EVPN/VXLAN network fabric

ABBDraftReview not recorded

Work in progress according to its author.

Local drafting workspace

EVPN/VXLAN network fabric

Network/evpn-vxlan.md

Local draft — not saved or submitted. Download and use the Git/PR workflow. Changes stay in this page’s memory, never alter the published note, and are lost on reload. The .md download contains the narrative only; preserve the original frontmatter in Git. The preview is not publication validation.

Preview

Images and raw HTML are disabled. Preview links do not navigate. Markdown links are checked when the source is built, not here.

Published source loaded. No local changes.

View source & provenance

Effort scenario: evpn-vxlan

Workstream: Foundations. Zero-additional-work Phase 1 acceptance milestone, revised 2026-10-17.

Work package Low h Working h High h
No additional work beyond the owning Phase 1 feature increments 0 0 0

The earlier 72/184/336-hour conditional aggregate is superseded, not retained or added again. The reduced scope has three proposed feature budgets totalling 80 engineering hours / 80 scheduling hours. Firmware is reported complete in AM4; its supplied 40/40-hour point is historical budget context, not future work or measured actual effort. The new Cisco Nexus Dashboard service is a separate item with its own 40/40-hour feature budgets, not hidden in the integration budget. The milestone retains the existing DNS/IPAM consumer contract. It adds no duplicate engineering or duration, and a successful plan/build is not architectural approval.

Summary

This draft defines the network-fabric capability proposed for the first CLaaS offering: provide controlled connectivity and separation for HCP management, tenant workers and the supporting services they consume. On 2026-10-17, the proposer deliberately reduces Phase 1 to the basics for short-term feasibility: firmware, VRF separation/details, 100 pre-provisioned VLANs and integration into a new fabric orchestration service. Firmware is reported installed in AM4, with basic configuration that allows VLAN provisioning. VRFs are assumed configured, but their details are not yet available. These are reported progress, not inspected versions, proven isolation or accepted reliability.

Quanza owns all four feature outcomes in Networking. The aggregate delivery and three pending increments are proposed; completed firmware and DCM are available capabilities with no fictitious future increments or invented finish dates.

EVPN supplies a BGP-based control plane for network virtualization; VXLAN is an overlay encapsulation over IP. RFC 8365 describes their combination, including multihoming and interconnection mechanisms (N1). Those standards are a useful interoperability basis, not proof that a particular device combination or configuration delivers the desired tenant service.

Capabilities

The four-feature Phase 1 scope below is the delivery selection. The following broader design concerns remain architectural context, not additional promised features or work silently included in the new 80-hour budget. Required tenant, platform and storage separation remains part of the VRF outcome; wider MTU, congestion, failure/recovery qualification and full automation coverage are not claimed complete or priced by this reduced feature list.

Concern Proposed first-offering outcome What still needs deciding
Underlay and attachments Predictable IP reachability between the selected fabric endpoints and server attachments Physical redundancy, routing design, addressing, device/release combination and failure domain
Tenant and management separation Explicit permitted and denied paths between management, tenant and shared-service scopes VRF/VNI allocation, gateways, route import/export and separate firewall/policy enforcement
CLaaS interfaces Reachability for hosted control-plane endpoints, workers, ingress/egress and required shared services API exposure/load-balancing contract, routing handoffs, DNS and responsibility at each boundary
Storage path The consuming nodes can reach the authorized external Ceph services without exposing unrelated storage access Endpoint paths, segmentation, capacity, latency and contention limits for the selected storage design
Packet transport End-to-end packet sizes and forwarding work for the selected host and cluster networking Underlay MTU and combined encapsulation overhead, including any cluster overlay; IPv4/IPv6 scope
Controlled change An owned, repeatable configuration path with scoped access, review and drift visibility Controller/API choice, authoritative intent, reconciliation ownership and emergency-change procedure
Failure and operations Observable forwarding and tested recovery appropriate to the first service promise Link/device failures, maintenance, control-plane/controller outage and measurable convergence criteria

EVPN segmentation is not by itself encryption or application authorization. Route-policy mistakes can cross intended boundaries; N1 section 11 identifies misrouting/misdelivery risks from modified tunnel/control information. Allocate and verify the actual security controls against the applicable requirements, including denied-path tests, rather than infer BIO2 compliance from VRFs or VNIs.

Constraints

In clarification round 1 on 2026-10-12, the proposer reports initial EVPN/VXLAN firmware/configuration on the switches and a couple dozen statically pre-provisioned VLANs available to consume. The rest of the setup and final design are not known. No device/release inventory, configuration revision, isolation, MTU or failure-test evidence was supplied or inspected. This is reported progress, not a blank fabric; VLAN availability does not establish tenant isolation or host-attachment readiness.

The 17 October agreement supersedes the broad 72/184/336-hour estimate with the explicit feature budgets below. The older couple-dozen-VLAN report is not evidence that the new 100-VLAN target is available. Do not infer one VLAN per tenant, complete isolation or a numerical completion percentage. Existing firmware is credited as complete only for AM4; no other site's firmware is marked ready.

Round 2 on 2026-10-12 reports leaf/link or node loss has not been tested. Those test gaps remain explicit. The reduced scope does not establish resilience or absorb the former broad qualification package into 80 hours. If required service acceptance needs additional failure/MTU/scale work, allocate and estimate that work explicitly rather than claim it done or silently weaken the boundary. Networking within the core team is concentrated in one engineer with networking familiarity, not a confirmed dedicated network-specialist allocation. Network-team involvement, final design ownership and change windows remain to identify; staffing contention is not a new technical dependency edge.

The assignment reports existing network hardware available for the March scope, which is one location with local redundancy. Treat that as the starting inventory assumption, not proof of configured EVPN/VXLAN, sufficient capacity or a supported feature set. The actual devices, releases, allocation and failure cases still need qualification. No new hardware procurement dependency is assumed without an identified gap.

The earlier proposer description was two 100G physical interfaces per bare-metal node, carrying VLAN-separated traffic in an active-active bond to a redundant leaf pair. The 19 October hardware profiles now refine that blanket inventory description: Control, Worker and GPU roles list one E810-CQDA2 dual-port 100Gb adapter, while Ceph lists two single-port 400Gb InfiniBand NDR/Ethernet adapters. Actual mode, negotiated speed and role-specific switch/bond compatibility remain unconfirmed; the label is not achieved throughput. The proposer reports that the E810 card cannot provide the required true 200 Gbit/s through-card bandwidth and probably needs replacement. The NIC issue has no selected replacement or estimated lead time. It does not reopen completed AM4 switch firmware or DCM work. Qualify actual compatibility, failure behaviour, capacity and contention; neither a port count nor the word redundant proves usable aggregate capacity or independent failure domains.

