HPE OneView
HPE OneView is the hardware-management system the proposer has chosen for the DC 3.0 hardware. On 2026-10-17, the proposer confirms an existing setup on the VMware platform, operated by the housing team, on the existing production network. Consuming this installation has no dependency on the new EVPN/VXLAN fabric in Phase 1. This note owns the four Phase 1 delivery increments below. Existing service availability is reported, not independently inspected evidence that its hardware consumers are ready. Version, licensing and support coverage remain unconfirmed.
Service Information
What is known, incorporating the proposer's 2026-10-17 clarification:
| Item | Information |
|---|---|
| Product | HPE OneView, selected by the proposer |
| Hosting location | Existing VMware platform; exact instance/location not supplied |
| Service network | Existing production network; no new EVPN/VXLAN hosting dependency in Phase 1 |
| Version | Not supplied |
| Availability and access | Existing setup reported available; scoped operator access not inspected |
| Licensing and support coverage | Not supplied |
| Managing party | Housing team |
This note does not move OneView onto the Datacenter Services Cluster or any other CLaaS platform. It consumes the existing VMware-hosted service. If a future placement is considered, the service must not depend on the hardware or clusters it manages to start, or recovery could deadlock.
Costs and Responsibilities
Costs
No cost or licensing figures have been supplied.
Responsibilities
Managing Party
The housing team operates the existing OneView service. Service operation covers availability, patching, licensing, the vendor support process and access; the actual coverage and named contacts remain to confirm. This does not silently transfer platform-side BMC automation or role-setting design to housing.
Consuming Party
The platform team defines and documents role-optimal settings and owns its BMC identity/setup automation, retaining the 14 October responsibility split. Housing/infra applies and manages Phase 1 profiles and firmware updates. The hardware note retains its stable feature identities as zero-additional-work acceptance milestones referencing these increments, rather than charging the same enrolment/IPMI/firmware work twice.
Roadmap and Lifecycle
Lifecycle
No version or support period has been recorded. Qualify release support for the reported Gen12 role configurations and the remaining per-node inventory; the screenshot is not a support matrix.
Roadmap
The delivery outcome is the four Phase 1 OneView hardware capabilities ready, using the existing service rather than installing a new OneView stack. Service qualification still needs to establish that:
- the instance is healthy and reachable through its agreed operator-management and recovery access paths;
- its version supports the server models in the inventory;
- licences and support connectivity cover the intended servers;
- named operators have scoped access, with credentials delivered through the organization's secret management and never written into this vault;
- the service is healthy and its own recovery is understood.
The milestone and all four feature increments are proposed, in datacenter. Current capability readiness remains unknown; no completed provisioning, profile qualification or update results are inferred. The existing service is a reported prerequisite, not a second newly budgeted installation. Missing access, version or entitlement evidence remains a qualification concern, not zero work or a fabricated completion date.
DC 3.0 hardware provisioning
Have all DC 3.0 hardware provisioned in HPE OneView, reconciled with the DCIM inventory. This is hardware enrolment into the existing management service, not OpenShift/OS installation. Record coverage, health exceptions and the licence/support checks described in the hardware enrolment boundary. The supplied budget is 8 engineering hours / 16 scheduling hours, replacing the earlier 32/40-hour enrolment point rather than adding another copy.
IPMI access and configuration
Ensure IPMI access and configuration are complete for the DC 3.0 hardware.
Retain the BMC security and automation boundary:
permitted management paths succeed, tenant/public paths are denied, identities
are scoped and credentials use approved secret delivery, never Git or inventory.
This consumes operational DCM access, reported ready on 17 October, without
waiting for a future DCM delivery increment, DCIM or the final OneView milestone.
The architectural dependency on DCM remains explicit. A conservative
earliest_start: 2026-10-17 prevents proposed IPMI work being forecast before
that confirmation; it is a planning boundary, not DCM's actual completion date.
The supplied budget is 8 engineering hours / 8 scheduling hours,
replacing the earlier BMC 8/24-hour point.
DC 3.0 hardware and firmware profiles
Have firmware and configuration profiles for all DC 3.0 hardware, tuning the right settings for each hardware model and role. The platform team defines and documents the settings; housing/infra applies and manages the Phase 1 profiles. Record profile coverage, selected baselines and justified exceptions. A profile's existence is not proof that firmware has been updated or settings applied. The supplied budget is 24 engineering hours / 24 scheduling hours.
DC 3.0 hardware firmware updates
Update firmware for all components of the DC 3.0 hardware to the selected, compatible baselines. Reconcile observed versions and applied settings per node against its profile, record exceptions and qualify staged maintenance without breaking the running services. Retain the role-specific change and single-writer controls. This is not a floating latest-firmware policy or evidence of vendor support. The supplied budget is 16 engineering hours / 16 scheduling hours.
Profiles and updates replace the earlier combined firmware/configuration 16/32-hour budget. The four feature budgets total 56 engineering hours, counted once. They are proposer-supplied completion points; equal low/working/high bounds are not independently assessed ranges or verified remaining work. No current actuals were supplied, so all four use conditional-completion basis with low confidence. The 19 October delivery/racking/patching report does not complete these management increments. Any E810-CQDA2 replacement, procurement wait and resulting requalification remain unestimated outside these budgets; no NIC owner, product or automatic gate on IPMI is inferred.
