Establish CLaaS production acceptance and assurance
Effort scenario: caas-production-assurance
Workstream: Assurance and operations. Conditional hours under the assessment convention.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Actual policy applicability, acceptance roles and requirement traceability | 24 | 48 | 96 |
| Separate operations team's skills/access/runbook/service handover | 24 | 56 | 112 |
| Evidence review, unresolved findings and handover rehearsal | 24 | 48 | 96 |
| Release decision package and bounded transition/hypercare preparation | 8 | 24 | 48 |
Sizing confidence: low. Includes platform/security/operations participation in defining and reviewing the bounded service, not writing all component runbooks again or implementing every unassessed BIO2 control. A missing control becomes scoped engineering work rather than a presumed policy exception. Staffing for recurring support, long hypercare and tenant application migration are unestimated until scope is agreed. Formal authority/approval, service coverage and policy response queues are external lead time; engineer hours cannot manufacture approval.
This proposed delivery outcome makes the acceptance basis for the first CLaaS offering explicit. It records no institutional approval, BIO2 compliance conclusion, completed implementation or agreed delivery estimate. The assignment proposer will own the initial acceptance proposal; the formal decision route and participating responsibilities remain open.
The acceptance campaign uses a separate representative non-production environment. Its readiness gates execution of that campaign, not the start of defining criteria. Qualify the latest compatible stable component releases together and pin the accepted baseline. Evidence from different versions or a materially different topology must not silently stand in for the production configuration.
Outcome and completion criteria to agree
Identify the first consumer, workload boundary and meaningful business result. Agree the operating responsibilities and measurable service expectations before selecting evidence that demonstrates them. Include support and incidents, maintenance and upgrades, tenant onboarding and retirement, access boundaries and recovery. Distinguish provider obligations from tenant obligations.
The first-release service boundary now supplies the initial service choices. Consumer selection and incident support coverage are still open; do not replace either with an invented tenant or SLA. Acceptance must cover the TOPdesk approval → reviewed protected-branch merge → AAP → GitOps/external-system → usable cluster chain, not merely a successful job.
The accepted service direction is now a tailored tenant-admin role with provider-reserved security/admission controls, rather than a promise of unrestricted Kubernetes cluster-admin. Identify a supported enforcement point outside the tenant's ability to weaken or delete. Test attempts to change admission and security policy, obtain disallowed privileges and cross provider/tenant boundaries. Neither ongoing ACM reconciliation nor a successful login proves prevention. These are proposed checks, not observed failures or a demonstrated control.
Identity acceptance must cover the selected organizational upstream-to-Keycloak integration, required platform-engineer MFA, intended tenant opt-in behaviour and tenant administration of own-cluster groups and memberships. Reconcile those with applicable organizational policy rather than infer permission from this proposal. Qualify at least two break-glass accounts per provider/platform cluster against identity-outage recovery, including custody and audit; hosted-tenant coverage is a stretch goal rather than a current acceptance gate. Use Keycloak where possible and native identities where needed, and qualify each consumer's actual authentication path and permission boundary. Neither secret storage nor a successful human login demonstrates every controller's access path.
The first offer also requires RBD, CephFS and S3 access, a provider-supplied way to protect tenant workloads, and MetalLB BGP integration for internal/public application entry points. Define acceptance for each interface and for their tenant boundaries; CSI readiness does not establish S3, backup-job completion does not prove restore usability, and a BGP announcement is not proof of approved internet exposure. Provider-owned CSI, networking and backup permissions must not become privileges that the tailored tenant role can assign to its own apps.
Qualify the existing external NetScaler handoff without exposing private tenant APIs/consoles. Verify permitted and denied publication paths, TLS responsibilities and cross-tenant isolation. Separately establish the tenant image-source contract: external Harbor is still a tentative preference, and successful image pulls alone do not prove image approval, credential isolation or an agreed support service.
Demonstrate observability from local collection to central ACM roll-up, log access, audit forwarding to external Splunk and an actionable alert handoff. Tenant queries and exports must not expose other tenants or provider internals. Verify collection-outage handling rather than assuming a central dashboard proves completeness. Runtime outbound flows must follow the organizational egress contract. Public application acceptance includes the existing NetScaler request/approval and completion handoff, not a presumed automated appliance change.
Establish the applicable BIO2 baseline, organizational interpretation, relevant security frameworks and assessment scope with the responsible roles. Trace each applicable requirement to an architecture response, implementation responsibility and verification evidence. Record inherited controls and their service boundaries; a link to a policy is not implementation evidence. Unassessed requirements must remain visible, and a recorded exception must not be presented as satisfying a requirement. No authoritative BIO2 source has been assessed for this proposal.
Tenant application and lifecycle checks
The first service includes tenant GitOps. Test that a tenant-controlled repository cannot cause privileged reconciliation against another tenant or provider-reserved resources. Provider GitOps qualification is not evidence for this separate application-delivery boundary.
Hosted tenant API publication through MetalLB on MCE and ingress on tenant workers need a supported configuration and explicit permitted/denied paths. VLAN/VRF naming or fabric presence is not private-access enforcement. Qualify the converged physical path and failure behaviour against the role-specific NIC configurations, including qualification of the reported E810 bandwidth workaround and its operating limits. Permanent remediation remains required, high-priority follow-up, not a Phase 1 acceptance prerequisite. Do not apply the earlier blanket two-100G description to the Ceph 400Gb adapters or treat nominal port rates as measured aggregate throughput. MCE's own API remains on the installer-established API VIP/keepalived arrangement; qualify its startup, failover and recovery rather than promise a MetalLB handover. Ceph-side quotas need interface-specific tenant mapping and enforcement; test the organizational storage-service approval and completion handoff for increases. Tenant-local GitOps must restrict repositories to organizational GitLab and retain provider-reserved controller privileges despite tenant administrative access.
