Red Hat Quay service proposal
Red Hat Quay is the proposed concrete OCI registry service contributing to Registry. The CLaaS clarification now selects a new Quay service on DCS for the first operational offering. Historical source S5 is not the authority for that new proposal and does not establish deployment, institutional approval or support. Exact Quay, Operator and OpenShift releases remain TBD. This note describes the service boundary; the HLD retains the broader draft topology and runtime reasoning, not automatically March commitments.
Phase 1 feature set
The 2026-10-12 scope agreement sets the Phase 1 end goal: one Quay instance per datacenter, two instances in total, for platform purposes only. This replaces the earlier one-location Quay planning assumption. It does not claim either instance is deployed or change the placement of every other CLaaS service.
Estimates are engineering hours / total duration in hours, supplied in the agreement. They are recorded once, without an inferred per-datacenter multiplier; confirm site-coverage assumptions before scheduling. Duration is not engineering effort. Summing feature durations does not forecast Phase 1 completion: sequencing, concurrency and external waits still need qualification.
| Required feature | Engineering h / total duration h |
|---|---|
| Base Quay install | 8 / 16 |
| Authentication and authorization config | 8 / 16 |
| Mirror sync of OpenShift installers, Operators and marketplace | 16 / 32 |
| Image scanning | 8 / 8 |
The four budgets sum to 40 engineering hours. The parent delivery is a zero-effort, zero-duration acceptance milestone requiring all four features; it adds no duplicate installation/integration budget. The earlier 80/192/384 h broad conditional estimate is superseded, not added. Backend, full blob/pull, trust, recovery and handover concerns remain qualification obligations; these smaller supplied budgets do not prove they are satisfied.
The CLaaS summary consumes structured effort estimates. Each supplied point estimate
is encoded with equal low/working/high values, not an independently assessed
uncertainty range. Confidence remains low pending implementation and backend/site
qualification. On the proposer's request, all six delivery features and the Phase 1
milestone are proposed. Readiness remains unknown; no actual dates are inferred.
The supplied scheduling durations are recorded as duration_hours
and contribute to date-based roadmap forecasts. The confirmed convention is eight
scheduling hours per Monday–Friday working day; these durations are independent of
engineering effort and headcount. They do not resolve missing prerequisite estimates,
external waits or other unknown inputs that limit the forecast.
Base Quay install
Estimate: 8 engineering hours / 16 total duration hours. Establish a platform-only Quay instance at each datacenter. Qualify the supported application, Operator and database/object-store/runtime-dependency contracts, trusted endpoints and complete manifest/blob pulls, not just running pods. Release/backend selection and local restore/handover evidence remain open. Two instances do not prove HA.
Authentication and authorization config
Estimate: 8 engineering hours / 16 total duration hours. Allow platform engineers to log in and issue separate service accounts/robot identities and tokens for each consuming cluster. Qualify allowed and denied repository operations, protected credential delivery and revocation. Human login does not establish robot authentication; no token-federation mechanism is selected here.
Mirror sync
Estimate: 16 engineering hours / 32 total duration hours. Synchronize the required OpenShift installers, Operators and marketplace into both datacenter registries. Identify approved sources, releases/catalogue content and sync schedule; verify complete destination content and representative cluster consumption, not just one copied image. Tool choice and associated-artifact coverage remain subject to the mirroring evidence. Phase 1 must work without the optional global tier. Independent initial bootstrap remains external.
Image scanning
Estimate: 8 engineering hours / 8 total duration hours. Enable supported image scanning and verify vulnerability findings for platform content, including feed access/freshness and unavailable-results behavior. Scanning supplies findings, not release approval or admission enforcement.