The 17 October report assumes VRFs have been configured, but supplies no details. Allocation, routing interaction and security enforcement are therefore not established. The VRF increment must explain how VLANs, VRFs and actual filtering protect management and tenants on the converged physical path. Qualify contention and link/device failures across storage and other traffic; logical separation alone does not provide independent physical capacity or trust.

Keep the physical fabric distinct from the Kubernetes cluster network. This proposal does not replace the CNI or prescribe that the tenant cluster's overlay must use the same encapsulation as the datacenter fabric. The selected OpenShift, HCP, NIC, switch and storage configurations need a combined support and integration assessment. Address/IPAM authority, privilege boundaries and approved change ownership are prerequisites to safe automation, not benefits obtained merely by installing a controller.

Service Description

The network provider supplies the agreed connectivity and separation contract; the CLaaS provider owns its cluster-side integration and tenant-facing promise. Network operations, platform operations and tenant responsibilities must agree on where each path is diagnosed and restored. On 2026-10-14 the proposer assigns networking work, including this fabric and its DCM feature, to the Networking domain, with its own architects. Detailed network design belongs there; the CLaaS team specifies its consumer requirements and acceptance paths. The 17 October agreement names Quanza as owner of all four Phase 1 fabric features. The individual architect, service operator for Cisco Nexus Dashboard and formal acceptance authority remain unrecorded. Networking is an explicit domain assignment, not inferred from the subject folder. DCM is already reported complete; the new feature points replace the broad fabric range.

Roadmaps

The delivery block is now a zero-additional-work Phase 1 milestone over the three pending increments. The explicit order is firmware → VRF setup/details → 100 pre-provisioned VLANs → orchestrator integration, with VRF and VLAN order swapped from the proposer's initial list as explicitly requested. All four feature outcomes are Quanza-owned. The firmware capability is already available in AM4, so VRF work references it architecturally rather than waiting on new firmware work. The next increments each depend on the previous pending outcome; integration also requires the separately available orchestrator service. No parent/child cycle is introduced, and DCM/IPMI consumption is not gated on this new automation foundation.

The three proposed durations total 80 scheduling hours (ten working days) under the existing eight-hour weekday convention, only after their inputs and external service availability are satisfied. They are not dates or a resource-levelled commitment. The old aggregate and the completed firmware 40/40 are not added again.

Broader multisite overlays, stretched Layer 2, additional tenant patterns and fully self-service network provisioning are candidates for later scope unless the first consumer's requirements make them necessary. First-release deferrals must preserve required isolation, availability and recovery. A controlled operator-assisted workflow may be considered instead of full automation; it still needs review, repeatability, ownership and an auditable result.

EVPN/VXLAN firmware installation

Outcome and owner: Quanza installs the EVPN/VXLAN firmware baseline on the in-scope switches. The proposer reports this already completed in AM4 on 2026-10-17, and reports basic configuration that permits VLAN provisioning. No actual completion date, switch inventory or installed release was supplied. Readiness is therefore recorded for AM4 only, on the basis of the report, not a tested support matrix or proof that another site has the same baseline.

The supplied 40 engineering / 40 scheduling hours are the feature's budget, not measured effort spent. There is no next firmware increment planned for this reported-complete scope, so no delivery block or invented actual finish is added. VRF work consumes this available capability. Its conservative 17 October earliest start prevents planning before the confirmation boundary; that is not the firmware installation date. Another site or later firmware change would need its own explicit scope and readiness, not an assumed AM4 result.

VRF setup and separation details

Outcome and owner: Quanza establishes and documents the required tenant, platform and storage traffic separation, including VRF allocation, VLAN mapping, permitted routing/handoffs and where filtering enforces the boundary. The proposer assumes VRFs are configured but has no details yet. Existing configuration may be reusable; it is not accepted isolation evidence or a completed increment.

Acceptance needs a usable description of the actual boundaries and confirmation that the required paths work while unauthorized cross-boundary traffic is refused. A VRF name alone is not an access-control guarantee. The feature remains proposed, with unknown readiness and a supplied 32 engineering / 32 scheduling hours. It consumes the reported-ready AM4 firmware capability; it does not wait for another installation or infer a firmware finish date.

100 pre-provisioned VLANs

Outcome and owner: Quanza makes a set of 100 pre-provisioned VLANs available for the Phase 1 consumers, with their identifiers, permitted use and VRF/traffic boundaries documented. Basic configuration is reported to allow VLAN provisioning; neither that report nor the older couple-dozen-VLAN baseline proves all 100 ready. The number does not imply one VLAN per tenant, 100 tenants or an approved allocation.

The supplied budget is 8 engineering / 8 scheduling hours. Delivery is proposed, with unknown readiness. The proposer explicitly orders this outcome after the VRF setup/details increment. This is a planning sequence, not a claim that a vendor technically forbids creating VLANs earlier. Acceptance checks the full agreed set and its usable consumer mapping, not just the ability to create a single VLAN.

Ceph consumer handoff — 19 October 2026. The proposer confirms that Ceph can be installed and operated when connectivity is established and the pre-provisioned VLANs can be consumed. For that consumer, this existing feature hands over usable host/storage paths within the agreed VRF boundaries, not just a list of VLAN IDs. Required addresses must come from the authorized allocation authority and the permitted paths must work; a VLAN count alone does not prove connectivity. No addressing details or path-test evidence were supplied by this clarification. The handoff remains proposed with unknown readiness, using its existing 8/8-hour budget rather than adding another network task. It does not wait for Nexus Dashboard onboarding. The complete fabric milestone retains its broader DNS/IPAM baseline and orchestration prerequisites; those are not copied into this scoped Ceph start gate. Completed DCM connectivity and AM4 firmware are unchanged.

Integration into the fabric orchestrator

Outcome and owner: Quanza integrates the Phase 1 fabric into the separately available Cisco Nexus Dashboard service. This 40 engineering / 40 scheduling hours covers fabric onboarding and integration, not installing or funding that service a second time. It follows the 100-VLAN outcome and requires the new service to be available. Delivery is proposed and readiness remains unknown.

