EVPN/VXLAN network fabric
Effort scenario: evpn-vxlan
Workstream: Foundations. Zero-additional-work Phase 1 acceptance milestone, revised 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| No additional work beyond the owning Phase 1 feature increments | 0 | 0 | 0 |
The earlier 72/184/336-hour conditional aggregate is superseded, not retained or added again. The reduced scope has three proposed feature budgets totalling 80 engineering hours / 80 scheduling hours. Firmware is reported complete in AM4; its supplied 40/40-hour point is historical budget context, not future work or measured actual effort. The new Cisco Nexus Dashboard service is a separate item with its own 40/40-hour feature budgets, not hidden in the integration budget. The milestone retains the existing DNS/IPAM consumer contract. It adds no duplicate engineering or duration, and a successful plan/build is not architectural approval.
Summary
This draft defines the network-fabric capability proposed for the first CLaaS offering: provide controlled connectivity and separation for HCP management, tenant workers and the supporting services they consume. On 2026-10-17, the proposer deliberately reduces Phase 1 to the basics for short-term feasibility: firmware, VRF separation/details, 100 pre-provisioned VLANs and integration into a new fabric orchestration service. Firmware is reported installed in AM4, with basic configuration that allows VLAN provisioning. VRFs are assumed configured, but their details are not yet available. These are reported progress, not inspected versions, proven isolation or accepted reliability.
Quanza owns all four feature outcomes in Networking. The aggregate delivery and three pending increments are proposed; completed firmware and DCM are available capabilities with no fictitious future increments or invented finish dates.
EVPN supplies a BGP-based control plane for network virtualization; VXLAN is an overlay encapsulation over IP. RFC 8365 describes their combination, including multihoming and interconnection mechanisms (N1). Those standards are a useful interoperability basis, not proof that a particular device combination or configuration delivers the desired tenant service.
Capabilities
The four-feature Phase 1 scope below is the delivery selection. The following broader design concerns remain architectural context, not additional promised features or work silently included in the new 80-hour budget. Required tenant, platform and storage separation remains part of the VRF outcome; wider MTU, congestion, failure/recovery qualification and full automation coverage are not claimed complete or priced by this reduced feature list.
| Concern | Proposed first-offering outcome | What still needs deciding |
|---|---|---|
| Underlay and attachments | Predictable IP reachability between the selected fabric endpoints and server attachments | Physical redundancy, routing design, addressing, device/release combination and failure domain |
| Tenant and management separation | Explicit permitted and denied paths between management, tenant and shared-service scopes | VRF/VNI allocation, gateways, route import/export and separate firewall/policy enforcement |
| CLaaS interfaces | Reachability for hosted control-plane endpoints, workers, ingress/egress and required shared services | API exposure/load-balancing contract, routing handoffs, DNS and responsibility at each boundary |
| Storage path | The consuming nodes can reach the authorized external Ceph services without exposing unrelated storage access | Endpoint paths, segmentation, capacity, latency and contention limits for the selected storage design |
| Packet transport | End-to-end packet sizes and forwarding work for the selected host and cluster networking | Underlay MTU and combined encapsulation overhead, including any cluster overlay; IPv4/IPv6 scope |
| Controlled change | An owned, repeatable configuration path with scoped access, review and drift visibility | Controller/API choice, authoritative intent, reconciliation ownership and emergency-change procedure |
| Failure and operations | Observable forwarding and tested recovery appropriate to the first service promise | Link/device failures, maintenance, control-plane/controller outage and measurable convergence criteria |
EVPN segmentation is not by itself encryption or application authorization. Route-policy mistakes can cross intended boundaries; N1 section 11 identifies misrouting/misdelivery risks from modified tunnel/control information. Allocate and verify the actual security controls against the applicable requirements, including denied-path tests, rather than infer BIO2 compliance from VRFs or VNIs.