Stretch goals and later phases
These are optional additions, not prerequisites of the Phase 1 milestone or the current CLaaS roadmap closure. Include them in Phase 1 if time allows; otherwise allocate them to later phases. No later phase number, delivery date or capacity commitment is invented. Selecting them adds scope and their separate budgets.
| Stretch feature | Engineering h / total duration h |
|---|---|
| Global tiered setup | 24 / 40 |
| Separate tenant-facing Quay deployment on CLaaS | 80 / 160 |
Global tiered setup
Estimate: 24 engineering hours / 40 total duration hours. Add a third, global Quay instance above the two datacenter instances as the main internet-pulling registry; configure both datacenter instances to use it as their upstream. Qualify supported synchronization, intake and failure behavior. This does not imply automatic geo-replication, failover or native pull-through caching. The HLD's broader seed tier is not required before Phase 1 can be accepted.
Tenant-facing Quay on CLaaS
Estimate: 80 engineering hours / 160 total duration hours. Establish a separate Quay deployment on the CLaaS offering for tenant-facing registry use. This is not tenant publishing on the platform registries or a dedicated instance per tenant. Qualify CLaaS hosting, tenant access, artifact policies and operations independently. The tenant image-source contract remains separate; this stretch does not silently replace its tentative external-Harbor path. Exact placement and scheduling prerequisites still need definition.
Effort scenario: red-hat-quay
Workstream: Automation and registry. The Phase 1 milestone adds no duplicate feature work.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Acceptance milestone requiring the four Phase 1 features | 0 | 0 | 0 |
Scope and provenance are in Phase 1. Stretch work is excluded; acceptance is unknown until evidence is supplied.
Effort scenario: red-hat-quay#base-install
Workstream: Automation and registry. Supplied point estimate for base installation.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Base Quay install | 8 | 8 | 8 |
Total duration: 16 h. Existing DCS/certificate gates remain; backend/site readiness and budget adequacy are unverified. Shared platform rollout and independent initial bootstrap are not charged again; coordinated recovery owns multi-service ordering.
Effort scenario: red-hat-quay#authentication-authorization
Workstream: Automation and registry. Supplied point estimate for human and cluster access.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Authentication and authorization config | 8 | 8 | 8 |
Total duration: 16 h. Shared identity establishment belongs to Keycloak; this feature owns Quay consumer configuration, cluster identities/tokens and access qualification. No reusable configuration or accepted results were supplied.
Effort scenario: red-hat-quay#mirror-sync
Workstream: Automation and registry. Supplied point estimate for platform content synchronization.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| OpenShift installers, Operators and marketplace mirror sync | 16 | 16 | 16 |
Total duration: 32 h. Source/content selection, release-specific tool support and complete destination qualification remain open. Global tier and tenant publishing are excluded.
Effort scenario: red-hat-quay#image-scanning
Workstream: Automation and registry. Supplied point estimate for platform image scanning.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Image scanning | 8 | 8 | 8 |
Total duration: 8 h. Compatible scanning/database/feed integration remains to qualify; deployment trust enforcement is not delivered by scan results.
Effort scenario: red-hat-quay#global-tier
Workstream: Automation and registry. Supplied point estimate for the optional global tier.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Global tier above the two datacenter instances | 24 | 24 | 24 |
Total duration: 40 h. Adds a third instance and upstream integration; hosting and dependencies remain to qualify. Excluded from required Phase 1.
Effort scenario: red-hat-quay#tenant-registry
Workstream: Automation and registry. Supplied point estimate for tenant-facing Quay on CLaaS.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Separate tenant-facing Quay deployment on CLaaS | 80 | 80 | 80 |
Total duration: 160 h. Hosting/onboarding/qualification contracts remain open. Excluded from required Phase 1; no per-tenant or per-datacenter rollout is inferred for this separate deployment.
Service Information
First CLaaS delivery scope
Round 3 on 2026-10-12 confirms Quay still needs establishing. No reusable registry deployment/configuration or test evidence was supplied or inspected. The later same-day Phase 1 agreement replaces the earlier 80/192/384 h aggregate with four feature budgets. Existing cluster automation does not establish backend, full blob/pull, trust, restore or handover acceptance. The endpoint-to-internal/public-issuer mapping was not answered, so the combined certificate-lifecycle gate remains conservative pending that actual consumer scope. Initial bootstrap still uses approved external registries, not this future service.
