Local drafting workspace

OpenShift platform baseline

Platform/openshift-platform.md

Local draft — not saved or submitted. Download and use the Git/PR workflow. Changes stay in this page’s memory, never alter the published note, and are lost on reload. The .md download contains the narrative only; preserve the original frontmatter in Git. The preview is not publication validation.

Preview

Images and raw HTML are disabled. Preview links do not navigate. Markdown links are checked when the source is built, not here.

Published source loaded. No local changes.

View source & provenance

Effort scenario: openshift-platform

Workstream: Foundations. Conditional hours, not a measured remainder; basis and exclusions.

Work package Low h Working h High h
Combined release/entitlement and host inventory suitability matrix 16 40 80
Four-role resource, persistence and installation design 16 32 64
Reusable manifests, time/DNS/trust/image input contracts 16 40 72
Design review, unresolved decisions and installer acceptance criteria 8 16 32

Sizing confidence: low until versions and host inventory are confirmed. This is common design/compatibility work counted once, not runtime qualification of all roles. Includes NTP/time-source access, bootstrap image allowlist and basic host allocation evidence that were implicit before. New procurement, firmware remediation or a redesigned supported topology must be estimated separately. Service approvals and vendor response time are not hands-on duration.

Service Information

This proposed SBB is the shared OpenShift baseline, not another cluster and not evidence that any cluster is installed. The assignment specifies external Ceph storage and an EVPN/VXLAN network for every OpenShift platform. Those common contracts are recorded here once; the individual cluster-role notes reference this baseline and explain what they add.

The concrete roles are the ACM and Global Hub cluster, MCE management cluster, Virtualization worker-hosting cluster, and Datacenter Services Cluster. A hosted tenant cluster is an OpenShift consumer too, but its control plane and workers are placed through HCP, not by provisioning another copy of a standalone control-plane cluster.

The assignment reports existing network and compute hardware available for reuse. This is the planning starting point, not a verified inventory or a claim that capacity, firmware, feature support and failure-domain placement are suitable. No new procurement dependency has been identified yet; any gap found during qualification must be made explicit rather than hidden inside a configuration estimate.

Roadmap and Lifecycle

In clarification round 1 on 2026-10-12, the proposer reports the four-role dev estate can deploy HCP tenants in the intended topology, with existing platform-team RBD/authentication automation. No host inventory, configuration revision, deployed release matrix or support decision was supplied or inspected. These are inputs to reuse review, not proof that the common production baseline is complete.

The intended initial operating scale is a few dozen tenants, with control planes on MCE and workers on the separate Virtualization cluster. Exact launch batch, capacity profiles, provider sizing and production/test counts remain open. Retain the 56/128/248 h conditional range for release/support and inventory review, capacity/persistence design, bootstrap inputs and acceptance criteria. It does not count dev installations again. A working tenant does not establish fleet-scale capacity, failure headroom or upgrade support. No actual dates are inferred.

This outcome is the reviewed, implementable common baseline contract, not a completed runtime test on every cluster. It fixes initial disks/persistence, host inventory suitability, release compatibility, bootstrap DNS/time/image/trust paths and network/storage inputs. On-cluster qualification belongs to the bootstrapped roles and feature outcomes. This boundary permits investigation now without making the initial installer wait for its own future in-cluster services.

The delivery outcome is to establish the reusable baseline and independently qualifiable network/storage/bootstrap input contracts. Its estimate covers that shared work once. The provider bootstrap owns initial cluster installation, while the individual role notes own role-specific configuration and validation. Reusing this node does not mean all clusters are deployed for the price or duration of one cluster.

The first offering is at one location with local redundancy. The actual site, failure domains, versions, entitlement, sizing, ownership and estimates remain open. The existing research line is OpenShift 4.22, with ACM 2.17 discussed in the fleet material; these are documentation baselines, not a selected or tested combined release set. Hosted control planes, Virtualization, MCE, CSI and the external Ceph release need an explicit compatibility decision.

The proposer selects latest compatible stable releases as the release-selection rule. Qualify a supported combination of platform, Operators and external interfaces, then pin the accepted versions and controlled upgrade path. This is not permission to follow floating latest releases or choose each component's newest version independently. If compatibility or support requires an older component, record the reason; existing research versions are not automatically the accepted deployment baseline. Use the separate representative qualification environment to establish the relevant evidence before production acceptance.

Architecture

All cluster roles inherit EVPN/VXLAN and external Ceph. The common dependency does not mean they share unrestricted networks, pools, credentials or failure domains. Management/control-plane persistence, VM disks and tenant PVCs have different consumers and support requirements; upstream ceph-csi qualification for one is not proof for the others.

Keycloak is the proposed common human identity and authentication service. Platform and application authorization remain local responsibilities. OpenBao is consumed externally for the first phase. Bootstrap and recovery must not require an unavailable cluster, its own future DCS-hosted secrets store or its ordinary SSO path. Keycloak is now placed on DCS following external bootstrap; the initial bootstrap identity, access handover and emergency access still need explicit design; the absence of a scheduling edge is not proof of independent operation.