Constraints
In clarification round 1 on 2026-10-12, the proposer reports initial EVPN/VXLAN firmware/configuration on the switches and a couple dozen statically pre-provisioned VLANs available to consume. The rest of the setup and final design are not known. No device/release inventory, configuration revision, isolation, MTU or failure-test evidence was supplied or inspected. This is reported progress, not a blank fabric; VLAN availability does not establish tenant isolation or host-attachment readiness.
The 17 October agreement supersedes the broad 72/184/336-hour estimate with the explicit feature budgets below. The older couple-dozen-VLAN report is not evidence that the new 100-VLAN target is available. Do not infer one VLAN per tenant, complete isolation or a numerical completion percentage. Existing firmware is credited as complete only for AM4; no other site's firmware is marked ready.
Round 2 on 2026-10-12 reports leaf/link or node loss has not been tested. Those test gaps remain explicit. The reduced scope does not establish resilience or absorb the former broad qualification package into 80 hours. If required service acceptance needs additional failure/MTU/scale work, allocate and estimate that work explicitly rather than claim it done or silently weaken the boundary. Networking within the core team is concentrated in one engineer with networking familiarity, not a confirmed dedicated network-specialist allocation. Network-team involvement, final design ownership and change windows remain to identify; staffing contention is not a new technical dependency edge.
The assignment reports existing network hardware available for the March scope, which is one location with local redundancy. Treat that as the starting inventory assumption, not proof of configured EVPN/VXLAN, sufficient capacity or a supported feature set. The actual devices, releases, allocation and failure cases still need qualification. No new hardware procurement dependency is assumed without an identified gap.
The earlier proposer description was two 100G physical interfaces per bare-metal node, carrying VLAN-separated traffic in an active-active bond to a redundant leaf pair. The 19 October hardware profiles now refine that blanket inventory description: Control, Worker and GPU roles list one E810-CQDA2 dual-port 100Gb adapter, while Ceph lists two single-port 400Gb InfiniBand NDR/Ethernet adapters. Actual mode, negotiated speed and role-specific switch/bond compatibility remain unconfirmed; the label is not achieved throughput. The proposer reports that the E810 card cannot provide the required true 200 Gbit/s through-card bandwidth and probably needs replacement. The NIC issue has no selected replacement or estimated lead time. It does not reopen completed AM4 switch firmware or DCM work. Qualify actual compatibility, failure behaviour, capacity and contention; neither a port count nor the word redundant proves usable aggregate capacity or independent failure domains.
The 17 October report assumes VRFs have been configured, but supplies no details. Allocation, routing interaction and security enforcement are therefore not established. The VRF increment must explain how VLANs, VRFs and actual filtering protect management and tenants on the converged physical path. Qualify contention and link/device failures across storage and other traffic; logical separation alone does not provide independent physical capacity or trust.
Keep the physical fabric distinct from the Kubernetes cluster network. This proposal does not replace the CNI or prescribe that the tenant cluster's overlay must use the same encapsulation as the datacenter fabric. The selected OpenShift, HCP, NIC, switch and storage configurations need a combined support and integration assessment. Address/IPAM authority, privilege boundaries and approved change ownership are prerequisites to safe automation, not benefits obtained merely by installing a controller.
Service Description
The network provider supplies the agreed connectivity and separation contract; the CLaaS provider owns its cluster-side integration and tenant-facing promise. Network operations, platform operations and tenant responsibilities must agree on where each path is diagnosed and restored. On 2026-10-14 the proposer assigns networking work, including this fabric and its DCM feature, to the Networking domain, with its own architects. Detailed network design belongs there; the CLaaS team specifies its consumer requirements and acceptance paths. The 17 October agreement names Quanza as owner of all four Phase 1 fabric features. The individual architect, service operator for Cisco Nexus Dashboard and formal acceptance authority remain unrecorded. Networking is an explicit domain assignment, not inferred from the subject folder. DCM is already reported complete; the new feature points replace the broad fabric range.
