Representative non-production qualification environment
Effort scenario: qualification-environment#substrate
Workstream: Foundations. Provisional remaining engineering hours under the hours convention, based on reported dev progress and the separate-production-build decision in round 2.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Reconcile existing dev topology, capacity and external test allocations | 4 | 16 | 32 |
| Review/adapt separate identities, networks, storage scopes and test data | 8 | 16 | 40 |
| Check destructive-test boundary and restore/cleanup authority | 4 | 8 | 16 |
| Allocation evidence and team handoff | 4 | 8 | 16 |
Reassessed on 2026-10-12, crediting the reported existing development estate. Sizing confidence: low until actual allocation and isolation evidence is reviewed. Low assumes reusable resources and test interfaces; working allows bounded permission/allocation corrections. High allows revised allocations and separation rework, not another installation. Hours include specialist review. Service queues can dominate elapsed time and are excluded. A production-shared dependency must be explicitly isolated or excluded from destructive testing; a new namespace alone is insufficient.
Effort scenario: qualification-environment#representative
Workstream: Assurance and operations. Conditional hours; this is environment acceptance, not installation or the whole test campaign.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Compare built provider/tenant topology with production intent | 8 | 16 | 32 |
| Establish fixtures, observation points and test reset procedure | 8 | 16 | 32 |
| Resolve fidelity gaps and permitted-scenario coverage | 8 | 24 | 48 |
| Record limitations and authorize campaign handoff | 4 | 8 | 16 |
Sizing confidence: medium once the estate exists. Evidence must state which capacity, failure and integration claims the lab cannot support. Role installation and controller configuration are counted in their owning outcomes. High allows a second representativeness review, not an unpriced additional estate. Acceptance waiting time is outside the hours.
The proposer selects a separate representative non-production environment for provisioning, upgrade, recovery and tenant-isolation qualification before production acceptance. The existing development estate may satisfy this requirement, subject to fidelity, allocation and safe-test review; a second non-production estate is not silently added.
Agree which provider roles, hosted-control-plane/worker topology and external interfaces must be represented. Scale may differ only where the acceptance scenario remains meaningful; document differences and the tests they cannot support. Do not claim capacity or failure-domain evidence from an undersized lab.
Establish infrastructure allocation, access, test identities/data, cleanup and recovery arrangements. Separate cluster names do not prove safe isolation from production credentials, networks, storage or consumed organizational services. Destructive recovery and isolation tests require an authorized boundary even in non-production; this note does not authorize them on existing live systems.
Allocated test substrate
The 2026-10-20 hardware clarification places development and the eventual end-of-Q1-2027 production offering on the same 64-node AM4 estate, not two physical estates. The separate non-production test boundary below is not a claim of additional hardware or confirmed concurrent capacity. Host allocation, safe coexistence or transition windows remain open; the existing qualification scope and estimates are unchanged.
The substrate outcome reserves the non-production compute/network/storage scope,
external-service test interfaces, authorized access and safe test data. It precedes
initial installation, without requiring the completed clusters it will host.
Availability and counts have not been verified. Allocation waiting time is not
engineering effort and is not modelled as a made-up technical predecessor.
Representative environment acceptance
The representative outcome documents the actual installed topology, differences
from production, permitted tests and the evidence those differences cannot supply.
Provider bootstrap and role-specific outcomes own installation in each agreed
estate; this outcome does not price another copy of those deployments. It gates
the final acceptance campaign, not early test design or isolated component tests.
No resources are provisioned by recording these outcomes.
Reported progress and remaining qualification
In clarification round 1 on 2026-10-12, the proposer reports a development environment containing Global Hub, MCE, Virtualization and DCS clusters, able to deploy HCP tenant clusters in the intended split topology. This is reported progress, not an inspected inventory, test report or accepted production replica. No configuration revision, host count, allocation or safe-test authority was supplied.
