CLaaS — March 2027 roadmap
This roadmap explores the first CLaaS offering, with tenant clusters based on Hosted Control Planes and a target of 31 March 2027. The source observation date records this proposal's first discussion baseline; it is not evidence that implementation started then. The 15 October agreement adopts a rolling start: while no planned start date is set, the calculation uses today in Europe/Amsterdam. Source observations, actual dates and the March target do not move with that clock.
What this first roadmap establishes
The selected items are a small, provisional dependency-backed scope for review. They are not an exhaustive plan or a declaration that the base infrastructure is ready. Each item's authoritative delivery state, estimates and prerequisites live in that item's own frontmatter. This note selects the items and target; it does not copy their data into a second plan.
The source now has low/working/high effort estimates
for its outcomes, owned by each note/feature's delivery.effort_estimate and linked
to its narrative work breakdown. After round 2, two low-confidence ranges estimate
identified remaining work from reported progress; the 14 October DCM and hardware
clarifications add supplied remaining-work points for DCM, firmware and OneView
enrolment. The 15 October DNS clarification adds a 16-hour remaining-work point
for tenant-zone creation/delegation, replacing the earlier mixed DNS placeholder;
baseline address/naming confirmation remains unestimated. Other estimates retain conditional
completion basis. The Quay feature agreement
adds supplied point budgets, encoded with equal low/working/high bounds, not
independently assessed ranges. Its supplied scheduling durations are recorded as
duration_hours, separate from engineering effort. The forecast uses eight hours
per Monday–Friday working day, rounding positive partial days up for displayed
date spans; unknown prerequisites still prevent a dated forecast. These are not
independently verified actuals or commitments, and named
delivery owners remain open. Keycloak is explicitly assigned to IAM;
the EVPN/VXLAN fabric and DCM feature are now assigned to Networking.
Datacenter hardware and its three features are assigned to datacenter.
Other corporate domain allocations are not yet recorded.
Those omissions are deliberate. A missing estimate remains unknown, not zero.
The generated forecast must not claim that March is achievable until the inputs
and their assumptions are credible.
The proposer identifies a dedicated OpenShift development team of seven engineers dedicated to platform work. Weekly availability and other-team participation remain unquantified; networking is concentrated in one engineer, while storage and IAM/security/PKI are external to the core team. Do not infer weekly hours, divide effort by seven, or imply that this dependency forecast resource-levels work.
A separate operations team will run production. The development-team headcount does not supply operational coverage; handover responsibilities, readiness and acceptance belong in production assurance, with exact team assignments still open.
Implementation is already underway: many activities are reported at different
stages of completion. The unattended evidence pass found no per-component actuals
or accepted results in this source. Delivery states initially remained explicitly
unknown, pending owner evidence of remaining work and blockers, not a claim that
nothing has started. The proposer has since set Quay's Phase 1 milestone and six
feature increments to proposed; its capability readiness remains unknown. No
actual dates or accepted results are inferred from that planning-state choice.
Do not manufacture actuals or move the roadmap's
observation date merely to make the forecast appear current.
Clarification round 1 on 2026-10-12 records reported progress in the owning notes: the four-role development estate already deploys HCP tenants; platform RBD and authentication automation exists; initial fabric configuration/static VLANs exist. No revisions or qualification records were supplied or inspected. Initial operating ambition is a few dozen tenants, with launch batch, profiles and capacity still open. Four ranges credit conditional reuse, while other estimates await reconciliation. Unknown metadata must not erase this progress or suggest all prerequisites start from scratch. The assessment update records the evidence boundary and counting implications. No actual dates, durations or March commitment are inferred; dependencies still need increment-level review.
Keep the main line visible
Feature-level scope keeps capability metadata inside its owning note: RBD and CephFS share the storage note; fleet integration and HCP hosting share the MCE note. The shared baseline now references Ceph's external bootstrap access contract, with live RBD consumer qualification after bootstrap. Final tenant hosting additionally requires CephFS; HCP realization references MCE's hosting feature. ACM hub/Global Hub, observability metrics/logs/audit and test-estate allocation/acceptance are also separated in their owning notes. The HCP note adds cross-controller tenant-control qualification. Their aggregate estimates are not counted again. Read the relationship audit for reasons and conservative gates retained pending decisions.