Acceptance identifies the fabric and configuration baseline in the service, qualifies scoped operator/API access and the intended supported integration path, and records which system owns each configuration value. Git, Nexus Dashboard and manual administration must not become competing writers. This feature demonstrates the actual AM4 onboarding; the service's own Fabric Management and Manage features only enable that function and scoped API access. Exact release, credentials and interfaces remain to detail with the service owner; no supported deployment or working integration is inferred from the product name.

This creates the foundation for future network automation. Any network/fabric automation must consume the available orchestration service first, but full dynamic VLAN self-service or a new tenant-network automation workflow is not silently added to Phase 1. Existing ACM-driven IPMI provisioning and completed DCM connectivity are not retroactively blocked by the new service.

Effort scenario: evpn-vxlan#vrf-setup

Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.

Work package Low h Working h High h
Establish and document the required tenant/platform/storage VRF separation 32 32 32

Duration: 32 scheduling hours. Low confidence while the assumed existing VRF configuration and its boundaries remain unverified. Equal bounds encode the supplied point, not an independently assessed range or a verified remainder.

Effort scenario: evpn-vxlan#pre-provisioned-vlans

Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.

Work package Low h Working h High h
Make and qualify the agreed set of 100 pre-provisioned VLANs 8 8 8

Duration: 8 scheduling hours. Low confidence until the 100-VLAN set, consumer mapping and actual remainder are confirmed. This does not count firmware again.

Effort scenario: evpn-vxlan#orchestrator-integration

Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.

Work package Low h Working h High h
Integrate the fabric into the separately available orchestration service 40 40 40

Duration: 40 scheduling hours. Low confidence until the service, supported interface and actual integration remainder are known. The service's own 40/40-hour setup is budgeted in its own note, not included here.

Landing Locations

The first CLaaS scope is AM4, confirmed on 2026-10-20, retaining one location with local redundancy. Its reported hardware inventory is 64 nodes across four racks; exact host/rack mapping, fabric attachment details and management-platform placement remain unresolved. The rack count does not prove independent failure domains or select a Nexus Dashboard hosting location. Do not infer a stretched fabric or additional location from the end-state ambition. Record the management platform's bootstrap and recovery dependencies separately from the network it will manage.

Available SBBs

The newly required Cisco Nexus Dashboard service has its own SBB and Phase 1 delivery item, in Networking. This is the proposer's service direction, not institutional approval or a verified Cisco SKU. On 2026-10-17 the proposer identifies the product as Cisco Nexus Dashboard, current 4.x line with integrated fabric management, replacing the earlier wrong working name. The previously examined Cisco DevNet documentation distinguishes Nexus Dashboard Fabric Controller (NDFC) legacy interfaces, the unified Manage fabric APIs, and Nexus Dashboard Orchestrator (NDO) orchestration for multisite/multifabric management (N2). In the selected direction, Manage is Nexus Dashboard's API/configuration capability and NDFC a legacy function, not a separate product. NDO and Network Services Orchestrator (NSO) are not this product and are not required in this phase. The exact release remains to select.

The examined documentation calls Infra, Manage, One Manage, Analyze and Orchestration APIs GA from 4.2.1 and describes legacy API deprecation in 4.3.1. The latest non-prerelease CiscoDevNet Ansible NDFC collection observed was 3.13.0, published 2026-08-27, with stated ND 4.3.1 support (N3). That collection release is not a selection of the network-management product, an assurance of latest product GA, or proof of compatibility with our switches. The Cisco product pages returned HTTP 403 during consultation; latest product patch, lifecycle, hardware support and licensing remain unverified. Avoid choosing a legacy API from its familiar name without checking the intended release.

Qualify the selected service against scoped API roles, inventory and fabric onboarding, configuration preview/deployment, repeatability, drift/change handling, failure recovery and the owned integration with automation. Establish which system owns each configuration value; Git-reviewed intent and a controller must not become competing writers. Reliability and operational savings need representative evidence, not the product name alone.

Interfaces

Describe host attachments and L3 handoffs, tenant/shared-service routing, IPAM/DNS allocation, telemetry and the management API separately. The external Ceph proposal needs a verified path from its actual consuming nodes to the required Ceph services. It does not imply that storage replication traffic and tenant traffic share one unrestricted network. The hosting contract owns the integration of these paths with HCP and tenant execution.

DCM network

The DCM (DataCenter Management) network already exists in RWS infrastructure. In RWS notation it is a highly secured network used only to manage critical datacenter infrastructure. The proposer's clarification of 2026-10-14 defines this feature as extending that existing service to the new DC 3.0 switching setup and connecting all server IPMI interfaces to it. It is not a new standalone management-network service. Its consumer scope and progress remain separate from the tenant/platform fabric outcome.

Required outcome. The new EVPN/VXLAN switching setup makes the existing DCM network operationally available to the IPMI interfaces of the datacenter hardware. The consumers are platform engineers accessing server IPMI and the platform accessing IPMI for ACM-driven provisioning. HPE OneView is another management consumer, not a claim that its separately planned enrolment/configuration work is complete.

Design responsibility. This feature belongs to Networking, with detailed design and the handoff to the existing DCM infrastructure owned by that domain's architects and delivery process. The proposer suggests a management VRF with a VLAN connecting the new IPMI interfaces to DCM. This is a design hypothesis, not an approved topology or an implementation instruction. Networking must define the actual attachment, routing, filtering, resilience and controlled recovery access in the design. A VLAN or VRF alone does not establish the secured boundary.

Reported DCM completion — 17 October 2026

The proposer confirms that DCM networking on the EVPN/VXLAN setup is implemented and complete. Quanza owns completion. This supersedes the 14 October "mostly done" report and its 16 engineering / 40 scheduling hours of future work. The scoped network capability is recorded as ready on the basis of this report, not an independently inspected deployment or security test. No configuration revision, test report or actual completion date was supplied. The proposer explicitly confirms that the completion date is unknown. No start or finish date is inferred from the report date. Capability readiness is ready, with the dated report as its stated basis, and no next delivery increment is planned. The optional delivery block is therefore omitted rather than keeping a fictitious unknown future task or inventing an actual_finish. Quanza's completion ownership remains recorded here. Consumers retain their architectural dependency on this capability, but do not wait for new DCM work. The earlier undated delivery placeholder incorrectly blocked IPMI scheduling and is superseded by this distinction between available capability and future work.