Establish the operational Quay service on DCS for platform content only in the first release, at each of the two datacenters. Tenant artifact publishing is not part of this initial registry offer. This Quay-specific change replaces the earlier one-location assumption; second-site hosting readiness and its relationship to the March target still need qualification, not an inferred expansion of all CLaaS services. Global upstream and tenant registry are stretch scope. The separate tenant image-source contract now records existing external Harbor as a tentative preferred route. Service selection, permissions and image policy remain to qualify; excluding tenant publishing here does not establish that external contract.
Initial DCS, Quay and its dependencies need an independent bootstrap image source. The external bootstrap cannot pull all of its prerequisites from a Quay service that is not running yet. The proposer selects approved external registries for initial bootstrap; the exact allowlist, artifacts, credentials and controlled access path still need definition. The Quay feature delivery blocks own operational-service readiness after DCS exists, not the initial supply of images needed to build DCS.
The 2026-10-12 DCS refinement scopes registry prerequisites to DCS's configured service-platform, local VM baseline and service-team access rather than final ACM management acceptance. Qualified internal and public issuer paths remain required; no public-validation contingency is selected. Authorized engineers may prepare setup under staged safeguards, but service acceptance consumes the feature results. Quay's own backend, content, trust and restore work stays here; the DCS platform rollout is not charged again. Quay then participates in DCS's all-installed-workloads ACM-independence demonstration instead of depending on that later demonstration.
Portfolio-management information has not been reconfirmed for this proposal. S3 in the source ledger names historical contacts and managing arrangements. They are not assigned here as current owners.
| Item | Information for this draft |
|---|---|
| Solution architect | Unassigned; accountable role and person to be confirmed. |
| CMDB number | Not confirmed. |
| Service Level Agreement | Availability, recovery and support objectives not agreed. |
| First- and second-line support | Groups, queues and escalation paths not confirmed. |
| Third-line support | Engineering and vendor entitlement/escalation arrangements not confirmed. |
| Response times and on-call arrangements | Not agreed. |
| Managing party | Platform-managed service proposed; accountable organization not confirmed. |
| Contact | Historical source contact must be reconfirmed, not inherited. |
Costs and Responsibilities
Costs
| Cost driver | Basis to measure before pricing |
|---|---|
| Application, mirror and scan runtime | Compute demand, concurrency, scan backlog and platform overhead. |
| Blob retention | Retained bytes, object requests, churn, deletion/garbage-collection lag and backups. |
| Metadata and runtime dependencies | Database/cache capacity, support, monitoring and recovery effort. |
| Content distribution | Upstream transfer, per-locality copies and selected tenant cross-locality copies. |
| Product and service lifecycle | Subscription entitlement, engineering, upgrades and operational support. |
Additional Specifications
No prices, budget or charging model are established. Capacity reporting should separate curated platform content from tenant content and additional locality copies. Deduplication within a product instance must not be assumed to eliminate storage across independent instances. Retention and backup policy will materially change cost, so neither can be inferred from the historical capacity tables.
Responsibilities
These are proposed allocations to roles, not assignments to named people.
Managing Party
The service-managing role would operate endpoints, configuration and Operator lifecycle; maintain repository onboarding and permissions; own mirror execution, capacity signals and alerts; and coordinate dependency support and restore tests. It would publish the actual service contract and retain evidence of upgrades, recovery and credential revocation. Platform/security roles must agree who authorizes source intake and exceptional fallback rather than leaving that decision implicit in a mirror job.
Consuming Party
Consumers would own the origin and release evidence of their artifacts, use scoped publishing identities, follow repository/retention rules and deploy the authorized digest. Consumers must identify which artifacts need another locality and why. Registry operators do not become application release approvers merely because they host the repository.
Roadmap and Lifecycle
Lifecycle
| Version | Delivery start | Delivery end | Extended support candidate |
|---|---|---|---|
| Exact Quay/Operator release TBD | Not committed | Not established | Not assessed; requires actual release and entitlement. |
A historical selection date is not a product version or support date. The release baseline must include compatible OpenShift, Clair and dependency versions, plus upgrade/restore constraints. Q3 tracks this obligation.