Test the active-active two-interface/leaf-pair arrangement under representative failures. Tenant Argo CD administration and authorized Operator installation must not enable indirect changes to provider-managed components. A curated marketplace is a stretch goal, but those protection checks are not deferred: reject Operator privileges incompatible with the protected platform boundary. Obtain and test against the applicable organizational image-trust policy; no signature or scanning requirement is fabricated in its absence.
Prove that ExternalDNS and Infoblox delegation let a tenant control its own subzone without changing a parent zone, another tenant or provider records. Include onboarding and retirement handoffs, not only a successful record write. The external-secrets pattern must not let tenant resources retrieve provider secrets. Qualify separate direct tenant OpenBao access and the provider controller's own identity and destination controls.
Operational handover
Round 2 on 2026-10-12 confirms the seven core engineers are dedicated to platform development, with other-team storage and IAM/security/PKI participation still unquantified and networking concentrated in one engineer. Production remains with a separate operations team; its participation and handover acceptance are not supplied by the development team's dedication. Plan for reduced December productivity and the proposer's beginning-of-March platform-readiness aim, preserving the fixed 31 March first-production target. Exact dates, capacity, buffers and receiving-team commitments remain open; criteria and handover should not wait until March's end.
Production is assigned to a separate operations team, not automatically to the seven development engineers. Identify the actual team and per-service boundary, required access/skills, runbooks, monitoring and incident handoff, upgrade and recovery responsibilities, external-service escalation and handover evidence. Define who accepts operational readiness. Support hours, response commitments and staffing remain unagreed; a named team type or successful build proves none.
Approved complete retirement must cover the full service exit, including stopping reconciliation, revoking scoped access, external-service handoffs and policy-governed data/backup disposition. Verify that shared assets survive and retained records remain under their agreed controls. A successful cluster-delete command is not complete retirement evidence.
The requested persistent wildcard-validation path needs qualification against the actual CA and cert-manager Operator/client release. The bounded DNS-PERSIST-01 research records the now-confirmed method and current evidence limits. A CA announcement or standards permission is not a demonstrated client integration. Any DNS-01 contingency will be decided after qualification; do not silently weaken validation or select a different challenge to declare the certificate work complete. The existing external OpenBao service is the intended internal PKI source; its actual issuing authority, roles and trust distribution still need evidence.
Why this is on the roadmap
The first-production milestone needs a defensible basis for deciding that the bounded service can be used. A functioning cluster or a forecast finish date cannot supply that basis. Criteria should be developed alongside architecture and implementation, not postponed until the final week. This proposed item does not force all assurance work to follow a sequential documentation phase.
Evidence still needed
Record the agreed criteria, applicable requirement references, acknowledged responsibilities, the environment/configuration covered by each demonstration, results and unresolved conditions. No evidence is invented to fill the roadmap. Once scope and ownership are clear, estimate the engineering effort and elapsed duration separately in this note's delivery block.
The proposer reports that implementation work is already at varying completion stages. Reconcile that evidence in a later dedicated pass rather than treating draft/proposed records as a verified zero-progress baseline. The reported dedicated team of seven OpenShift engineers establishes team size, not completed controls, per-outcome ownership, effective allocation or guaranteed throughput.
Explore this note’s relationships 14 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (15)
- OpenShift GitOps — tenant application deliverySBB · draft · Automation. Icon: Automation
- Persistent DNS validation for public certificatesResearch · draft · Certificates. Icon: Certificates
- CLaaS effort assessmentNote · draft · CLaaS. Icon: General note
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — Clusters-as-a-Service: first production offeringNote · draft · CLaaS. Icon: General note
- Establish CLaaS production acceptance and assuranceNote · draft · CLaaS. Icon: General note
- Approved complete tenant retirementNote · draft · CLaaS. Icon: General note
- Datacenter hardwareNote · draft · Hardware. Icon: General note
- ExternalDNS — provider-managed DNS integrationSBB · draft · Network. Icon: Network
- NetScaler — existing external application perimeterSBB · draft · Network. Icon: Network
- Tenant workload egress — organizational serviceNote · draft · Network. Icon: Network
- CLaaS observability — local stacks and central visibilityNote · draft · Observability. Icon: General note
- Representative non-production qualification environmentNote · draft · Platform. Icon: Platform
- Tenant application images — external Harbor candidateNote · draft · Registry. Icon: Registry
- External-secrets — platform workload secret deliverySBB · draft · Secrets. Icon: Secrets
Relationships (16)
- CLaaS effort summaryReferences →Establish CLaaS production acceptance and assuranceCLaaS/effort-summary.md · Markdown link
- CLaaS — Clusters-as-a-Service: first production offeringReferences →Establish CLaaS production acceptance and assuranceCLaaS/index.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →OpenShift GitOps — tenant application deliveryCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Persistent DNS validation for public certificatesCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →CLaaS effort assessmentCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →CLaaS — Clusters-as-a-Service: first production offeringCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Approved complete tenant retirementCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Datacenter hardwareCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →ExternalDNS — provider-managed DNS integrationCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →NetScaler — existing external application perimeterCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Tenant workload egress — organizational serviceCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →CLaaS observability — local stacks and central visibilityCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Representative non-production qualification environmentCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Tenant application images — external Harbor candidateCLaaS/production-assurance.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →External-secrets — platform workload secret deliveryCLaaS/production-assurance.md · Markdown link
- Representative non-production qualification environmentReferences →Establish CLaaS production acceptance and assurancePlatform/qualification-environment.md · Markdown link