Roadmaps
The delivery block is now a zero-additional-work Phase 1 milestone over the three pending increments. The explicit order is firmware → VRF setup/details → 100 pre-provisioned VLANs → orchestrator integration, with VRF and VLAN order swapped from the proposer's initial list as explicitly requested. All four feature outcomes are Quanza-owned. The firmware capability is already available in AM4, so VRF work references it architecturally rather than waiting on new firmware work. The next increments each depend on the previous pending outcome; integration also requires the separately available orchestrator service. No parent/child cycle is introduced, and DCM/IPMI consumption is not gated on this new automation foundation.
The three proposed durations total 80 scheduling hours (ten working days) under the existing eight-hour weekday convention, only after their inputs and external service availability are satisfied. They are not dates or a resource-levelled commitment. The old aggregate and the completed firmware 40/40 are not added again.
Broader multisite overlays, stretched Layer 2, additional tenant patterns and fully self-service network provisioning are candidates for later scope unless the first consumer's requirements make them necessary. First-release deferrals must preserve required isolation, availability and recovery. A controlled operator-assisted workflow may be considered instead of full automation; it still needs review, repeatability, ownership and an auditable result.
EVPN/VXLAN firmware installation
Outcome and owner: Quanza installs the EVPN/VXLAN firmware baseline on the in-scope switches. The proposer reports this already completed in AM4 on 2026-10-17, and reports basic configuration that permits VLAN provisioning. No actual completion date, switch inventory or installed release was supplied. Readiness is therefore recorded for AM4 only, on the basis of the report, not a tested support matrix or proof that another site has the same baseline.
The supplied 40 engineering / 40 scheduling hours are the feature's budget,
not measured effort spent. There is no next firmware increment planned for
this reported-complete scope, so no delivery block or invented actual finish
is added. VRF work consumes this available capability. Its conservative 17
October earliest start prevents planning before the confirmation boundary;
that is not the firmware installation date. Another site or later firmware change
would need its own explicit scope and readiness, not an assumed AM4 result.
VRF setup and separation details
Outcome and owner: Quanza establishes and documents the required tenant, platform and storage traffic separation, including VRF allocation, VLAN mapping, permitted routing/handoffs and where filtering enforces the boundary. The proposer assumes VRFs are configured but has no details yet. Existing configuration may be reusable; it is not accepted isolation evidence or a completed increment.
Acceptance needs a usable description of the actual boundaries and confirmation that the required paths work while unauthorized cross-boundary traffic is refused. A VRF name alone is not an access-control guarantee. The feature remains proposed, with unknown readiness and a supplied 32 engineering / 32 scheduling hours. It consumes the reported-ready AM4 firmware capability; it does not wait for another installation or infer a firmware finish date.
100 pre-provisioned VLANs
Outcome and owner: Quanza makes a set of 100 pre-provisioned VLANs available for the Phase 1 consumers, with their identifiers, permitted use and VRF/traffic boundaries documented. Basic configuration is reported to allow VLAN provisioning; neither that report nor the older couple-dozen-VLAN baseline proves all 100 ready. The number does not imply one VLAN per tenant, 100 tenants or an approved allocation.
The supplied budget is 8 engineering / 8 scheduling hours. Delivery is proposed, with unknown readiness. The proposer explicitly orders this outcome after the VRF setup/details increment. This is a planning sequence, not a claim that a vendor technically forbids creating VLANs earlier. Acceptance checks the full agreed set and its usable consumer mapping, not just the ability to create a single VLAN.
Ceph consumer handoff — 19 October 2026. The proposer confirms that Ceph can be installed and operated when connectivity is established and the pre-provisioned VLANs can be consumed. For that consumer, this existing feature hands over usable host/storage paths within the agreed VRF boundaries, not just a list of VLAN IDs. Required addresses must come from the authorized allocation authority and the permitted paths must work; a VLAN count alone does not prove connectivity. No addressing details or path-test evidence were supplied by this clarification. The handoff remains proposed with unknown readiness, using its existing 8/8-hour budget rather than adding another network task. It does not wait for Nexus Dashboard onboarding. The complete fabric milestone retains its broader DNS/IPAM baseline and orchestration prerequisites; those are not copied into this scoped Ceph start gate. Completed DCM connectivity and AM4 firmware are unchanged.