The access requirement is platform engineers reaching server IPMI and the platform reaching IPMI for provisioning from ACM. "Consumer handoff" means making those network paths usable, not another service, milestone or extra budget. Completion does not mark the broader fabric, IPMI/BMC configuration or OneView enrolment done.

Access boundary. Permit named platform engineers through approved management paths, HPE OneView, and the authorized OpenShift nodes/provisioning identities. The OpenShift path must work from the nodes' bonded 100G interfaces to the IPMI interfaces on DCM. This is scoped infrastructure-management access, not blanket access for tenant workloads or every cluster. Tenant workloads, public networks and general office networks remain refused. Networking must qualify the permitted and denied paths and define controlled emergency access; no security approval or compliance is claimed by this note.

Records and dependencies. Addresses and names remain under the DNS, DHCP and IPAM authority. The proposer expects interfaces to be defined in the DCIM service, identifying NetBox as the intended tool. That record is useful for planning and evidence, but DCIM is neither an architectural nor a delivery prerequisite for this feature. DCM connectivity must not depend on NetBox being available. The separate hardware features retain their own inventory requirements. Addressing is an implementation detail needed by this completed network outcome, not new separately priced DCM work. The architectural address-authority relationship remains; its former DNS/IPAM delivery start gate is removed so confirmation work for other consumers does not retroactively block completed DCM connectivity. The separately budgeted tenant-zone delegation feature is different scope and remains unchanged.

Network acceptance boundary, for all in-scope new server interfaces:

  • Platform engineers can manage the new hardware through its IPMI interface over the approved DCM access path.
  • The platform has the permitted IPMI network path for ACM-driven provisioning, including the previously described bonded 100G node attachment where used.
  • Authorized management consumers have the required network reachability. BMC accounts/settings and OneView provisioning remain separately owned increments.

Retained technical evidence should identify the interface/node scope, configuration baseline and permitted/denied-path results. No such test records were inspected in this clarification; the source is the proposer's completion report. DCM owns the network path; BMC configuration and OneView provisioning work remain owned by the OneView features and referenced by the hardware acceptance milestones. Prepare the necessary test interfaces during integration, without adding a circular gate on completing those hardware features. DCM does not wait for the whole fabric outcome or for a full OneView enrolment milestone.

Planning. Reported completion leaves 0 remaining engineering hours and 0 future scheduling hours for this DCM increment. The earlier 16/40-hour point remains historical estimate context, not measured effort spent or another budget to add. The OneView IPMI budget remains separate. The later 17 October reduced-scope agreement supersedes the broader 72/184/336-hour fabric range; DCM completion does not claim the new VRF/VLAN/integration increments done. The actual finish date remains unknown; this historical gap does not prevent planning consumption of the reported-ready capability.

DCM remaining work and historical estimate

Workstream: Foundations. Remaining-work assessment dated 2026-10-17, based on the proposer's completion report.

Work package Low h Working h High h
No remaining network work in the reported-complete DCM increment 0 0 0

Future duration: 0 scheduling hours. The earlier 16 engineering / 40 scheduling hours are superseded, not converted into measured actual effort or elapsed time. Confidence remains low in the absence of inspected implementation evidence; the zero remainder reflects the reported completion, not an independent test result. No new addressing, access-handoff, BMC configuration or OneView enrolment budget is added to this completed network feature.

Dependencies

DNS/DHCP/IPAM provides address and naming authority; DHCP is needed only for attachment patterns that use it. Identity and secrets controls must cover privileged management/API access. Inventory and automation need a deliberate handoff, and recovery must remain possible when the normal controller is unavailable. These are architecture responsibilities, not automatically serial roadmap tasks; additional delivery edges need an actual readiness condition.

EIRA Alignment

An applicable EIRA mapping has not been established. This note does not infer one from its folder, protocol or vendor candidate.

Primary evidence and next iteration

Consulted 2026-10-09. N1 is the standards baseline; N2 is the currently served API documentation (release 4.2 and later), not an immutable product-release record. N3 is a pinned automation-collection release. None is observed deployment evidence.

The broader design agenda above remains context, not another set of promised Phase 1 features. The 17 October agreement now supplies the small scope and feature points, and the Cisco Nexus Dashboard service has its own feature budgets; its release, hosting, owner and actual progress remain to detail. Full topology and implementation configuration remain Networking design work, not fabricated by these planning notes.

Explore this note’s relationships 19 connected notes

Connections are authored references and declared relationships, not verified runtime dependencies or approval.

20 notes · 38 relationships

Every note and relationship is available in the list below. The interactive map requires JavaScript.

Outline is the note kindABBSBBHLDResearchNoteMarkdown referenceTyped relationship
Icon is the documented subjectNetworkStorageAutomationInventoryPlatformGeneral note
Notes and relationships Accessible list

Notes (20)

Relationships (38)

Features of this note

5 features declared in this note's metadata. Each is one capability with its own section. Readiness is the author's dated assessment for the scope it names; delivery is the next increment of work. The two are independent, and nothing here combines them across features or implies approval.

Source & provenance

This is the published reading view. The Markdown source and Git review workflow remain authoritative; publication is not architectural approval.

Source
Network/evpn-vxlan.md
Identifier
evpn-vxlan
Kind
Architecture building block
Status
Draft, as authored
Revision
a3203210221340f80866b0462f4d63b49ebc5aea

Review not recorded. A recorded review date is the author’s review of the whole note, not an edit date, build date or approval. Editing a local draft does not update it.

Read the Markdown source

Read-only narrative source. Authored labels and relationships are listed above; this view does not write to the vault.


# EVPN/VXLAN network fabric

## Effort scenario: evpn-vxlan

**Workstream:** Foundations.
Zero-additional-work Phase 1 acceptance milestone, revised **2026-10-17**.

| Work package | Low h | Working h | High h |
| --- | ---: | ---: | ---: |
| No additional work beyond the owning Phase 1 feature increments | 0 | 0 | 0 |

The earlier **72/184/336-hour** conditional aggregate is **superseded**, not retained
or added again. The reduced scope has three proposed feature budgets totalling
**80 engineering hours / 80 scheduling hours**. Firmware is reported complete in
AM4; its supplied **40/40-hour** point is historical budget context, not future
work or measured actual effort. The new Cisco Nexus Dashboard **service is a separate
item with its own 40/40-hour feature budgets**, not hidden in the integration budget.
The milestone retains the existing DNS/IPAM consumer contract. It adds no duplicate
engineering or duration, and a successful plan/build is not architectural approval.