Roadmap
First establish the supported release combination and validate the storage, identity and copying contracts. The Phase 1 feature set requires two platform-only datacenter instances; stretch scope identifies the optional global upstream and separate CLaaS tenant registry. Refine their hosting and service objectives with accountable decision makers. Implementation and onboarding dates remain unset. Geo-replication, a dedicated registry per tenant and air-gapped logistics are not committed roadmap items.
Architecture
Application Functions
| ABB | Proposed contribution |
|---|---|
| Registry | OCI push/pull and repository administration, curated content copies, access controls, and evidence interfaces. Scan integration is proposed where supported; deployment trust decisions stay outside Quay. |
The realizes assertion expresses this intended contribution. Product support,
configuration and acceptance evidence are still needed before claiming conformity.
Dependencies
| Dependency boundary | Purpose and unresolved contract |
|---|---|
| DCS and Quay Operator | Selected first-release hosting direction; versions and managed/external boundaries unset. Bootstrap image access must be independent of this service; upgrade reversal needs a supported recovery path, not an assumed downgrade. |
| S3-compatible object API | Durable blobs. Validate exact ODF/Ceph service, Quay driver, credentials, TLS, retention and recovery. Client download endpoints or supported proxy mode are part of the delivery contract. Bucket provisioning alone does not establish HA. |
| PostgreSQL | Registry metadata and separate Clair state. Examined 3.18 documentation requires separate instances, excludes other workloads and pgBouncer, and leaves backups to service operations. Release, availability and restore arrangements unset. |
| Redis | Documented roles include live builder logs and garbage-collection locking. Supported topology, optional feature load, loss/rebuild semantics and failure behavior remain to validate; HA is not assumed. |
| Identity and credential services | Proposed human OIDC and scoped robots. Validate mapping, deprovisioning and token renewal. Documented one-hour robot federation has an audience-provisioning limitation; no chosen integration or validation policy is proven. |
| DNS, TLS and network ingress/egress | Separate audience endpoints, blob-download paths and permitted upstream access. Routing, certificate lifecycle, backend transport and locality dependencies unconfirmed. |
| Clair and vulnerability data | Finding visibility, separate database and feed access. Compatible release, coverage/freshness and scan-report recovery gap require an explicit trust policy. |
| Recovery, telemetry and trust tooling | Consistent config/generated keys/metadata/blobs and coordinated writers; external promotion/admission enforcement and audit retention. Products, targets and ownership unselected. |
The CLaaS proposal now declares the DCS, certificate, Keycloak and OpenBao dependency directions in metadata. Exact database, object-service, scanning and consumer integration choices remain unverified. In particular, selecting tenant Ceph RGW does not automatically choose the registry's bucket, driver or support contract. Historical product names remain context, not proof of current integration. The runtime-boundary research supplies dated documentation evidence for these constraints; it is not an integration test.
Technical Architecture
Use Operator-managed Quay on platform-managed OpenShift as the target proposal. The seed tier admits curated platform content; locality platform tiers distribute it to managed clusters; separate shared tenant-facing tiers accept workload publishing. Organizations and repository permissions provide proposed tenant separation inside a tenant-facing service, while endpoint/network boundaries separate tenant traffic from platform administration and lifecycle content. That boundary must also cover tenant workloads using platform-authorized node pull credentials or cached images; endpoint separation alone is insufficient.
The Operator does not make backend services resilient automatically. Each instance needs an explicit metadata, object and runtime-dependency contract. Release-specific mirroring, signatures/referrers, encryption and IAM behavior are assumptions to validate, not guaranteed service features. See storage, copying, IAM and trust gates.
Technical Documentation
| Design | Location and status |
|---|---|
| HLD | Quay registry design, independently authored draft. |
| LLD and runbooks | Not authored in this slice; no implementation or live configuration evidence. |
Historical sources are indexed in the subject ledger. The initial 2026-10-02 draft used historical sources only. The later mirroring and runtime-boundary investigations add public vendor documentation evidence without selecting a release or demonstrating live behavior.