Their readiness and progress are explicitly unknown, pending the later evidence pass. Readiness describes an existing capability for its named scope; a feature's delivery block describes its next bounded increment. A scheduling prerequisite targets that increment, not every enhancement or sibling feature in the owning SBB. Existing note-level delivery remains supported elsewhere; this is a bounded first application of the model, not an assertion that every vendor feature is catalogued or that assigning unknown states establishes actual completion percentages.
The five explicitly selected outcomes remain the main line. The supporting dependency chain now includes the shared OpenShift baseline, ACM and Global Hub, MCE, OpenShift Virtualization, HCP, DCS, Keycloak and OpenBao. The existing network and Ceph blocks remain visible through the shared baseline. All retain their own note and metadata; no separate plan database is introduced.
The agreed TOPdesk-to-reviewed-merge provisioning flow also makes automation qualification an explicit supporting outcome for final hosting/service acceptance. Technical HCP realization can use the reported existing dev path without waiting for that complete workflow. The intended production execution chain uses AAP to direct provider GitOps and act on external systems where needed. It must demonstrate the approved request-to-cluster path; it does not imply that every general automation capability must be finished first or that Archy commits directly provision infrastructure.
Select Hosted control planes — CLaaS cluster realization to inspect the control-plane/worker split, or OpenShift platform baseline for common foundation dependencies. Filter by IAM to inspect Keycloak and its cross-domain consumers. Domain names are authored assignments, not inferred from these nodes' subject icons or roadmap roles.
The supporting blocks describe the proposed first offering, but their detailed feature/solution choices remain drafts. The 17 October reduced network scope now requires a separate fabric orchestration service and fabric integration in Phase 1 as the foundation for future network automation; it does not promise a full automation programme. The storage path models the upstream direction for review; it does not commit to removing all ODF consumers before March. No assigned architect or delivery date is inferred from a product or subject name.
The roadmap's hosting duration, when estimated, describes final integration and demonstration. The shared OpenShift baseline is estimated once; provider bootstrap owns initial cluster installation, and each concrete role separately accounts for subsequent role-specific setup and integration work. Earlier architecture and feasibility work may proceed in parallel; the dependency order does not claim that design waits until all infrastructure is complete.
Current service use versus later placement
The provisioning flow now depends on AAP on DCS and GitOps on the ACM/Global Hub cluster. Both use external GitLab initially. Their service-readiness outcomes are separate from the full workflow demonstration, so the same setup effort is not counted twice. A possible later Forgejo service on DCS is not part of the initial dependency chain. The independent bootstrap of these hosting clusters uses the selected external engineer-run bootstrap. That distinct outcome creates the initial cluster substrates; Keycloak is then established on DCS before the provider roles complete IAM-integrated readiness. This is not a claim that initial installation and production readiness are the same milestone, or that bootstrap credentials may bypass required authorization.
Existing external OpenBao is the current prerequisite. Its later DCS placement is documented in the OpenBao SBB, not added as a return dependency that would require DCS to exist before obtaining the credentials to build DCS. Existing service availability, permissions and integration still need verification, so the item is not marked done merely because the service exists.
Keycloak's upstream will use the available organizational federation: existing AD-backed federation or the IAM team's newer Keycloak-based service, subject to readiness and qualification. Tenant IAM self-service covers own-cluster groups and memberships. Platform-engineer MFA, tenant MFA opt-in and at least two break-glass accounts per provider/platform cluster are recorded in its owning note; tenant-cluster break-glass coverage is a stretch goal. Realm topology remains open. Authentication uses Keycloak when possible and native identities when needed, without making initial bootstrap depend on its own future IdP.
The first-release service boundary now explicitly requires all four platform roles for March, including DCS and Global Hub. DCS's actual installed-service inventory remains open; reusing organizational services does not silently remove the DCS role from this scope. This is the assignment's scope choice, not a technical requirement of the HCP mechanism. The ACM/MCE enrollment/support arrangement and the precise bootstrap/access handover still need design and evidence; this graph cannot certify the topology.
The 2026-10-12 DCS refinement now separates five consumable features within
that deliverable. Its local DNS/certificate/secret platform, namespace access and
minimal VM capability are service-use prerequisites; ACM import and the hard
all-installed-workloads independence demonstration are later acceptance. Both
issuer paths remain required, including the unresolved public-validation support
gate. Shared MetalLB packaging/pool controls are referenced through
metallb-bgp#pattern, not the tenant-ingress demonstration after HCP. The DCS
milestone adds no duplicate engineering hours; the owning note holds its feature
estimates and rough sequence. No durations or forecast dates were inferred.