## Summary

This draft defines the network-fabric capability proposed for the
[first CLaaS offering](../CLaaS/index.md): provide controlled connectivity and
separation for HCP management, tenant workers and the supporting services they
consume. On **2026-10-17**, the proposer deliberately **reduces Phase 1 to the basics**
for short-term feasibility: firmware, VRF separation/details, 100 pre-provisioned
VLANs and integration into a new fabric orchestration service. Firmware is reported
installed in **AM4**, with basic configuration that allows VLAN provisioning.
VRFs are assumed configured, but their details are not yet available. These are
reported progress, not inspected versions, proven isolation or accepted reliability.

Quanza owns all four feature outcomes in **Networking**. The aggregate delivery
and three pending increments are **proposed**; completed firmware and DCM are
available capabilities with no fictitious future increments or invented finish dates.

EVPN supplies a BGP-based control plane for network virtualization; VXLAN is an
overlay encapsulation over IP. RFC 8365 describes their combination, including
multihoming and interconnection mechanisms (N1). Those standards are a useful
interoperability basis, not proof that a particular device combination or
configuration delivers the desired tenant service.

## Capabilities

The **four-feature Phase 1 scope below is the delivery selection**. The following
broader design concerns remain architectural context, not additional promised
features or work silently included in the new 80-hour budget. Required tenant,
platform and storage separation remains part of the VRF outcome; wider MTU,
congestion, failure/recovery qualification and full automation coverage are not
claimed complete or priced by this reduced feature list.

| Concern | Proposed first-offering outcome | What still needs deciding |
| --- | --- | --- |
| Underlay and attachments | Predictable IP reachability between the selected fabric endpoints and server attachments | Physical redundancy, routing design, addressing, device/release combination and failure domain |
| Tenant and management separation | Explicit permitted and denied paths between management, tenant and shared-service scopes | VRF/VNI allocation, gateways, route import/export and separate firewall/policy enforcement |
| CLaaS interfaces | Reachability for hosted control-plane endpoints, workers, ingress/egress and required shared services | API exposure/load-balancing contract, routing handoffs, DNS and responsibility at each boundary |
| Storage path | The consuming nodes can reach the authorized external Ceph services without exposing unrelated storage access | Endpoint paths, segmentation, capacity, latency and contention limits for the selected storage design |
| Packet transport | End-to-end packet sizes and forwarding work for the selected host and cluster networking | Underlay MTU and combined encapsulation overhead, including any cluster overlay; IPv4/IPv6 scope |
| Controlled change | An owned, repeatable configuration path with scoped access, review and drift visibility | Controller/API choice, authoritative intent, reconciliation ownership and emergency-change procedure |
| Failure and operations | Observable forwarding and tested recovery appropriate to the first service promise | Link/device failures, maintenance, control-plane/controller outage and measurable convergence criteria |

EVPN segmentation is not by itself encryption or application authorization.
Route-policy mistakes can cross intended boundaries; N1 section 11 identifies
misrouting/misdelivery risks from modified tunnel/control information. Allocate
and verify the actual security controls against the applicable requirements,
including denied-path tests, rather than infer BIO2 compliance from VRFs or VNIs.

## Constraints

In clarification round 1 on **2026-10-12**, the proposer reports initial EVPN/VXLAN
firmware/configuration on the switches and a couple dozen statically pre-provisioned
VLANs available to consume. The rest of the setup and final design are not known.
No device/release inventory, configuration revision, isolation, MTU or failure-test
evidence was supplied or inspected. This is reported progress, not a blank fabric;
VLAN availability does not establish tenant isolation or host-attachment readiness.

The **17 October** agreement supersedes the broad 72/184/336-hour estimate with
the explicit feature budgets below. The older couple-dozen-VLAN report is not
evidence that the new **100-VLAN target** is available. Do not infer one VLAN per
tenant, complete isolation or a numerical completion percentage. Existing firmware
is credited as complete only for AM4; no other site's firmware is marked ready.

Round 2 on **2026-10-12** reports leaf/link or node loss has **not been tested**.
Those test gaps remain explicit. The reduced scope does not establish resilience
or absorb the former broad qualification package into 80 hours. If required service
acceptance needs additional failure/MTU/scale work, allocate and estimate that work
explicitly rather than claim it done or silently weaken the boundary. Networking
within the core team is concentrated in one
engineer with networking familiarity, not a confirmed dedicated network-specialist
allocation. Network-team involvement, final design ownership and change windows
remain to identify; staffing contention is not a new technical dependency edge.

The assignment reports existing network hardware available for the March scope,
which is one location with local redundancy. Treat that as the starting inventory
assumption, not proof of configured EVPN/VXLAN, sufficient capacity or a supported
feature set. The actual devices, releases, allocation and failure cases still
need qualification. No new hardware procurement dependency is assumed without
an identified gap.

The earlier proposer description was **two 100G physical interfaces per bare-metal
node**, carrying VLAN-separated traffic in an **active-active bond to a redundant
leaf pair**. The **19 October hardware profiles** now refine that blanket inventory
description: [Control, Worker and GPU roles](../Hardware/datacenter-hardware.md#reported-node-role-configurations)
list one E810-CQDA2 dual-port 100Gb adapter, while Ceph lists two single-port 400Gb
InfiniBand NDR/Ethernet adapters. Actual mode, negotiated speed and role-specific
switch/bond compatibility remain unconfirmed; the label is not achieved throughput.
The proposer reports that the E810 card cannot provide the required true 200 Gbit/s
through-card bandwidth and probably needs replacement. The [NIC issue](../Hardware/datacenter-hardware.md#intel-e810-cqda2-bandwidth-issue)
has no selected replacement or estimated lead time. It does not reopen completed
AM4 switch firmware or DCM work. Qualify actual compatibility, failure behaviour,
capacity and contention; neither a port count nor the word redundant proves usable
aggregate capacity or independent failure domains.

The **17 October** report assumes VRFs have been configured, but supplies **no
details**. Allocation, routing interaction and security enforcement are therefore
**not established**. The VRF increment must explain how VLANs,
VRFs and actual filtering protect management and tenants on the converged physical
path. Qualify contention and link/device failures across storage and other traffic;
logical separation alone does not provide independent physical capacity or trust.