The roadmap's prerequisites gate the qualified baseline, not the start of design discussion. Each finished service role still needs its configured identity, operational and recovery acceptance; this shared delivery state does not grant production acceptance to its consumers.

Physical hardware layer

The servers under every role are covered by the datacenter hardware note, reported as procured on 2026-10-13. The qualified baseline waits for that note's acceptance milestone: BMC management, role-appropriate firmware and OneView enrolment for the hosts it selects. This gates the baseline's host-suitability conclusion, not design work, and it does not require reinstalling the reported dev estate. Hardware budgets are counted in the hardware note, not in this note's range. The 19 October hardware role profiles now supply server models and component configurations. The 20 October report adds 24 Control, 24 Worker, 8 Ceph and 8 GPU nodes per datacenter, across four racks, with AM4 as the first Phase 1 site. Allocation to the individual provider clusters and to production/dev, plus rack/port mapping, remain open. The proposer confirms that this same hardware supports development and the eventual production offering targeted for end of Q1 2027, not a second physical estate. This does not change the separate-production-build plan or establish concurrent capacity, a transition method or production acceptance. Delivery, racking and network patching are reported complete, not accepted firmware or host suitability. The reported E810-CQDA2 issue may require replacement; its scope and timing are unestimated and are not hidden in this baseline's existing range or the OneView budgets.

Evidence and next detail

The topology is the assignment's 2026-10-09 proposal, not a live observation. OpenShift 4.22 HCP overview, sections 2.1–2.4 was consulted on that date for separation of control-plane/data-plane roles and MCE/ACM responsibilities. Product requirements, deployment details and tests are deliberately left for the next iteration; no HLD or LLD is claimed by this SBB.

Explore this note’s relationships 21 connected notes

Connections are authored references and declared relationships, not verified runtime dependencies or approval.

22 notes · 44 relationships

Every note and relationship is available in the list below. The interactive map requires JavaScript.

Outline is the note kindABBSBBHLDResearchNoteMarkdown referenceTyped relationship
Icon is the documented subjectIdentityNetworkStorageCertificatesFleetPlatformSecretsGeneral note
Notes and relationships Accessible list

Notes (22)

Relationships (44)

Source & provenance

This is the published reading view. The Markdown source and Git review workflow remain authoritative; publication is not architectural approval.

Source
Platform/openshift-platform.md
Identifier
openshift-platform
Kind
Solution building block
Status
Draft, as authored
Revision
a3203210221340f80866b0462f4d63b49ebc5aea

Review not recorded. A recorded review date is the author’s review of the whole note, not an edit date, build date or approval. Editing a local draft does not update it.

Read the Markdown source

Read-only narrative source. Authored labels and relationships are listed above; this view does not write to the vault.


# OpenShift platform baseline

## Effort scenario: openshift-platform

**Workstream:** Foundations.
Conditional hours, not a measured remainder; [basis and exclusions](../CLaaS/effort-assessment.md#scenario-boundary-and-counting-rules).

| Work package | Low h | Working h | High h |
| --- | ---: | ---: | ---: |
| Combined release/entitlement and host inventory suitability matrix | 16 | 40 | 80 |
| Four-role resource, persistence and installation design | 16 | 32 | 64 |
| Reusable manifests, time/DNS/trust/image input contracts | 16 | 40 | 72 |
| Design review, unresolved decisions and installer acceptance criteria | 8 | 16 | 32 |

Sizing confidence: low until versions and host inventory are confirmed. This is
common design/compatibility work counted once, not runtime qualification of all
roles. Includes NTP/time-source access, bootstrap image allowlist and basic host
allocation evidence that were implicit before. New procurement, firmware remediation
or a redesigned supported topology must be estimated separately. Service approvals
and vendor response time are not hands-on duration.

## Service Information

This proposed SBB is the **shared OpenShift baseline**, not another cluster and
not evidence that any cluster is installed. The assignment specifies external
Ceph storage and an EVPN/VXLAN network for every OpenShift platform. Those common
contracts are recorded here once; the individual cluster-role notes reference
this baseline and explain what they add.

The concrete roles are the [ACM and Global Hub cluster](../Fleet/acm-global-hub.md),
[MCE management cluster](../Fleet/mce-management-cluster.md),
[Virtualization worker-hosting cluster](openshift-virtualization.md), and
[Datacenter Services Cluster](datacenter-services-cluster.md). A hosted tenant
cluster is an OpenShift consumer too, but its control plane and workers are
placed through [HCP](hosted-control-planes.md), not by provisioning another copy
of a standalone control-plane cluster.

The assignment reports existing **network and compute hardware available for
reuse**. This is the planning starting point, not a verified inventory or a claim
that capacity, firmware, feature support and failure-domain placement are suitable.
No new procurement dependency has been identified yet; any gap found during
qualification must be made explicit rather than hidden inside a configuration estimate.

## Roadmap and Lifecycle

In clarification round 1 on **2026-10-12**, the proposer reports the four-role dev
estate can deploy HCP tenants in the intended topology, with existing platform-team
RBD/authentication automation. No host inventory, configuration revision, deployed
release matrix or support decision was supplied or inspected. These are inputs to
reuse review, not proof that the common production baseline is complete.