Integration into the fabric orchestrator
Outcome and owner: Quanza integrates the Phase 1 fabric into the separately available Cisco Nexus Dashboard service. This 40 engineering / 40 scheduling hours covers fabric onboarding and integration, not installing or funding that service a second time. It follows the 100-VLAN outcome and requires the new service to be available. Delivery is proposed and readiness remains unknown.
Acceptance identifies the fabric and configuration baseline in the service, qualifies scoped operator/API access and the intended supported integration path, and records which system owns each configuration value. Git, Nexus Dashboard and manual administration must not become competing writers. This feature demonstrates the actual AM4 onboarding; the service's own Fabric Management and Manage features only enable that function and scoped API access. Exact release, credentials and interfaces remain to detail with the service owner; no supported deployment or working integration is inferred from the product name.
This creates the foundation for future network automation. Any network/fabric automation must consume the available orchestration service first, but full dynamic VLAN self-service or a new tenant-network automation workflow is not silently added to Phase 1. Existing ACM-driven IPMI provisioning and completed DCM connectivity are not retroactively blocked by the new service.
Effort scenario: evpn-vxlan#vrf-setup
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Establish and document the required tenant/platform/storage VRF separation | 32 | 32 | 32 |
Duration: 32 scheduling hours. Low confidence while the assumed existing VRF configuration and its boundaries remain unverified. Equal bounds encode the supplied point, not an independently assessed range or a verified remainder.
Effort scenario: evpn-vxlan#pre-provisioned-vlans
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Make and qualify the agreed set of 100 pre-provisioned VLANs | 8 | 8 | 8 |
Duration: 8 scheduling hours. Low confidence until the 100-VLAN set, consumer mapping and actual remainder are confirmed. This does not count firmware again.
Effort scenario: evpn-vxlan#orchestrator-integration
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Integrate the fabric into the separately available orchestration service | 40 | 40 | 40 |
Duration: 40 scheduling hours. Low confidence until the service, supported interface and actual integration remainder are known. The service's own 40/40-hour setup is budgeted in its own note, not included here.
Landing Locations
The first CLaaS scope is AM4, confirmed on 2026-10-20, retaining one location with local redundancy. Its reported hardware inventory is 64 nodes across four racks; exact host/rack mapping, fabric attachment details and management-platform placement remain unresolved. The rack count does not prove independent failure domains or select a Nexus Dashboard hosting location. Do not infer a stretched fabric or additional location from the end-state ambition. Record the management platform's bootstrap and recovery dependencies separately from the network it will manage.
Available SBBs
The newly required Cisco Nexus Dashboard service has its own SBB and Phase 1 delivery item, in Networking. This is the proposer's service direction, not institutional approval or a verified Cisco SKU. On 2026-10-17 the proposer identifies the product as Cisco Nexus Dashboard, current 4.x line with integrated fabric management, replacing the earlier wrong working name. The previously examined Cisco DevNet documentation distinguishes Nexus Dashboard Fabric Controller (NDFC) legacy interfaces, the unified Manage fabric APIs, and Nexus Dashboard Orchestrator (NDO) orchestration for multisite/multifabric management (N2). In the selected direction, Manage is Nexus Dashboard's API/configuration capability and NDFC a legacy function, not a separate product. NDO and Network Services Orchestrator (NSO) are not this product and are not required in this phase. The exact release remains to select.
The examined documentation calls Infra, Manage, One Manage, Analyze and Orchestration APIs GA from 4.2.1 and describes legacy API deprecation in 4.3.1. The latest non-prerelease CiscoDevNet Ansible NDFC collection observed was 3.13.0, published 2026-08-27, with stated ND 4.3.1 support (N3). That collection release is not a selection of the network-management product, an assurance of latest product GA, or proof of compatibility with our switches. The Cisco product pages returned HTTP 403 during consultation; latest product patch, lifecycle, hardware support and licensing remain unverified. Avoid choosing a legacy API from its familiar name without checking the intended release.