Keep the physical fabric distinct from the Kubernetes cluster network. This
proposal does not replace the CNI or prescribe that the tenant cluster's overlay
must use the same encapsulation as the datacenter fabric. The selected OpenShift,
HCP, NIC, switch and storage configurations need a combined support and integration
assessment. Address/IPAM authority, privilege boundaries and approved change
ownership are prerequisites to safe automation, not benefits obtained merely by
installing a controller.

## Service Description

The network provider supplies the agreed connectivity and separation contract;
the CLaaS provider owns its cluster-side integration and tenant-facing promise.
Network operations, platform operations and tenant responsibilities must agree
on where each path is diagnosed and restored. On **2026-10-14** the proposer
assigns networking work, including this fabric and its DCM feature, to the
**Networking domain**, with its own architects. Detailed network design belongs
there; the CLaaS team specifies its consumer requirements and acceptance paths.
The **17 October** agreement names **Quanza** as owner of all four Phase 1 fabric
features. The individual architect, service operator for Cisco Nexus Dashboard and
formal acceptance authority remain unrecorded. Networking is an explicit domain
assignment, not inferred from the subject folder. DCM is already reported complete;
the new feature points replace the broad fabric range.

## Roadmaps

The delivery block is now a **zero-additional-work Phase 1 milestone** over the
three pending increments. The explicit order is **firmware → VRF setup/details →
100 pre-provisioned VLANs → orchestrator integration**, with VRF and VLAN order
swapped from the proposer's initial list as explicitly requested. All four feature
outcomes are Quanza-owned. The firmware capability is already available in AM4,
so VRF work references it architecturally rather than waiting on new firmware work.
The next increments each depend on the previous pending outcome; integration also
requires the separately available orchestrator service. No parent/child cycle is
introduced, and DCM/IPMI consumption is not gated on this new automation foundation.

The three proposed durations total **80 scheduling hours (ten working days)**
under the existing eight-hour weekday convention, only after their inputs and
external service availability are satisfied. They are not dates or a resource-levelled
commitment. The old aggregate and the completed firmware 40/40 are not added again.

Broader multisite overlays, stretched Layer 2, additional tenant patterns and
fully self-service network provisioning are candidates for later scope unless
the first consumer's requirements make them necessary. First-release deferrals
must preserve required isolation, availability and recovery. A controlled
operator-assisted workflow may be considered instead of full automation; it
still needs review, repeatability, ownership and an auditable result.

## EVPN/VXLAN firmware installation

**Outcome and owner:** Quanza installs the EVPN/VXLAN firmware baseline on the
in-scope switches. The proposer reports this **already completed in AM4** on
**2026-10-17**, and reports basic configuration that permits VLAN provisioning.
No actual completion date, switch inventory or installed release was supplied.
Readiness is therefore recorded for **AM4 only**, on the basis of the report,
not a tested support matrix or proof that another site has the same baseline.

The supplied **40 engineering / 40 scheduling hours** are the feature's budget,
not measured effort spent. There is **no next firmware increment planned for
this reported-complete scope**, so no `delivery` block or invented actual finish
is added. VRF work consumes this available capability. Its conservative **17
October earliest start** prevents planning before the confirmation boundary;
that is not the firmware installation date. Another site or later firmware change
would need its own explicit scope and readiness, not an assumed AM4 result.

## VRF setup and separation details

**Outcome and owner:** Quanza establishes and documents the required **tenant,
platform and storage traffic separation**, including VRF allocation, VLAN mapping,
permitted routing/handoffs and where filtering enforces the boundary. The proposer
assumes VRFs are configured but has **no details yet**. Existing configuration may
be reusable; it is not accepted isolation evidence or a completed increment.

Acceptance needs a usable description of the actual boundaries and confirmation
that the required paths work while unauthorized cross-boundary traffic is refused.
A VRF name alone is not an access-control guarantee. The feature remains
**proposed**, with unknown readiness and a supplied **32 engineering / 32
scheduling hours**. It consumes the reported-ready AM4 firmware capability; it
does not wait for another installation or infer a firmware finish date.

## 100 pre-provisioned VLANs

**Outcome and owner:** Quanza makes a set of **100 pre-provisioned VLANs available**
for the Phase 1 consumers, with their identifiers, permitted use and VRF/traffic
boundaries documented. Basic configuration is reported to allow VLAN provisioning;
neither that report nor the older couple-dozen-VLAN baseline proves all 100 ready.
The number does not imply one VLAN per tenant, 100 tenants or an approved allocation.

The supplied budget is **8 engineering / 8 scheduling hours**. Delivery is
**proposed**, with unknown readiness. The proposer explicitly orders this outcome
**after the VRF setup/details increment**. This is a planning sequence, not a
claim that a vendor technically forbids creating VLANs earlier. Acceptance checks
the full agreed set and its usable consumer mapping, not just the ability to
create a single VLAN.

**Ceph consumer handoff — 19 October 2026.** The proposer confirms that Ceph can be
installed and operated when connectivity is established and the pre-provisioned
VLANs can be consumed. For that consumer, this existing feature hands over usable
host/storage paths within the agreed VRF boundaries, not just a list of VLAN IDs.
Required addresses must come from the authorized allocation authority and the
permitted paths must work; a VLAN count alone does not prove connectivity. No
addressing details or path-test evidence were supplied by this clarification.
The handoff remains proposed with unknown readiness, using its existing **8/8-hour**
budget rather than adding another network task. It does not wait for Nexus
Dashboard onboarding. The complete fabric milestone retains its broader DNS/IPAM
baseline and orchestration prerequisites; those are not copied into this scoped
Ceph start gate. Completed DCM connectivity and AM4 firmware are unchanged.

## Integration into the fabric orchestrator

**Outcome and owner:** Quanza integrates the Phase 1 fabric into the separately
available [Cisco Nexus Dashboard service](nexus-fabric-orchestrator.md).
This **40 engineering / 40 scheduling hours** covers **fabric onboarding and
integration**, not installing or funding that service a second time. It follows
the 100-VLAN outcome and requires the new service to be available. Delivery is
**proposed** and readiness remains unknown.

