phase 1 nodes in AM4.Platform team8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
8 working hours (1 working day)——
DC 3.0 hardware and firmware profilesFeature of HPE OneViewSupporting prerequisiteDCIM/hpe-oneview.md #dc-30-hardware-and-firmware-profilesdatacenterProposedReadiness unknown for Firmware and configuration profiles covering the models and roles of all 64 Phase 1 nodes in AM4, with the appropriate role-specific settings.not recorded24 h working · 24–24 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
24 working hours (3 working days)—
All DC 3.0 hardware firmware updatedFeature of HPE OneViewSupporting prerequisiteDCIM/hpe-oneview.md #dc-30-hardware-firmware-updatesdatacenterProposedReadiness unknown for Firmware updated for the components of all 64 Phase 1 nodes in AM4, with observed versions reconciled to the selected baselines.Housing/infra team16 h working · 16–16 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
16 working hours (2 working days)—
InstallationFeature of Cisco Nexus DashboardSupporting prerequisiteNetwork/nexus-fabric-orchestrator.md #installationNetworkingProposedReadiness unknown for An installed Cisco Nexus Dashboard instance in the selected placement; release, hosting and recovery are not yet established.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
8 working hours (1 working day)—
  • Cisco Nexus Dashboard: Phase 1 requires an installed Cisco Nexus Dashboard instance.
  • Basic Setup: Settings and authentication are configured on the installed instance; this is the routine sequence announced for the four features.
—
Basic SetupFeature of Cisco Nexus DashboardSupporting prerequisiteNetwork/nexus-fabric-orchestrator.md #basic-setupNetworkingProposedReadiness unknown for Basic Cisco Nexus Dashboard settings and operator authentication configured on the installed instance.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
8 working hours (1 working day)
  • Installation: Settings and authentication are configured on the installed instance; this is the routine sequence announced for the four features.
  • Cisco Nexus Dashboard: Phase 1 requires the basic settings and authentication configured.
  • Fabric Management: The fabric-management function is enabled after basic settings and authentication; this is the routine sequence announced for the four features.
—
Fabric ManagementFeature of Cisco Nexus DashboardSupporting prerequisiteNetwork/nexus-fabric-orchestrator.md #fabric-managementNetworkingProposedReadiness unknown for The integrated fabric-management function enabled and set up in Cisco Nexus Dashboard, ready for fabric onboarding; onboarding the AM4 fabric is not included.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
8 working hours (1 working day)
  • Basic Setup: The fabric-management function is enabled after basic settings and authentication; this is the routine sequence announced for the four features.
  • Cisco Nexus Dashboard: Phase 1 requires the fabric-management function enabled and set up.
  • Manage: API roles are scoped to the enabled fabric-management function; this is the routine sequence announced for the four features.
—
ManageFeature of Cisco Nexus DashboardSupporting prerequisiteNetwork/nexus-fabric-orchestrator.md #manageNetworkingProposedReadiness unknown for Manage API access enabled with authentication and scoped roles, with representative allowed and denied requests qualified; not every VLAN/VRF operation, per-VLAN authorization or tenant network automation.not recorded16 h working · 16–16 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
16 working hours (2 working days)
  • Fabric Management: API roles are scoped to the enabled fabric-management function; this is the routine sequence announced for the four features.
—
DCIMSupporting prerequisiteDCIM/dcim-service.mddatacenterProposed—not recorded0 h working · 0–0 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
0 working hours (milestone)—
NetBox base installFeature of DCIMSupporting prerequisiteDCIM/dcim-service.md #netbox-base-installdatacenterProposedReadiness unknown for Externally hosted NetBox installed and basically configured with authentication.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
16 working hours (2 working days)—
  • DCIM: Phase 1 consumes an externally hosted NetBox service with basic configuration and authentication.
  • NetBox base data model: The base installation and authentication must be complete before defining the base data model.
  • Initial DC 3.0 hardware import: The import needs an available NetBox instance and authorized access.
—
NetBox base data modelFeature of DCIMSupporting prerequisiteDCIM/dcim-service.md #netbox-base-data-modeldatacenterProposedReadiness unknown for A defined base data model for the Phase 1 DC 3.0 hardware inventory.not recorded24 h working · 24–24 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
24 working hours (3 working days)
  • NetBox base install: The base installation and authentication must be complete before defining the base data model.
—
Initial DC 3.0 hardware importFeature of DCIMSupporting prerequisiteDCIM/dcim-service.md #initial-dc-30-hardware-importdatacenterProposedReadiness unknown for All hardware for the DC 3.0 setup imported into NetBox using the defined base model.not recorded8 h working · 8–8 h · Conditional completion
low confidence; assessed 17 Oct 2026; Estimate assumptions
16 working hours (2 working days)
  • DCIM: All DC 3.0 hardware must be recorded before accepting the inventory handoff.
—

192 dependencys across 27 columns of dependency order.

Derived from the delivery, features and roadmap blocks in the Markdown source at this revision. A forecast is arithmetic on authored estimates and recorded dates: it is not a commitment, a capacity plan, an approval or evidence that any item is accepted. An owner is a recorded assignment, not a confirmation; a readiness assessment is the author's dated statement for its stated scope, not a certification. Read how to write delivery metadata.