Qualify the selected service against scoped API roles, inventory and fabric onboarding, configuration preview/deployment, repeatability, drift/change handling, failure recovery and the owned integration with automation. Establish which system owns each configuration value; Git-reviewed intent and a controller must not become competing writers. Reliability and operational savings need representative evidence, not the product name alone.
Interfaces
Describe host attachments and L3 handoffs, tenant/shared-service routing, IPAM/DNS allocation, telemetry and the management API separately. The external Ceph proposal needs a verified path from its actual consuming nodes to the required Ceph services. It does not imply that storage replication traffic and tenant traffic share one unrestricted network. The hosting contract owns the integration of these paths with HCP and tenant execution.
DCM network
The DCM (DataCenter Management) network already exists in RWS infrastructure. In RWS notation it is a highly secured network used only to manage critical datacenter infrastructure. The proposer's clarification of 2026-10-14 defines this feature as extending that existing service to the new DC 3.0 switching setup and connecting all server IPMI interfaces to it. It is not a new standalone management-network service. Its consumer scope and progress remain separate from the tenant/platform fabric outcome.
Required outcome. The new EVPN/VXLAN switching setup makes the existing DCM network operationally available to the IPMI interfaces of the datacenter hardware. The consumers are platform engineers accessing server IPMI and the platform accessing IPMI for ACM-driven provisioning. HPE OneView is another management consumer, not a claim that its separately planned enrolment/configuration work is complete.
Design responsibility. This feature belongs to Networking, with detailed design and the handoff to the existing DCM infrastructure owned by that domain's architects and delivery process. The proposer suggests a management VRF with a VLAN connecting the new IPMI interfaces to DCM. This is a design hypothesis, not an approved topology or an implementation instruction. Networking must define the actual attachment, routing, filtering, resilience and controlled recovery access in the design. A VLAN or VRF alone does not establish the secured boundary.
Reported DCM completion — 17 October 2026
The proposer confirms that DCM networking on the EVPN/VXLAN setup is implemented
and complete. Quanza owns completion. This supersedes the 14 October
"mostly done" report and its 16 engineering / 40 scheduling hours of future work.
The scoped network capability is recorded as ready on the basis of this report,
not an independently inspected deployment or security test. No configuration
revision, test report or actual completion date was supplied.
The proposer explicitly confirms that the completion date is unknown. No
start or finish date is inferred from the report date. Capability readiness is
ready, with the dated report as its stated basis, and no next delivery
increment is planned. The optional delivery block is therefore omitted rather
than keeping a fictitious unknown future task or inventing an actual_finish.
Quanza's completion ownership remains recorded here. Consumers retain their
architectural dependency on this capability, but do not wait for new DCM work.
The earlier undated delivery placeholder incorrectly blocked IPMI scheduling and
is superseded by this distinction between available capability and future work.
The access requirement is platform engineers reaching server IPMI and the platform reaching IPMI for provisioning from ACM. "Consumer handoff" means making those network paths usable, not another service, milestone or extra budget. Completion does not mark the broader fabric, IPMI/BMC configuration or OneView enrolment done.
Access boundary. Permit named platform engineers through approved management paths, HPE OneView, and the authorized OpenShift nodes/provisioning identities. The OpenShift path must work from the nodes' bonded 100G interfaces to the IPMI interfaces on DCM. This is scoped infrastructure-management access, not blanket access for tenant workloads or every cluster. Tenant workloads, public networks and general office networks remain refused. Networking must qualify the permitted and denied paths and define controlled emergency access; no security approval or compliance is claimed by this note.
Records and dependencies. Addresses and names remain under the DNS, DHCP and IPAM authority. The proposer expects interfaces to be defined in the DCIM service, identifying NetBox as the intended tool. That record is useful for planning and evidence, but DCIM is neither an architectural nor a delivery prerequisite for this feature. DCM connectivity must not depend on NetBox being available. The separate hardware features retain their own inventory requirements. Addressing is an implementation detail needed by this completed network outcome, not new separately priced DCM work. The architectural address-authority relationship remains; its former DNS/IPAM delivery start gate is removed so confirmation work for other consumers does not retroactively block completed DCM connectivity. The separately budgeted tenant-zone delegation feature is different scope and remains unchanged.