The general March CLaaS scope is one location with local redundancy, using network and compute hardware reported available by the proposer. The Quay-specific 2026-10-12 Phase 1 scope now requires one platform-only instance per datacenter; second-site hosting readiness and alignment with the March target remain to qualify. This does not silently expand every other CLaaS service to two sites. No numeric availability, site-loss continuity or sufficient-capacity claim is inferred.
Application-service readiness
The first tenant offer now includes RBD and CephFS through the volume contract, plus a separate S3 object service. It also includes a platform-provided workload protection mechanism and MetalLB BGP application entry points for internal and internet-facing applications. Organizational DNS/IPAM is reused and its consumer contract is a shared prerequisite.
MetalLB and workload-protection qualification use a representative HCP cluster; they feed final hosting/recovery acceptance, not a circular prerequisite for creating that same cluster. The object service now selects Ceph RGW; OADP/Velero uses the existing organizational Cohesity destination, and MetalLB is operated by the provider inside each tenant cluster. Tenant APIs/consoles stay private. The public application perimeter reuses existing external NetScaler. Exact endpoint/API integration, data movement, BGP peer/pool controls and the perimeter handoff remain open. No working integration, duration or service guarantee is inferred from these choices.
Certificate lifecycle now qualifies provider-managed cert-manager in each provider and tenant cluster, with the existing external OpenBao service supplying the intended internal issuer interface, alongside Let's Encrypt. DNS-PERSIST-01 is confirmed intent with an explicit support qualification gap. Any DNS-01 contingency will be decided after qualification, not selected silently. The operational Quay service on DCS serves platform content only. Its Phase 1 feature set now separates base installation, platform-engineer/cluster access, OpenShift installer/Operator/ marketplace sync and image scanning. The owning note's zero-cost milestone requires all four; the summary counts each feature once. Global upstream and separate CLaaS tenant Quay are stretch scope, excluded from this roadmap's dependency closure. The tenant image-source contract is separate, with existing external Harbor a tentative preference rather than a confirmed selection. Initial bootstrap images come from approved external registries; their exact source and access contract remain open. Initial trust must also work before in-cluster certificate controllers exist. These feed final service acceptance rather than retroactively providing their own bootstrap prerequisites. MetalLB peers at the EVPN leaf layer; exact routing and prefix policy remain open. The external perimeter and tenant-image contracts feed final hosting acceptance; neither is made a prerequisite to bootstrapping its own test environment.
The observability outcome qualifies per-cluster stacks and central ACM multicluster roll-up after the hub role and a representative tenant cluster exist. It includes isolated own-cluster visibility, the intended shared application-logging capability and external Splunk audit forwarding. OpenShift Logging with Loki is selected for logging, while its topology and exact contracts remain open. The organizational egress contract separately qualifies tenant runtime outbound access. Public NetScaler publication follows the existing organizational process, not new appliance automation. These feed final service acceptance without reversing the bootstrap dependency order.
The separate qualification environment has an allocated-substrate feature before initial installation and representative estate acceptance after HCP, feeding production assurance. Both must be established, not assumed from production hardware inventory. The shared platform baseline selects latest compatible stable releases to qualify together and pin; no exact deployment version or floating-update policy is inferred.
Tenant access and lifecycle
The tenant application offer now includes OpenShift GitOps with tenant repository onboarding, separate from central provider reconciliation. It follows representative HCP readiness and feeds final hosting acceptance. Each tenant cluster hosts its own instance, with organizational GitLab as the initial allowed source host. Approved complete retirement is another supporting outcome feeding the offering milestone, with data and backup disposition governed by policy. Neither outcome is made a prerequisite to creating its own test tenant.
API-side MetalLB configuration is allocated to the MCE role, with actual private API reachability demonstrated by HCP realization; tenant application ingress remains the later MetalLB application outcome. MCE's own management API stays on the Agent-based Installer API VIP/keepalived arrangement for this project; research into an alternative is stretch scope, not a MetalLB handover commitment. Qualify the selected endpoint and recovery configuration. The hardware note owns the role-specific adapter configurations and the E810 workaround. Actual link rates, switch/bond compatibility, VRF interaction and security enforcement remain to qualify. Ceph-side entitlement increases use the organizational storage-service process rather than an assumed tenant self-service quota mechanism.
Tenant-local Argo CD administration and access to authorized Operators must remain within the provider-protected boundary: reject incompatible Operator privileges. A curated Operator marketplace is stretch scope; preventing tenant changes to platform-managed components is not. Existing organizational image-trust policy governs the workload image path, with its exact requirements and enforcement still to establish.