Acceptance identifies the fabric and configuration baseline in the service,
qualifies scoped operator/API access and the intended supported integration path,
and records which system owns each configuration value. Git, Nexus Dashboard and
manual administration must not become competing writers. This feature demonstrates
the actual AM4 onboarding; the service's own Fabric Management and Manage features
only enable that function and scoped API access. Exact release, credentials and
interfaces remain to detail with the service owner; no supported deployment or
working integration is inferred from the product name.

This creates the **foundation for future network automation**. Any network/fabric
automation must consume the available orchestration service first, but full
dynamic VLAN self-service or a new tenant-network automation workflow is not
silently added to Phase 1. Existing ACM-driven IPMI provisioning and completed DCM
connectivity are not retroactively blocked by the new service.

## Effort scenario: evpn-vxlan#vrf-setup

**Workstream:** Foundations.
Proposer-supplied conditional-completion point, dated **2026-10-17**.

| Work package | Low h | Working h | High h |
| --- | ---: | ---: | ---: |
| Establish and document the required tenant/platform/storage VRF separation | 32 | 32 | 32 |

**Duration: 32 scheduling hours.** Low confidence while the assumed existing VRF
configuration and its boundaries remain unverified. Equal bounds encode the
supplied point, not an independently assessed range or a verified remainder.

## Effort scenario: evpn-vxlan#pre-provisioned-vlans

**Workstream:** Foundations.
Proposer-supplied conditional-completion point, dated **2026-10-17**.

| Work package | Low h | Working h | High h |
| --- | ---: | ---: | ---: |
| Make and qualify the agreed set of 100 pre-provisioned VLANs | 8 | 8 | 8 |

**Duration: 8 scheduling hours.** Low confidence until the 100-VLAN set, consumer
mapping and actual remainder are confirmed. This does not count firmware again.

## Effort scenario: evpn-vxlan#orchestrator-integration

**Workstream:** Foundations.
Proposer-supplied conditional-completion point, dated **2026-10-17**.

| Work package | Low h | Working h | High h |
| --- | ---: | ---: | ---: |
| Integrate the fabric into the separately available orchestration service | 40 | 40 | 40 |

**Duration: 40 scheduling hours.** Low confidence until the service, supported
interface and actual integration remainder are known. The service's own
40/40-hour setup is budgeted in its own note, not included here.

## Landing Locations

The first CLaaS scope is **AM4**, confirmed on **2026-10-20**, retaining one location
with local redundancy. Its reported hardware inventory is 64 nodes across four
racks; exact host/rack mapping, fabric attachment details and management-platform
placement remain unresolved. The rack count does not prove independent failure
domains or select a Nexus Dashboard hosting location. Do not infer a
stretched fabric or additional location from the end-state ambition. Record the
management platform's bootstrap and recovery dependencies separately from the
network it will manage.

## Available SBBs

The newly required [Cisco Nexus Dashboard service](nexus-fabric-orchestrator.md)
has its **own SBB and Phase 1 delivery item**, in **Networking**. This is the
proposer's service direction, not institutional approval or a verified Cisco SKU.
On **2026-10-17** the proposer identifies the product as **Cisco Nexus Dashboard**,
current 4.x line with integrated fabric management, replacing the earlier wrong
working name. The previously examined Cisco DevNet documentation distinguishes
**Nexus Dashboard Fabric Controller (NDFC)** legacy interfaces, the unified
**Manage** fabric APIs, and **Nexus Dashboard Orchestrator (NDO)** orchestration
for multisite/multifabric management (N2). In the selected direction, Manage is
Nexus Dashboard's API/configuration capability and NDFC a legacy function, not a
separate product. NDO and Network Services Orchestrator (NSO) are not this product
and are not required in this phase. The exact release remains to select.

The examined documentation calls Infra, Manage, One Manage, Analyze and
Orchestration APIs GA from 4.2.1 and describes legacy API deprecation in 4.3.1.
The latest non-prerelease CiscoDevNet Ansible NDFC collection observed was
**3.13.0**, published **2026-08-27**, with stated ND **4.3.1** support (N3).
That collection release is not a selection of the network-management product,
an assurance of latest product GA, or proof of compatibility with our switches.
The Cisco product pages returned HTTP 403 during consultation; latest product
patch, lifecycle, hardware support and licensing remain unverified. Avoid choosing
a legacy API from its familiar name without checking the intended release.

Qualify the selected service against scoped API roles, inventory and fabric onboarding,
configuration preview/deployment, repeatability, drift/change handling, failure
recovery and the owned integration with [automation](../Automation/intent-to-runtime.md).
Establish which system owns each configuration value; Git-reviewed intent and a
controller must not become competing writers. Reliability and operational savings
need representative evidence, not the product name alone.

## Interfaces

Describe host attachments and L3 handoffs, tenant/shared-service routing, IPAM/DNS
allocation, telemetry and the management API separately. The
[external Ceph proposal](../Storage/external-ceph-csi.md) needs a verified path
from its actual consuming nodes to the required Ceph services. It does not imply
that storage replication traffic and tenant traffic share one unrestricted network.
The [hosting contract](../Platform/openshift-service-boundaries.md) owns the
integration of these paths with HCP and tenant execution.

## DCM network

The **DCM (DataCenter Management) network already exists in RWS infrastructure**.
In RWS notation it is a highly secured network used only to manage critical
datacenter infrastructure. The proposer's clarification of **2026-10-14** defines
this feature as extending that existing service to the new DC 3.0 switching
setup and connecting **all server IPMI interfaces** to it. It is not a new
standalone management-network service. Its consumer scope and progress remain
separate from the tenant/platform fabric outcome.

**Required outcome.** The new EVPN/VXLAN switching setup makes the existing DCM
network operationally available to the IPMI interfaces of the
[datacenter hardware](../Hardware/datacenter-hardware.md). The consumers are
platform engineers accessing server IPMI and the platform accessing IPMI for
**ACM-driven provisioning**. HPE OneView is another management consumer, not a
claim that its separately planned enrolment/configuration work is complete.

**Design responsibility.** This feature belongs to **Networking**, with detailed
design and the handoff to the existing DCM infrastructure owned by that domain's
architects and delivery process. The proposer suggests a management VRF with a
VLAN connecting the new IPMI interfaces to DCM. This is a **design hypothesis**,
not an approved topology or an implementation instruction. Networking must define
the actual attachment, routing, filtering, resilience and controlled recovery
access in the design. A VLAN or VRF alone does not establish the secured boundary.