Network acceptance boundary, for all in-scope new server interfaces:
- Platform engineers can manage the new hardware through its IPMI interface over the approved DCM access path.
- The platform has the permitted IPMI network path for ACM-driven provisioning, including the previously described bonded 100G node attachment where used.
- Authorized management consumers have the required network reachability. BMC accounts/settings and OneView provisioning remain separately owned increments.
Retained technical evidence should identify the interface/node scope, configuration baseline and permitted/denied-path results. No such test records were inspected in this clarification; the source is the proposer's completion report. DCM owns the network path; BMC configuration and OneView provisioning work remain owned by the OneView features and referenced by the hardware acceptance milestones. Prepare the necessary test interfaces during integration, without adding a circular gate on completing those hardware features. DCM does not wait for the whole fabric outcome or for a full OneView enrolment milestone.
Planning. Reported completion leaves 0 remaining engineering hours and 0 future scheduling hours for this DCM increment. The earlier 16/40-hour point remains historical estimate context, not measured effort spent or another budget to add. The OneView IPMI budget remains separate. The later 17 October reduced-scope agreement supersedes the broader 72/184/336-hour fabric range; DCM completion does not claim the new VRF/VLAN/integration increments done. The actual finish date remains unknown; this historical gap does not prevent planning consumption of the reported-ready capability.
DCM remaining work and historical estimate
Workstream: Foundations. Remaining-work assessment dated 2026-10-17, based on the proposer's completion report.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| No remaining network work in the reported-complete DCM increment | 0 | 0 | 0 |
Future duration: 0 scheduling hours. The earlier 16 engineering / 40 scheduling hours are superseded, not converted into measured actual effort or elapsed time. Confidence remains low in the absence of inspected implementation evidence; the zero remainder reflects the reported completion, not an independent test result. No new addressing, access-handoff, BMC configuration or OneView enrolment budget is added to this completed network feature.
Dependencies
DNS/DHCP/IPAM provides address and naming authority; DHCP is needed only for attachment patterns that use it. Identity and secrets controls must cover privileged management/API access. Inventory and automation need a deliberate handoff, and recovery must remain possible when the normal controller is unavailable. These are architecture responsibilities, not automatically serial roadmap tasks; additional delivery edges need an actual readiness condition.
EIRA Alignment
An applicable EIRA mapping has not been established. This note does not infer one from its folder, protocol or vendor candidate.
Primary evidence and next iteration
Consulted 2026-10-09. N1 is the standards baseline; N2 is the currently served API documentation (release 4.2 and later), not an immutable product-release record. N3 is a pinned automation-collection release. None is observed deployment evidence.
The broader design agenda above remains context, not another set of promised Phase 1 features. The 17 October agreement now supplies the small scope and feature points, and the Cisco Nexus Dashboard service has its own feature budgets; its release, hosting, owner and actual progress remain to detail. Full topology and implementation configuration remain Networking design work, not fabricated by these planning notes.