ExternalDNS and external-secrets now contribute reusable integration patterns to tenant provisioning after initial provider bootstrap. ExternalDNS is selected for provider and tenant clusters, with an Infoblox subzone delegated to each tenant out of the box. External-secrets serves platform-managed workloads; tenants consume external OpenBao directly. The common pattern outcomes do not double-count each rollout or supply their own initial bootstrap DNS/credentials.
Datacenter hardware
On 2026-10-13 the proposer reported the CLaaS hardware procured, with substantial unspecified work already done; the Ceph clusters and OpenShift depend on it. The datacenter hardware note now gates the Ceph backend baseline, the shared OpenShift baseline and provider bootstrap. The original 13/14 October points were BMC management 8/24 h, combined firmware management 16/32 h and OneView enrolment 32/40 h (engineering/scheduling hours). The 17 October OneView refinement below supersedes those budgets, retaining the three hardware feature IDs as proposed, zero-additional-work acceptance milestones in datacenter. It does not charge another copy of enrolment, IPMI or firmware work.
The agreed BMC/IPMI-before-enrolment and enrolment-before-role-assessment order remains. The platform team defines role settings and owns its BMC identity/setup automation; housing/infra applies and manages the Phase 1 OneView profiles and updates. BMC work still starts after operational DCM access, without a DCIM or final OneView milestone gate. The earlier 12-working-day sequence is superseded by the four OneView feature durations, not added to them. No completed readiness or resource-levelled commitment is inferred.
The later 2026-10-17 DCIM and OneView refinements below supply their Phase 1
feature budgets; the 19 October upstream Ceph plan below replaces the former
unestimated backend acceptance-only scope with five proposed feature budgets.
The 2026-10-14 DCM clarification defines the feature as
connecting the new switching setup and all server IPMI interfaces to the existing
secured RWS DCM network, in Networking. On 17 October, the proposer reports
it implemented and complete, with Quanza owning completion. The earlier
"mostly done" report and 16 engineering / 40 scheduling hours of remainder
are superseded by zero remaining work, not converted into measured actuals.
The required network paths serve platform engineers accessing server IPMI and
the platform accessing IPMI for ACM-driven provisioning. This is not another
"consumer handoff" task or a claim that BMC configuration/OneView provisioning
is complete. Addressing is part of the completed implementation, with no new DCM
budget; other DNS/IPAM consumer work and tenant-zone delegation are unchanged.
NetBox is not a prerequisite for DCM connectivity; the hardware inventory gates
remain unchanged. Readiness is ready on the proposer's report, not an
independently inspected test result. The proposer does not know the actual
completion date, and no actual_finish is invented. No next DCM delivery
increment is planned, so its former unknown delivery placeholder is removed.
IPMI retains the architectural dependency on the ready DCM capability, not a
wait for future network work. Its conservative 17 October earliest start is
the confirmation boundary, not a fabricated DCM finish date. The roadmap
observation date is not moved to invent an actual.
The hardware expansion grew the supporting closure from 55 to 63 outcomes;
the five selected outcomes, dates and target were unchanged. Hardware models, node
counts and rack positions were not supplied at that stage. The existing dev estate and Ceph
service remain reported working. Those historical reports are not evidence that
the later upstream Ceph feature plan is complete or an instruction to reinstall them.
On 2026-10-19, the proposer supplies Control, Worker, Ceph and GPU hardware profiles and confirms delivery, racking and network patching complete. The 20 October report adds 8 Ceph, 8 GPU, 24 Worker and 24 Control nodes per datacenter: 64 nodes across four racks, with AM4 as the Phase 1 starting site. Per-cluster/environment allocation, rack/port mapping and accepted management/firmware results remain open. The hardware acceptance milestone is now proposed, with its existing 0/0-hour accounting and the four OneView-owned 56 engineering / 64 scheduling hours unchanged. This permits conditional dates through that management chain, not an actual acceptance or a complete hardware forecast. The E810-CQDA2 bandwidth issue may require a different NIC; its replacement scope, effort, duration and procurement lead time are unestimated and excluded from those dates, not priced as zero. No replacement model, approval, delivery date or additional site is inferred. The proposer further confirms that the workaround allows Phase 1, but the issue must still be fixed. Permanent remediation remains required, high-priority follow-up, not a Phase 1 hardware-handoff prerequisite; no later phase or fix deadline is invented. Workaround implementation and limits remain to document. Budgets, readiness and scheduling dependencies are unchanged by this clarification. The recorded hardware/OneView work covers the initial AM4 inventory once; the node and rack counts do not multiply budgets or add a second datacenter to Phase 1. The proposer further confirms on 2026-10-20 that this same AM4 hardware supports development and the eventual production offering targeted for the end of Q1 2027, not two separate 64-node estates. This retains the existing 31 March 2027 target, not an accepted finish forecast. The separate-production-build plan is unchanged; concurrent operation, host allocation and transition windows are not established by physical reuse. Budgets and scheduling dependencies remain unchanged.