The intended initial operating scale is a few dozen tenants, with control planes
on MCE and workers on the separate Virtualization cluster. Exact launch batch,
capacity profiles, provider sizing and production/test counts remain open. Retain
the 56/128/248 h conditional range for release/support and inventory review,
capacity/persistence design, bootstrap inputs and acceptance criteria. It does not
count dev installations again. A working tenant does not establish fleet-scale
capacity, failure headroom or upgrade support. No actual dates are inferred.

This outcome is the **reviewed, implementable common baseline contract**, not a
completed runtime test on every cluster. It fixes initial disks/persistence, host
inventory suitability, release compatibility, bootstrap DNS/time/image/trust paths
and network/storage inputs. On-cluster qualification belongs to the bootstrapped
roles and feature outcomes. This boundary permits investigation now without
making the initial installer wait for its own future in-cluster services.

The delivery outcome is to establish the reusable baseline and independently
qualifiable network/storage/bootstrap input contracts. Its estimate covers that shared
work **once**. The [provider bootstrap](provider-bootstrap.md) owns initial
cluster installation, while the individual role notes own role-specific
configuration and validation. Reusing this node does not mean all clusters are
deployed for the price or duration of one cluster.

The first offering is at one location with local redundancy. The actual site,
failure domains, versions, entitlement, sizing, ownership and estimates remain
open. The existing research line is OpenShift **4.22**, with ACM **2.17** discussed
in the fleet material; these are documentation baselines, not a selected or
tested combined release set. Hosted control planes, Virtualization, MCE, CSI and
the external Ceph release need an explicit compatibility decision.

The proposer selects **latest compatible stable releases** as the release-selection
rule. Qualify a supported combination of platform, Operators and external
interfaces, then pin the accepted versions and controlled upgrade path. This is
not permission to follow floating latest releases or choose each component's
newest version independently. If compatibility or support requires an older
component, record the reason; existing research versions are not automatically
the accepted deployment baseline. Use the
[separate representative qualification environment](qualification-environment.md)
to establish the relevant evidence before production acceptance.

## Architecture

All cluster roles inherit [EVPN/VXLAN](../Network/evpn-vxlan.md) and
[external Ceph](../Storage/external-ceph-csi.md). The common dependency does not
mean they share unrestricted networks, pools, credentials or failure domains.
Management/control-plane persistence, VM disks and tenant PVCs have different
consumers and support requirements; upstream ceph-csi qualification for one is
not proof for the others.

[Keycloak](../Identity/keycloak.md) is the proposed common human identity and
authentication service. Platform and application authorization remain local
responsibilities. [OpenBao](../Secrets/openbao.md) is consumed externally for
the first phase. Bootstrap and recovery must not require an unavailable cluster,
its own future DCS-hosted secrets store or its ordinary SSO path. Keycloak is now
placed on DCS following external bootstrap; the initial bootstrap identity,
access handover and emergency access still need explicit design;
the absence of a scheduling edge is not proof of independent operation.

The roadmap's prerequisites gate the qualified baseline, not the start of design
discussion. Each finished service role still needs its configured identity,
operational and recovery acceptance; this shared delivery state does not grant
production acceptance to its consumers.

### Physical hardware layer

The servers under every role are covered by the
[datacenter hardware note](../Hardware/datacenter-hardware.md), reported as
procured on **2026-10-13**. The qualified baseline waits for that note's acceptance
milestone: BMC management, role-appropriate firmware and OneView enrolment for
the hosts it selects. This gates the baseline's host-suitability conclusion, not
design work, and it does not require reinstalling the reported dev estate.
Hardware budgets are counted in the hardware note, not in this note's range.
The **19 October** [hardware role profiles](../Hardware/datacenter-hardware.md#reported-node-role-configurations)
now supply server models and component configurations. The **20 October** report
adds **24 Control, 24 Worker, 8 Ceph and 8 GPU nodes per datacenter**, across four
racks, with **AM4** as the first Phase 1 site. Allocation to the individual
provider clusters and to production/dev, plus rack/port mapping, remain open.
The proposer confirms that this **same hardware** supports development and the
eventual production offering targeted for **end of Q1 2027**, not a second physical
estate. This does not change the separate-production-build plan or establish
concurrent capacity, a transition method or production acceptance. Delivery,
racking and network patching are reported complete, not accepted firmware or
host suitability. The reported [E810-CQDA2 issue](../Hardware/datacenter-hardware.md#intel-e810-cqda2-bandwidth-issue)
may require replacement; its scope and timing are unestimated and are not hidden
in this baseline's existing range or the OneView budgets.

### Evidence and next detail

The topology is the assignment's **2026-10-09 proposal**, not a live observation.
[OpenShift 4.22 HCP overview, sections 2.1–2.4](https://docs.redhat.com/en/documentation/openshift_container_platform/4.22/html/hosted_control_planes/hcp-overview)
was consulted on that date for separation of control-plane/data-plane roles and
MCE/ACM responsibilities. Product requirements, deployment details and tests are
deliberately left for the next iteration; no HLD or LLD is claimed by this SBB.