Approved complete tenant retirement
Effort scenario: tenant-retirement
Workstream: Assurance and operations. Conditional hours under the assessment convention.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Approval, tenant-owned inventory and data/backup disposition design | 8 | 24 | 48 |
| Controlled procedure, stop reconciliation and external cleanup handoffs | 16 | 40 | 80 |
| Recreate prevention, scoped deletion and retained-data access tests | 16 | 40 | 80 |
| Evidence and operations/tenant exit handover | 8 | 16 | 32 |
Sizing confidence: medium for a manual controlled procedure; no full deletion automation is promised. Argo, identity, DNS, NetScaler and storage owners contribute their established interfaces. High allows partial-retirement recovery and inventory corrections, not data erasure outside policy. Retention/legal holds may outlast March; completion means their disposition is explicitly governed, not all bytes disappear. Approval and service queues are lead time rather than active engineer hours.
The first offering must support approved complete retirement when a tenant cluster is no longer needed. This covers compute, identities, network allocations and stored data according to the applicable retention policy, with explicit evidence and backup handling. It is not authorization to delete a live tenant, an assumption that every record can be erased immediately, or a commitment to fully automated deletion without further design.
Define the approved request, scope, executing party and stopping/recovery points. Stop or remove tenant application reconciliation and revoke relevant repository, cluster and service credentials so a retired resource is not recreated. Identify hosted control-plane objects, worker VMs, tenant-scoped groups, private/public publication, DNS/IPAM allocations and RBD/CephFS/S3 data that belong to the tenant. Do not delete shared infrastructure, upstream human identities or another tenant's assets merely because they appeared in the tenant's dependency chain.
Agree export/retention requirements and backup disposition with the responsible roles. Retained backups, audit records or legal holds need an explicit authorized retention/access boundary and eventual disposal process; they are not silently removed or forgotten. Existing organizational NetScaler and storage processes remain external handoffs that require completion evidence.
The delivery outcome is a qualified end-to-end retirement procedure and evidence from an authorized representative non-production tenant. It feeds the CLaaS offering milestone, not initial cluster provisioning. The recovery dependency gates demonstration of this procedure, not the start of designing it. Tooling, owners, timing, data policy values and estimates remain to agree. No retirement or destructive test has been performed.
Explore this note’s relationships 10 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (11)
- CLaaS tenant lifecycle design — request, provisioning, change and retirementHLD · draft · Automation. Icon: Automation
- CLaaS effort assessmentNote · draft · CLaaS. Icon: General note
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — Clusters-as-a-Service: first production offeringNote · draft · CLaaS. Icon: General note
- Establish CLaaS production acceptance and assuranceNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- Approved complete tenant retirementNote · draft · CLaaS. Icon: General note
- CLaaS tenant network designHLD · draft · Network. Icon: Network
- SAK applicability and control allocation for CLaaSNote · draft · Security. Icon: General note
- Tenant isolation and provider-control protectionHLD · draft · Security. Icon: General note
- CLaaS storage and data-recovery designHLD · draft · Storage. Icon: Storage
Relationships (11)
- CLaaS tenant lifecycle design — request, provisioning, change and retirementDepends on →Approved complete tenant retirementAutomation/tenant-lifecycle-design.md · depends_on
- CLaaS tenant lifecycle design — request, provisioning, change and retirementReferences →Approved complete tenant retirementAutomation/tenant-lifecycle-design.md · Markdown link
- CLaaS effort summaryReferences →Approved complete tenant retirementCLaaS/effort-summary.md · Markdown link
- CLaaS — Clusters-as-a-Service: first production offeringReferences →Approved complete tenant retirementCLaaS/index.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Approved complete tenant retirementCLaaS/production-assurance.md · Markdown link
- CLaaS — March 2027 roadmapReferences →Approved complete tenant retirementCLaaS/roadmap.md · Markdown link
- Approved complete tenant retirementReferences →CLaaS effort assessmentCLaaS/tenant-retirement.md · Markdown link
- CLaaS tenant network designReferences →Approved complete tenant retirementNetwork/claas-network-design.md · Markdown link
- SAK applicability and control allocation for CLaaSReferences →Approved complete tenant retirementSecurity/sak-assurance.md · Markdown link
- Tenant isolation and provider-control protectionReferences →Approved complete tenant retirementSecurity/tenant-isolation.md · Markdown link
- CLaaS storage and data-recovery designReferences →Approved complete tenant retirementStorage/storage-recovery-design.md · Markdown link