Upstream Ceph backend — Phase 1
On 2026-10-19, the proposer selects an upstream Ceph installation, consumed for volumes through ceph-csi instead of ODF. Ceph clusters now owns five proposed features: base install 16/24, setup and tuning 40/40, RBD availability 16/16, CephFS availability 16/16, and RadosGW availability prepared for multisite/multiregion 40/40 (engineering/scheduling hours). Their totals are 128 engineering / 136 scheduling hours, counted once; the parent is a zero-additional-work milestone over all five features. The proposer assigns the backend milestone, its features, ceph-csi integration features and tenant RGW/S3 delivery to datacenter; named owners remain open.
Base install requires hardware acceptance and established connectivity over consumable pre-provisioned VLANs, after VRF separation. The 19 October clarification gates Ceph installation and operation on that scoped handoff, not Nexus Dashboard onboarding or the complete fabric milestone. Setup/tuning follows installation. The three capability outcomes then have no assumed sibling dependency or confirmed parallel staffing. Consumer access waits for setup/tuning; RBD, CephFS and tenant S3 qualifications wait for their particular backend availability. Final hosting acceptance consumes the complete backend milestone. This avoids making initial block-storage integration wait for RadosGW or CephFS delivery. Ceph bootstrap access and tenant S3 integration also use the VLAN handoff instead of the whole-fabric scheduling gate. Their other prerequisites remain unchanged, including the tenant object endpoint's DNS/IPAM contract. Authorized Ceph addressing is part of the network handoff, not permission to invent allocations or readiness.
Consumer integration estimates remain separate and unchanged: no second backend installation, pool/rights setup, hardware tuning or gateway preparation is counted there. Capability readiness remains unknown. Release, support, ownership, production criteria and actual progress remain open; no dates, extra sites, active replication or ODF migration are inferred. The summed scheduling hours are not an elapsed commitment, and the full forecast remains incomplete on other prerequisites.
DNS/IPAM readiness and tenant delegation
On 2026-10-15, the proposer reports that address allocations probably exist but their details are not yet available, most naming/resolution setup is already present in the existing service, and the team has access to the relevant platform zones. These are reported progress, not accepted allocation or resolution evidence. The baseline DNS/IPAM outcome is set to proposed, with no confirmed remaining duration or engineering estimate and no verified completion. Existing service presence must not be treated as a new build or as proof of the specific consumer contract.
The separate tenant zone creation and delegation feature arranges platform-engineer and scoped service-account authority to create zones and delegations, giving each tenant control limited to its own zone. It is proposed, in Networking, with 16 engineering hours of remaining work and 40 scheduling hours. Its qualification includes permitted zone creation and tenant changes, denied parent/cross-tenant changes, and an owned handoff. No permission grant or zone creation was performed by authoring these notes.
This feature feeds ExternalDNS qualification, and through it tenant onboarding; DCM and initial bootstrap do not wait for tenant zone-creation rights. The earlier 28/64/128-hour DNS placeholder combined these scopes and is superseded, not added again. That clarification produced a historical closure of 64 outcomes; its five selected main-line outcomes and target were unchanged. Baseline DNS/IPAM confirmation remains outstanding for EVPN/VXLAN and provider bootstrap; it does not reopen completed DCM connectivity or gate IPMI configuration. OneView-service and DCIM readiness still gate later enrolment. The independent zone feature can show a conditional forecast using the agreed rolling-today default. The authored observation date remains 9 October; it is separate from the displayed calculation date. No earliest availability or fixed start was supplied for that feature. A later fixed roadmap start replaces the rolling default; proposed dates remain forecasts, not agreed bookings.
External NetBox service — Phase 1
On 2026-10-17, the proposer confirms that NetBox is consumed from an external service outside the CLaaS platform, expected to enter production "soon" and replace legacy OpenDCIM. No dated availability, completed migration or verified service readiness is inferred.