Explore this note’s relationships 25 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (26)
- Intent, delivery and runtime evidenceNote · draft · Automation. Icon: Automation
- Certificate Lifecycle and TrustABB · draft · Certificates. Icon: Certificates
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — Clusters-as-a-Service: first production offeringNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- CLaaS technical feasibility evidence registerResearch · draft · CLaaS. Icon: General note
- Inventory, intended configuration and observed stateNote · draft · DCIM. Icon: Inventory
- Federated AuthenticationABB · draft · Identity. Icon: Identity
- Keycloak — shared identity providerSBB · draft · Identity. Icon: Identity
- DNS, DHCP and IP address managementABB · draft · Network. Icon: Network
- DCS — Datacenter Services ClusterSBB · draft · Platform. Icon: Platform
- OpenShift hosting and service boundariesNote · draft · Platform. Icon: Platform
- Provider bootstrap — external engineer-run foundationNote · draft · Platform. Icon: Platform
- Coordinated recovery and service restorationNote · draft · Recovery. Icon: Recovery
- RegistryNote · draft · Registry. Icon: Registry
- Quay registry designHLD · draft · Registry. Icon: Registry
- Red Hat Quay service proposalSBB · draft · Registry. Icon: Registry
- Registry capabilityABB · draft · Registry. Icon: Registry
- Quay artifact mirroring and evidence preservationResearch · draft · Registry. Icon: Registry
- Quay runtime dependencies, access and recoveryResearch · draft · Registry. Icon: Registry
- Registry review questionsNote · draft · Registry. Icon: Registry
- Tenant application images — external Harbor candidateNote · draft · Registry. Icon: Registry
- OpenBao — external first, DCS laterSBB · draft · Secrets. Icon: Secrets
- Secrets ManagementABB · draft · Secrets. Icon: Secrets
- SAK applicability and control allocation for CLaaSNote · draft · Security. Icon: General note
- What object-service contract does Quay require?Research · draft · Storage. Icon: Storage
Relationships (41)
- Intent, delivery and runtime evidenceDepends on →Red Hat Quay service proposalAutomation/intent-to-runtime.md · depends_on
- Certificate Lifecycle and TrustReferences →Red Hat Quay service proposalCertificates/certificate-lifecycle.md · Markdown link
- CLaaS effort summaryReferences →Red Hat Quay service proposalCLaaS/effort-summary.md · Markdown link
- CLaaS — Clusters-as-a-Service: first production offeringReferences →Red Hat Quay service proposalCLaaS/index.md · Markdown link
- CLaaS technical feasibility evidence registerReferences →Red Hat Quay service proposalCLaaS/technical-feasibility.md · Markdown link
- Inventory, intended configuration and observed stateReferences →Red Hat Quay service proposalDCIM/inventory-intent-and-observed-state.md · Markdown link
- Federated AuthenticationReferences →Red Hat Quay service proposalIdentity/federated-authentication.md · Markdown link
- DNS, DHCP and IP address managementReferences →Red Hat Quay service proposalNetwork/dns-dhcp-ipam.md · Markdown link
- DCS — Datacenter Services Cluster
· datacenter-services-cluster#acm-managementDepends on →Red Hat Quay service proposal· red-hat-quayPlatform/datacenter-services-cluster.md · features.acm-management.depends_on: red-hat-quay - OpenShift hosting and service boundariesDepends on →Red Hat Quay service proposalPlatform/openshift-service-boundaries.md · depends_on
- Quay registry designReferences →Red Hat Quay service proposalRegistry/quay-design.md · Markdown link
- Red Hat Quay service proposalDepends on →Certificate Lifecycle and TrustRegistry/red-hat-quay.md · depends_on
- Red Hat Quay service proposalDepends on →Keycloak — shared identity providerRegistry/red-hat-quay.md · depends_on
- Red Hat Quay service proposalDepends on →DCS — Datacenter Services Cluster
· datacenter-services-cluster#service-accessRegistry/red-hat-quay.md · depends_on: datacenter-services-cluster#service-access - Red Hat Quay service proposalDepends on →DCS — Datacenter Services Cluster
· datacenter-services-cluster#service-platformRegistry/red-hat-quay.md · depends_on: datacenter-services-cluster#service-platform - Red Hat Quay service proposalDepends on →OpenBao — external first, DCS laterRegistry/red-hat-quay.md · depends_on