Explore this note’s relationships 19 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (20)
- Intent, delivery and runtime evidenceNote · draft · Automation. Icon: Automation
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — Clusters-as-a-Service: first production offeringNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- CLaaS technical feasibility evidence registerResearch · draft · CLaaS. Icon: General note
- DCIM serviceABB · draft · DCIM. Icon: Inventory
- HPE OneViewSBB · draft · DCIM. Icon: Inventory
- Inventory and hardware-management control designHLD · draft · DCIM. Icon: Inventory
- Datacenter hardwareNote · draft · Hardware. Icon: General note
- CLaaS tenant network designHLD · draft · Network. Icon: Network
- DNS, DHCP and IP address managementABB · draft · Network. Icon: Network
- EVPN/VXLAN network fabricABB · draft · Network. Icon: Network
- MetalLB — BGP application entry pointsSBB · draft · Network. Icon: Network
- Cisco Nexus DashboardSBB · draft · Network. Icon: Network
- OpenShift platform baselineSBB · draft · Platform. Icon: Platform
- OpenShift hosting and service boundariesNote · draft · Platform. Icon: Platform
- SAK applicability and control allocation for CLaaSNote · draft · Security. Icon: General note
- Ceph clustersSBB · draft · Storage. Icon: Storage
- External Ceph through ceph-csiSBB · draft · Storage. Icon: Storage
- Ceph RGW — tenant S3 object serviceSBB · draft · Storage. Icon: Storage
Relationships (38)
- CLaaS — Clusters-as-a-Service: first production offeringReferences →EVPN/VXLAN network fabricCLaaS/index.md · Markdown link
- CLaaS technical feasibility evidence registerReferences →EVPN/VXLAN network fabricCLaaS/technical-feasibility.md · Markdown link
- HPE OneView
· hpe-oneview#ipmi-configurationDepends on →EVPN/VXLAN network fabric· evpn-vxlan#dcm-networkDCIM/hpe-oneview.md · features.ipmi-configuration.depends_on: evpn-vxlan#dcm-network - Inventory and hardware-management control designDepends on →EVPN/VXLAN network fabricDCIM/inventory-control-design.md · depends_on
- Inventory and hardware-management control designReferences →EVPN/VXLAN network fabricDCIM/inventory-control-design.md · Markdown link
- Datacenter hardware
· datacenter-hardware#bmc-managementDepends on →EVPN/VXLAN network fabric· evpn-vxlan#dcm-networkHardware/datacenter-hardware.md · features.bmc-management.depends_on: evpn-vxlan#dcm-network - Datacenter hardwareReferences →EVPN/VXLAN network fabricHardware/datacenter-hardware.md · Markdown link
- CLaaS tenant network designDepends on →EVPN/VXLAN network fabricNetwork/claas-network-design.md · depends_on
- CLaaS tenant network designReferences →EVPN/VXLAN network fabricNetwork/claas-network-design.md · Markdown link
- DNS, DHCP and IP address managementReferences →EVPN/VXLAN network fabricNetwork/dns-dhcp-ipam.md · Markdown link
- EVPN/VXLAN network fabric
· evpn-vxlan#dcm-networkDepends on →DNS, DHCP and IP address management· dns-dhcp-ipamNetwork/evpn-vxlan.md · features.dcm-network.depends_on: dns-dhcp-ipam - EVPN/VXLAN network fabricDepends on →DNS, DHCP and IP address managementNetwork/evpn-vxlan.md · depends_on
- EVPN/VXLAN network fabric
· evpn-vxlan#orchestrator-integrationDepends on →Cisco Nexus Dashboard· nexus-fabric-orchestratorNetwork/evpn-vxlan.md · features.orchestrator-integration.depends_on: nexus-fabric-orchestrator - EVPN/VXLAN network fabricReferences →Intent, delivery and runtime evidenceNetwork/evpn-vxlan.md · Markdown link
- EVPN/VXLAN network fabricReferences →CLaaS — Clusters-as-a-Service: first production offeringNetwork/evpn-vxlan.md · Markdown link
- EVPN/VXLAN network fabricReferences →DNS, DHCP and IP address managementNetwork/evpn-vxlan.md · Markdown link
- EVPN/VXLAN network fabricReferences →OpenShift hosting and service boundariesNetwork/evpn-vxlan.md · Markdown link
- EVPN/VXLAN network fabricReferences →External Ceph through ceph-csiNetwork/evpn-vxlan.md · Markdown link
- MetalLB — BGP application entry points
· metallb-bgp#patternDepends on →EVPN/VXLAN network fabric· evpn-vxlanNetwork/metallb-bgp.md · features.pattern.depends_on: evpn-vxlan - MetalLB — BGP application entry pointsDepends on →EVPN/VXLAN network fabricNetwork/metallb-bgp.md · depends_on