DCIM and its three Phase 1 increments are now proposed, in datacenter: base installation and basic configuration with authentication (8 engineering / 16 scheduling hours), base data model (24 / 24 hours), and initial import of all DC 3.0 hardware (8 / 16 hours). These are supplied point budgets, not independently assessed ranges or verified remaining work. The owning features retain unknown readiness and conditional-completion basis; the aggregate milestone adds no duplicate hours. Total recorded engineering effort is 40 hours.
The agreed order is base install → base data model → initial hardware import: the model's delivery frontmatter requires completed installation, and import requires both. This is 56 scheduling hours (seven working days) of sequential work once the inputs are available, not a committed delivery date. DCIM remains a gate for OneView enrolment and subsequent firmware work, not for DCM connectivity or BMC setup automation. No DCS hosting or future CLaaS identity dependency is added for this external offering. That refinement produced a historical closure of 67 outcomes, with the five main-line outcomes and March target unchanged. Stretch goals remain undefined and outside this increment. The subsequent OneView refinement below records its existing service and hardware delivery features, preserving this NetBox dependency order.
Existing HPE OneView service — Phase 1
On 2026-10-17, the proposer confirms an existing HPE OneView setup, hosted on VMware on the existing production network and operated by housing. Consuming that service in Phase 1 has no architectural dependency on the new EVPN/VXLAN fabric; the separate IPMI feature still qualifies the DCM path to the new DC 3.0 hardware. OneView and its four Phase 1 increments are proposed, in datacenter:
| Feature | Engineering h | Scheduling h |
|---|---|---|
| All DC 3.0 hardware provisioned in OneView | 8 | 16 |
| IPMI access and configuration complete | 8 | 8 |
| Hardware/firmware profiles for all DC 3.0 hardware roles | 24 | 24 |
| Firmware updated for all DC 3.0 hardware components | 16 | 16 |
The 56 engineering hours replace the overlapping earlier hardware budgets, not supplement them. The original hardware feature IDs retain their acceptance boundaries with zero additional effort/duration; all four implementation budgets are owned by OneView. Existing service availability does not prove completed provisioning, profiles, firmware rollout or licensing/support qualification. The supplied points use conditional-completion basis with unknown readiness; the earlier remaining-work classifications are not carried forward as fresh actuals.
Explicit feature prerequisites preserve IPMI → hardware provisioning → profiles → firmware updates. IPMI consumes the already-ready DCM capability; NetBox/DCIM additionally gates provisioning. There is no pending DCM delivery gate. The existing service is consumed before the aggregate OneView milestone is complete; no feature waits on its own parent milestone. The sequential durations span 64 scheduling hours (eight working days) after external inputs are available, not a guaranteed delivery date. No new OneView installation or VMware migration is added. With completed DCM retained as a capability rather than future work, that refinement left 70 scheduled outcomes, before the reduced-network expansion below. The five main-line items and March target are unchanged. DCM's readiness, unknown historical completion date and Quanza ownership remain in its source note and architecture relationships; it is not displayed as a pending task on the future-work timeline.
Reduced EVPN/VXLAN scope — Phase 1
On 2026-10-17, the proposer deliberately reduces the fabric delivery scope for short-term feasibility. Quanza owns all four selected feature outcomes, in Networking:
| Feature, in the agreed order | Engineering h | Scheduling h | Recorded situation |
|---|---|---|---|
| Firmware installation | 40 | 40 | Reported complete in AM4; budget context only, not measured actuals or future work |
| VRF setup and separation details | 32 | 32 | Proposed; configuration assumed present, but no details supplied |
| 100 pre-provisioned VLANs | 8 | 8 | Proposed; basic configuration permits provisioning, not proof all 100 available |
| Fabric-orchestrator integration | 40 | 40 | Proposed; requires the separate orchestration service |
The requested order is firmware → VRF → VLANs → integration, explicitly swapping VRF and VLANs from the initial list. Each pending delivery waits for the previous pending outcome. Completed firmware is a ready AM4 capability, with no fictitious future installation or invented completion date; VRF work consumes it architecturally with a conservative 17 October confirmation boundary. This is not a claim about firmware at other sites. Completed DCM and the existing IPMI planning fix remain independent of the new automation foundation.
The parent EVPN/VXLAN delivery is now a proposed zero-additional-work milestone over those increments, retaining its existing DNS/IPAM consumer contract. The 80 engineering / 80 scheduling hours for the three proposed features replace the old 72/184/336-hour aggregate. They exclude the completed firmware 40/40 and do not price or claim broader MTU, scale or failure/recovery qualification. Required tenant/platform/storage separation remains part of VRF acceptance; reduced scope does not imply proven security or weaken that boundary.