### Reported DCM completion — 17 October 2026

The proposer confirms that **DCM networking on the EVPN/VXLAN setup is implemented
and complete**. **Quanza owns completion**. This supersedes the 14 October
"mostly done" report and its 16 engineering / 40 scheduling hours of future work.
The scoped network capability is recorded as **ready on the basis of this report**,
not an independently inspected deployment or security test. No configuration
revision, test report or actual completion date was supplied.
The proposer explicitly confirms that the **completion date is unknown**. No
start or finish date is inferred from the report date. Capability readiness is
**ready**, with the dated report as its stated basis, and **no next delivery
increment is planned**. The optional `delivery` block is therefore omitted rather
than keeping a fictitious unknown future task or inventing an `actual_finish`.
Quanza's completion ownership remains recorded here. Consumers retain their
architectural dependency on this capability, but do not wait for new DCM work.
The earlier undated delivery placeholder incorrectly blocked IPMI scheduling and
is superseded by this distinction between available capability and future work.

The access requirement is platform engineers reaching server IPMI and the platform
reaching IPMI for provisioning from ACM. "Consumer handoff" means making those
network paths usable, not another service, milestone or extra budget. Completion
does not mark the broader fabric, IPMI/BMC configuration or OneView enrolment done.

**Access boundary.** Permit named platform engineers through approved management
paths, HPE OneView, and the authorized OpenShift nodes/provisioning identities.
The OpenShift path must work from the nodes' bonded 100G interfaces to the IPMI
interfaces on DCM. This is scoped infrastructure-management access, not blanket
access for tenant workloads or every cluster. Tenant workloads, public networks
and general office networks remain refused. Networking must qualify the permitted
and denied paths and define controlled emergency access; no security approval or
compliance is claimed by this note.

**Records and dependencies.** Addresses and names remain under the
[DNS, DHCP and IPAM](dns-dhcp-ipam.md) authority. The proposer expects interfaces
to be defined in the [DCIM service](../DCIM/dcim-service.md), identifying **NetBox**
as the intended tool. That record is useful for planning and evidence, but **DCIM
is neither an architectural nor a delivery prerequisite for this feature**.
DCM connectivity must not depend on NetBox being available. The separate hardware
features retain their own inventory requirements. Addressing is an implementation
detail needed by this completed network outcome, **not new separately priced DCM
work**. The architectural address-authority relationship remains; its former
DNS/IPAM delivery start gate is removed so confirmation work for other consumers
does not retroactively block completed DCM connectivity. The separately budgeted
tenant-zone delegation feature is different scope and remains unchanged.

**Network acceptance boundary**, for all in-scope new server interfaces:

- Platform engineers can manage the new hardware through its IPMI interface over
  the approved DCM access path.
- The platform has the permitted IPMI network path for ACM-driven provisioning,
  including the previously described bonded 100G node attachment where used.
- Authorized management consumers have the required network reachability. BMC
  accounts/settings and OneView provisioning remain separately owned increments.

Retained technical evidence should identify the interface/node scope, configuration
baseline and permitted/denied-path results. No such test records were inspected
in this clarification; the source is the proposer's completion report. DCM owns
the network path; BMC configuration and OneView provisioning work remain owned
by the OneView features and referenced by the hardware acceptance milestones.
Prepare the necessary test interfaces during integration, without adding a
circular gate on completing those hardware features. DCM does not wait for the
whole fabric outcome or for a full OneView enrolment milestone.

**Planning.** Reported completion leaves **0 remaining engineering hours and
0 future scheduling hours** for this DCM increment. The earlier **16/40-hour**
point remains historical estimate context, not measured effort spent or another
budget to add. The OneView IPMI budget remains separate. The later **17 October**
reduced-scope agreement supersedes the broader **72/184/336-hour** fabric range;
DCM completion does not claim the new VRF/VLAN/integration increments done.
The actual finish date remains unknown; this historical gap does not prevent
planning consumption of the reported-ready capability.

## DCM remaining work and historical estimate

**Workstream:** Foundations.
Remaining-work assessment dated **2026-10-17**, based on the proposer's
[completion report](#reported-dcm-completion--17-october-2026).

| Work package | Low h | Working h | High h |
| --- | ---: | ---: | ---: |
| No remaining network work in the reported-complete DCM increment | 0 | 0 | 0 |

**Future duration: 0 scheduling hours.** The earlier 16 engineering / 40 scheduling
hours are superseded, not converted into measured actual effort or elapsed time.
Confidence remains low in the absence of inspected implementation evidence; the
zero remainder reflects the reported completion, not an independent test result.
No new addressing, access-handoff, BMC configuration or OneView enrolment budget
is added to this completed network feature.

## Dependencies

[DNS/DHCP/IPAM](dns-dhcp-ipam.md) provides address and naming authority; DHCP is
needed only for attachment patterns that use it. Identity and secrets controls
must cover privileged management/API access. Inventory and automation need a
deliberate handoff, and recovery must remain possible when the normal controller
is unavailable. These are architecture responsibilities, not automatically serial
roadmap tasks; additional delivery edges need an actual readiness condition.

## EIRA Alignment

An applicable EIRA mapping has not been established. This note does not infer
one from its folder, protocol or vendor candidate.

## Primary evidence and next iteration

Consulted **2026-10-09**. N1 is the standards baseline; N2 is the currently served
API documentation (release 4.2 and later), not an immutable product-release record.
N3 is a pinned automation-collection release. None is observed deployment evidence.

| Ref | Primary source |
| --- | --- |
| N1 | [RFC 8365, Network Virtualization Overlay using EVPN: sections 1, 4–5, 8 and 11](https://www.rfc-editor.org/rfc/rfc8365.html) |
| N2 | [Cisco DevNet, Nexus Dashboard API v1 introduction and API availability](https://developer.cisco.com/docs/nexus-dashboard/) |
| N3 | [CiscoDevNet NDFC collection 3.13.0 release](https://github.com/CiscoDevNet/ansible-dcnm/releases/tag/3.13.0); [latest-release lookup](https://api.github.com/repos/CiscoDevNet/ansible-dcnm/releases/latest) |

The broader design agenda above remains context, not another set of promised
Phase 1 features. The **17 October** agreement now supplies the small scope and
feature points, and the Cisco Nexus Dashboard service has its own feature budgets;
its release, hosting, owner and actual progress remain to detail. Full topology and implementation configuration
remain Networking design work, not fabricated by these planning notes.