- Red Hat Quay service proposalReferences →Certificate Lifecycle and TrustRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Federated AuthenticationRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →DNS, DHCP and IP address managementRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →DCS — Datacenter Services ClusterRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Provider bootstrap — external engineer-run foundationRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Coordinated recovery and service restorationRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Quay registry designRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Registry capabilityRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Quay artifact mirroring and evidence preservationRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Quay runtime dependencies, access and recoveryRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Registry review questionsRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →Tenant application images — external Harbor candidateRegistry/red-hat-quay.md · Markdown link
- Red Hat Quay service proposalReferences →What object-service contract does Quay require?Registry/red-hat-quay.md · Markdown link
- Quay runtime dependencies, access and recoveryReferences →Red Hat Quay service proposalRegistry/research-runtime-boundaries.md · Markdown link
- Registry review questionsReferences →Red Hat Quay service proposalRegistry/review-questions.md · Markdown link
- Tenant application images — external Harbor candidateReferences →Red Hat Quay service proposalRegistry/tenant-image-source.md · Markdown link
- Secrets ManagementReferences →Red Hat Quay service proposalSecrets/secrets-management.md · Markdown link
- SAK applicability and control allocation for CLaaSReferences →Red Hat Quay service proposalSecurity/sak-assurance.md · Markdown link
Features of this note
6 features declared in this note's metadata. Each is one capability with its own section. Readiness is the author's dated assessment for the scope it names; delivery is the next increment of work. The two are independent, and nothing here combines them across features or implies approval.
Base Quay install
red-hat-quay#base-install- Section
- Base Quay install
- Readiness
- Readiness unknown for Platform-only Quay instances in both datacenters., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 16 working hours (2 working days).
- Effort estimate
- 8 h working · 8–8 h · Conditional completion; low confidence; assessed 12 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
Quay authentication and authorization config
red-hat-quay#authentication-authorization- Readiness
- Readiness unknown for Platform-engineer login and separate service accounts/tokens for every consuming cluster., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 16 working hours (2 working days).
- Effort estimate
- 8 h working · 8–8 h · Conditional completion; low confidence; assessed 12 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
Quay image scanning
red-hat-quay#image-scanning- Section
- Image scanning
- Readiness
- Readiness unknown for Vulnerability findings for the Phase 1 platform image content., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 8 working hours (1 working day).
- Effort estimate
- 8 h working · 8–8 h · Conditional completion; low confidence; assessed 12 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
Quay mirror sync — OpenShift installers, Operators and marketplace
red-hat-quay#mirror-sync- Section
- Mirror sync
- Readiness
- Readiness unknown for Required platform lifecycle content available from both datacenter registries., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 32 working hours (4 working days).
- Effort estimate
- 16 h working · 16–16 h · Conditional completion; low confidence; assessed 12 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
Stretch — global tiered Quay setup
red-hat-quay#global-tier- Section
- Global tiered setup
- Readiness
- Not assessed No readiness assessment is written in the source; this is not the same as ready.
- Next delivery
- Proposed, duration 40 working hours (5 working days).
- Effort estimate
- 24 h working · 24–24 h · Conditional completion; low confidence; assessed 12 Oct 2026. Estimate assumptions
Stretch — tenant-facing Quay on CLaaS
red-hat-quay#tenant-registry- Section
- Tenant-facing Quay on CLaaS
- Readiness
- Not assessed No readiness assessment is written in the source; this is not the same as ready.
- Next delivery
- Proposed, duration 160 working hours (20 working days).
- Effort estimate
- 80 h working · 80–80 h · Conditional completion; low confidence; assessed 12 Oct 2026. Estimate assumptions