The new Cisco Nexus Dashboard
service is a separate Phase 1 service item in Networking, required for fabric
integration and future network automation. The proposer identifies it as the
current 4.x line with integrated fabric management; NDO and NSO are not required
in this phase. Its legacy technical id nexus-fabric-orchestrator is kept for
stable links. On 2026-10-17 the proposer supplies four feature budgets:
| Feature, in the announced order | Engineering h | Scheduling h | Recorded situation |
|---|---|---|---|
| Installation | 8 | 8 | Proposed; release, hosting and recovery not selected |
| Basic Setup (settings and authentication) | 8 | 8 | Proposed |
| Fabric Management (enable and set up) | 8 | 8 | Proposed; excludes AM4 fabric onboarding |
| Manage (API enablement and roles) | 16 | 16 | Proposed; scoped allowed/denied qualification, not full network automation |
The service parent is a proposed zero-additional-work milestone over those features, which total 40 engineering / 40 scheduling hours (five working days). Each feature waits for the previous one; readiness is unknown, and no progress was supplied. The integration's separate 40/40-hour budget onboards the fabric after the service is available. It is not counted again, and the reduced fabric's 80/80 hours stay separate. Release, placement, support, operator and delivery owner remain open; Quanza's fabric ownership is not assigned to this service. No service dependency on final fabric acceptance is invented. Unrelated AAP/GitOps or ACM/IPMI work is not blanket-gated by it.
That network refinement produced a historical closure of 78 outcomes: the four new pending service features joined the previous 74. The subsequent Ceph expansion brings the current closure to 83 outcomes. The five selected main-line items and March target stay fixed. With no external service prerequisite supplied, the service chain and the three fabric increments now receive conditional forecast dates. They are not commitments. The fabric aggregate and other unknown prerequisites still prevent a complete, trustworthy dated forecast for March.
How to review it
Start with the conditional effort summary, then follow each outcome to its work packages and assumptions. The assessment method and questions explain their conditional basis. The roadmap displays ranges, confidence, assessment dates and assumption links directly, even while progress is unknown. The summary is reproducibly derived from the same metadata; the roadmap still has no trustworthy dated forecast or resource-levelled commitment.
Open this roadmap from the website's Roadmaps navigation. Select an item to inspect its dependencies and follow the source note. Use Explore a scenario to try hypothetical duration, effort or earliest-start values. Scenario changes stay in page memory; a downloaded proposal is for manual review, not an alternative source consumed by the website.
First select the consumer and workload scope; identify existing foundation services and their owners; then determine which gaps must be closed for that scope. Record estimates in the owning notes, including their basis in prose. Assign domains using the agreed RWS vocabulary when it is available, not by guessing from subject folders or product names.
Forecast interpretation
Round 2 on 2026-10-12 confirms a separate production build using similar dev patterns. Common RBD qualification now uses the existing allocated dev substrate rather than waiting for future production installation. Full authorized provisioning demonstration gates final hosting/service acceptance, not technical HCP realization. The remaining production-role, consumer, isolation and recovery obligations remain.
The seven engineers are dedicated to platform work, with differing expertise; networking is concentrated in one engineer, and storage/IAM/security/PKI sit in other teams. Weekly engineering capacity and external participation are unquantified. December productivity is expected to be reduced, not assumed zero. The planning aim is platform availability at the beginning of March, with unforeseen-issue buffer before 31 March 2027. No exact internal date, buffer or duration is inferred.
The target stays fixed if prerequisites move. Forecasts are dependency-based, Monday-to-Friday elapsed working-day calculations with separately identified source-observation and effective calculation dates. They do not account for holidays, resource contention or probabilistic risk, and they do not infer elapsed duration from engineering hours. Independent items are assumed able to proceed in parallel. These limits matter when several items need the same team or an external change window.
Review missing inputs, forecast margin and cross-domain dependencies before treating a finish date as credible. A later forecast calls for a discussion of scope, assumptions and delivery constraints, not silently moving the target or dropping a required prerequisite. Future expansion is not part of the March commitment unless explicitly included.