- MetalLB — BGP application entry pointsReferences →EVPN/VXLAN network fabricNetwork/metallb-bgp.md · Markdown link
- Cisco Nexus DashboardReferences →EVPN/VXLAN network fabricNetwork/nexus-fabric-orchestrator.md · Markdown link
- OpenShift platform baselineDepends on →EVPN/VXLAN network fabricPlatform/openshift-platform.md · depends_on
- OpenShift platform baselineReferences →EVPN/VXLAN network fabricPlatform/openshift-platform.md · Markdown link
- OpenShift hosting and service boundariesReferences →EVPN/VXLAN network fabricPlatform/openshift-service-boundaries.md · Markdown link
- SAK applicability and control allocation for CLaaSReferences →EVPN/VXLAN network fabricSecurity/sak-assurance.md · Markdown link
- Ceph clusters
· ceph-clusters#base-installDepends on →EVPN/VXLAN network fabric· evpn-vxlan#pre-provisioned-vlansStorage/ceph-clusters.md · features.base-install.depends_on: evpn-vxlan#pre-provisioned-vlans - External Ceph through ceph-csi
· external-ceph-csi#backend-accessDepends on →EVPN/VXLAN network fabric· evpn-vxlan#pre-provisioned-vlansStorage/external-ceph-csi.md · features.backend-access.depends_on: evpn-vxlan#pre-provisioned-vlans - External Ceph through ceph-csiReferences →EVPN/VXLAN network fabricStorage/external-ceph-csi.md · Markdown link
- Ceph RGW — tenant S3 object serviceDepends on →EVPN/VXLAN network fabric
· evpn-vxlan#pre-provisioned-vlansStorage/tenant-object-storage.md · depends_on: evpn-vxlan#pre-provisioned-vlans
Features of this note
5 features declared in this note's metadata. Each is one capability with its own section. Readiness is the author's dated assessment for the scope it names; delivery is the next increment of work. The two are independent, and nothing here combines them across features or implies approval.
100 pre-provisioned VLANs
evpn-vxlan#pre-provisioned-vlans- Section
- 100 pre-provisioned VLANs
- Readiness
- Readiness unknown for An available set of 100 pre-provisioned VLANs within the agreed tenant, platform and storage separation boundaries., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 8 working hours (1 working day); Networking; recorded owner Quanza.
- Effort estimate
- 8 h working · 8–8 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
DCM network
evpn-vxlan#dcm-network- Section
- DCM network
- Readiness
- Ready for Implemented DCM network connectivity for the DC 3.0 server IPMI interfaces, for platform engineers and ACM-driven platform provisioning; this does not establish completed BMC configuration or OneView enrolment., assessed 17 Oct 2026; evidence: Reported DCM completion — 17 October 2026. The author assessed that this capability is usable for the stated scope on the stated date. This is a recorded assessment, not an approval, and it says nothing about other scopes.
- Next delivery
- No delivery increment is planned in the source.
EVPN/VXLAN firmware installation
evpn-vxlan#firmware-install- Readiness
- Ready for EVPN/VXLAN firmware installed on the AM4 switches, as reported by the proposer; other sites and the readiness of VRF/VLAN separation are not established by this installation., assessed 17 Oct 2026; evidence: EVPN/VXLAN firmware installation. The author assessed that this capability is usable for the stated scope on the stated date. This is a recorded assessment, not an approval, and it says nothing about other scopes.
- Next delivery
- No delivery increment is planned in the source.
Integration into the fabric orchestrator
evpn-vxlan#orchestrator-integration- Readiness
- Readiness unknown for The Phase 1 fabric integrated into the separately available Cisco Nexus Dashboard service as the foundation for future network automation., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 40 working hours (5 working days); Networking; recorded owner Quanza.
- Effort estimate
- 40 h working · 40–40 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
VRF setup and separation details
evpn-vxlan#vrf-setup- Readiness
- Readiness unknown for Documented and qualified separation of tenant, platform and storage traffic in the Phase 1 fabric., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 32 working hours (4 working days); Networking; recorded owner Quanza.
- Effort estimate
- 32 h working · 32–32 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)