Identify whether this estate is the qualification environment, document differences from production, and establish separate identities/storage/network scopes and approved test interfaces. The unchanged representative-acceptance range covers fidelity review and evidence, not another installation. The intended few-dozen-tenant scale must inform capacity and test coverage; one tenant does not prove fleet capacity.
Round 2 confirms a separate production build, retaining dev rather than promoting
its resources. Allocation/safe-test review of the existing dev estate is now the
identified remainder for substrate: the 20/48/104 h range has remaining-work basis
and low confidence, grounded in the proposer's reports rather than inspected assets.
Representative acceptance stays conditional until fidelity and test scope are known.
Reported unrun scenarios include leaf/link/node loss, upgrades, storage interruption,
identity failure and restores; limited worker-replacement tests do not replace them.
Explore this note’s relationships 10 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (11)
- CLaaS effort assessmentNote · draft · CLaaS. Icon: General note
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — Clusters-as-a-Service: first production offeringNote · draft · CLaaS. Icon: General note
- CLaaS platform design — service planes, hosting and failure boundariesHLD · draft · CLaaS. Icon: General note
- Establish CLaaS production acceptance and assuranceNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- Datacenter hardwareNote · draft · Hardware. Icon: General note
- Hosted control planes — CLaaS cluster realizationSBB · draft · Platform. Icon: Platform
- OpenShift platform baselineSBB · draft · Platform. Icon: Platform
- Representative non-production qualification environmentNote · draft · Platform. Icon: Platform
- SAK applicability and control allocation for CLaaSNote · draft · Security. Icon: General note
Relationships (11)
- CLaaS effort summaryReferences →Representative non-production qualification environmentCLaaS/effort-summary.md · Markdown link
- CLaaS — Clusters-as-a-Service: first production offeringReferences →Representative non-production qualification environmentCLaaS/index.md · Markdown link
- CLaaS platform design — service planes, hosting and failure boundariesReferences →Representative non-production qualification environmentCLaaS/platform-design.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Representative non-production qualification environmentCLaaS/production-assurance.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Representative non-production qualification environmentCLaaS/roadmap.md · Markdown link
- OpenShift platform baselineReferences →Representative non-production qualification environmentPlatform/openshift-platform.md · Markdown link
- Representative non-production qualification environment
· qualification-environment#representativeDepends on →Hosted control planes — CLaaS cluster realization· hosted-control-planesPlatform/qualification-environment.md · features.representative.depends_on: hosted-control-planes - Representative non-production qualification environmentReferences →CLaaS effort assessmentPlatform/qualification-environment.md · Markdown link
- Representative non-production qualification environmentReferences →Establish CLaaS production acceptance and assurancePlatform/qualification-environment.md · Markdown link
- Representative non-production qualification environmentReferences →Datacenter hardwarePlatform/qualification-environment.md · Markdown link
- SAK applicability and control allocation for CLaaSReferences →Representative non-production qualification environmentSecurity/sak-assurance.md · Markdown link
Features of this note
2 features declared in this note's metadata. Each is one capability with its own section. Readiness is the author's dated assessment for the scope it names; delivery is the next increment of work. The two are independent, and nothing here combines them across features or implies approval.
Allocated non-production test substrate
qualification-environment#substrate- Section
- Allocated test substrate
- Readiness
- Not assessed No readiness assessment is written in the source; this is not the same as ready.
- Next delivery
- Unknown: not reconciled in the source, so no dates are forecast.
- Effort estimate
- 48 h working · 20–104 h · Remaining work; low confidence; assessed 12 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
Representative qualification environment acceptance
qualification-environment#representative- Readiness
- Not assessed No readiness assessment is written in the source; this is not the same as ready.
- Next delivery
- Unknown: not reconciled in the source, so no dates are forecast.
- Effort estimate
- 64 h working · 28–128 h · Conditional completion; low confidence; assessed 11 Oct 2026. Estimate assumptions
- Depends on
- Allocated non-production test substrate
qualification-environment#substrate, Hosted control planes — CLaaS cluster realizationhosted-control-planes - Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)