Explore this note’s relationships 38 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (39)
- AAP — provisioning orchestration on DCSSBB · draft · Automation. Icon: Automation
- Intent, delivery and runtime evidenceNote · draft · Automation. Icon: Automation
- OpenShift GitOps — central provider reconciliationSBB · draft · Automation. Icon: Automation
- Operational Git — external GitLab firstSBB · draft · Automation. Icon: Automation
- OpenShift GitOps — tenant application deliverySBB · draft · Automation. Icon: Automation
- Persistent DNS validation for public certificatesResearch · draft · Certificates. Icon: Certificates
- CLaaS effort assessmentNote · draft · CLaaS. Icon: General note
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — Clusters-as-a-Service: first production offeringNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- Approved complete tenant retirementNote · draft · CLaaS. Icon: General note
- DCIM serviceABB · draft · DCIM. Icon: Inventory
- HPE OneViewSBB · draft · DCIM. Icon: Inventory
- ACM and Global Hub clusterSBB · draft · Fleet. Icon: Fleet
- MCE cluster — hosted control-plane managementSBB · draft · Fleet. Icon: Fleet
- Datacenter hardwareNote · draft · Hardware. Icon: General note
- Keycloak — shared identity providerSBB · draft · Identity. Icon: Identity
- DNS, DHCP and IP address managementABB · draft · Network. Icon: Network
- EVPN/VXLAN network fabricABB · draft · Network. Icon: Network
- ExternalDNS — provider-managed DNS integrationSBB · draft · Network. Icon: Network
- NetScaler — existing external application perimeterSBB · draft · Network. Icon: Network
- MetalLB — BGP application entry pointsSBB · draft · Network. Icon: Network
- Cisco Nexus DashboardSBB · draft · Network. Icon: Network
- Tenant workload egress — organizational serviceNote · draft · Network. Icon: Network
- CLaaS observability — local stacks and central visibilityNote · draft · Observability. Icon: General note
- DCS — Datacenter Services ClusterSBB · draft · Platform. Icon: Platform
- Hosted control planes — CLaaS cluster realizationSBB · draft · Platform. Icon: Platform
- OpenShift platform baselineSBB · draft · Platform. Icon: Platform
- OpenShift Virtualization — tenant worker hostingSBB · draft · Platform. Icon: Platform
- Provider bootstrap — external engineer-run foundationNote · draft · Platform. Icon: Platform
- Representative non-production qualification environmentNote · draft · Platform. Icon: Platform
- Tenant workload protection — platform-provided backupNote · draft · Recovery. Icon: Recovery
- Red Hat Quay service proposalSBB · draft · Registry. Icon: Registry
- Tenant application images — external Harbor candidateNote · draft · Registry. Icon: Registry
- External-secrets — platform workload secret deliverySBB · draft · Secrets. Icon: Secrets
- OpenBao — external first, DCS laterSBB · draft · Secrets. Icon: Secrets
- Ceph clustersSBB · draft · Storage. Icon: Storage
- External Ceph through ceph-csiSBB · draft · Storage. Icon: Storage
- Ceph RGW — tenant S3 object serviceSBB · draft · Storage. Icon: Storage
Relationships (39)
- CLaaS — Clusters-as-a-Service: first production offeringReferences →CLaaS — March 2027 roadmapCLaaS/index.md · Markdown link
- CLaaS — March 2027 roadmapReferences →AAP — provisioning orchestration on DCSCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Intent, delivery and runtime evidenceCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →OpenShift GitOps — central provider reconciliationCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Operational Git — external GitLab firstCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →OpenShift GitOps — tenant application deliveryCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Persistent DNS validation for public certificatesCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →CLaaS — Clusters-as-a-Service: first production offeringCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Approved complete tenant retirementCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →MCE cluster — hosted control-plane managementCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Keycloak — shared identity providerCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →DNS, DHCP and IP address managementCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →ExternalDNS — provider-managed DNS integrationCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →NetScaler — existing external application perimeterCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →MetalLB — BGP application entry pointsCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Tenant workload egress — organizational serviceCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →CLaaS observability — local stacks and central visibilityCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →DCS — Datacenter Services ClusterCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Hosted control planes — CLaaS cluster realizationCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →OpenShift Virtualization — tenant worker hostingCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Provider bootstrap — external engineer-run foundationCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Representative non-production qualification environmentCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Tenant workload protection — platform-provided backupCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Tenant application images — external Harbor candidateCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →External-secrets — platform workload secret deliveryCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →OpenBao — external first, DCS laterCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →External Ceph through ceph-csiCLaaS/roadmap.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Ceph RGW — tenant S3 object serviceCLaaS/roadmap.md · Markdown link