The dependency order preserves the agreed IPMI/BMC → enrolment → role assessment sequence, then applies updates against those profiles: IPMI configuration → hardware provisioning → hardware profiles → firmware updates. The feature durations sum to 64 scheduling hours (eight working days) after their external prerequisites are available; this is not a committed finish date. On 2026-10-20, the proposer records 64 nodes per datacenter across four racks, with AM4 first in Phase 1: 24 Control, 24 Worker, 8 Ceph and 8 GPU. Those counts define the initial hardware coverage, not per-node budget multipliers. The existing 56 engineering / 64 scheduling-hour points are unchanged and still need reconciliation against actual progress and inventory coverage. DCIM additionally gates provisioning; IPMI consumes the already-ready DCM capability rather than waiting on a pending network task. Neither NetBox nor the DCM network waits for the final OneView milestone, avoiding a bootstrap cycle.
Effort scenario: hpe-oneview
Workstream: Foundations. Phase 1 milestone; all work is counted in the four owning features.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| No additional work beyond the four Phase 1 features | 0 | 0 | 0 |
Zero is an accounting convention, not a readiness claim.
Effort scenario: hpe-oneview#hardware-provisioning
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Provision and reconcile all DC 3.0 hardware in the existing OneView service | 8 | 8 | 8 |
Duration: 16 scheduling hours. Low confidence until coverage and actual remainder are verified. Replaces the earlier hardware-enrolment estimate.
Effort scenario: hpe-oneview#ipmi-configuration
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Complete IPMI access and BMC configuration for the DC 3.0 hardware | 8 | 8 | 8 |
Duration: 8 scheduling hours. Low confidence until coverage and actual remainder are verified. Excludes the separately budgeted DCM network work.
Effort scenario: hpe-oneview#hardware-profiles
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Define and make available firmware/configuration profiles for every DC 3.0 hardware role | 24 | 24 | 24 |
Duration: 24 scheduling hours. Low confidence until models, role settings and profile coverage are qualified. Does not duplicate firmware rollout.
Effort scenario: hpe-oneview#firmware-updates
Workstream: Foundations. Proposer-supplied conditional-completion point, dated 2026-10-17.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Update all DC 3.0 hardware components and qualify observed firmware/settings | 16 | 16 | 16 |
Duration: 16 scheduling hours. Low confidence until the actual remainder and maintenance constraints are verified. Replacing unsupported hardware is not implied.
Architecture
Application Functions
In general terms, OneView manages server hardware through its management interfaces: inventory, health and alerts, configuration through server profiles, and firmware updates. This summary is not checked against version-specific documentation. The 2026-10-14 clarification chooses OneView profiles and firmware updates as the Phase 1 planning route: the platform team defines role-optimal settings and housing/infra applies and manages them in the datacenter domain. Hardware must be enrolled before that assessment. This assigns the consumer workflow; the 2026-10-17 clarification separately names housing as the service operator. Neither statement establishes tested version-specific support. Keep one writer of record for firmware and settings, as set out in the firmware feature.
No ABB for hardware management exists yet, so no realizes is recorded.
Dependencies
The existing VMware-hosted OneView installation runs on the existing production network. Phase 1 consumes it as-is; the service has no architectural dependency on the new EVPN/VXLAN fabric or its DCM feature. No new service-network design or migration is implied by this plan.
This is separate from connectivity to the new DC 3.0 hardware. The IPMI feature retains its architectural dependency on the reported-ready DCM capability, without a future-delivery wait. Delivery requires DCIM and IPMI for provisioning, provisioned hardware for profile definition, then profiles for updates. The aggregate milestone is not a prerequisite for any of its own features. OneView has no CLaaS hosting dependency on DCS, provider bootstrap or the hardware it manages; no migration from VMware is implied.
Technical Architecture
The existing service runs on VMware on the existing production network and is operated by housing, as reported on 2026-10-17. Exact deployment, network paths, access model, release and recovery details remain to document, including reconciliation with the DCIM service.
Technical Documentation
| Design | Location |
|---|---|
| HLD | Inventory and hardware-management control design (draft) |
| LLD | Not yet authored or linked |
Evidence is the proposer's 13/14/17 October planning statements, not an inspection of OneView, VMware, inventory or firmware. No vendor documentation was consulted for this draft; version-specific support and accepted readiness remain unverified.
Explore this note’s relationships 7 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (8)
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- DCIM serviceABB · draft · DCIM. Icon: Inventory
- HPE OneViewSBB · draft · DCIM. Icon: Inventory
- Inventory and hardware-management control designHLD · draft · DCIM. Icon: Inventory
- Datacenter hardwareNote · draft · Hardware. Icon: General note
- EVPN/VXLAN network fabricABB · draft · Network. Icon: Network
- DCS — Datacenter Services ClusterSBB · draft · Platform. Icon: Platform
Relationships (13)
- HPE OneView
· hpe-oneview#ipmi-configurationDepends on →EVPN/VXLAN network fabric· evpn-vxlan#dcm-networkDCIM/hpe-oneview.md · features.ipmi-configuration.depends_on: evpn-vxlan#dcm-network - HPE OneViewReferences →Inventory and hardware-management control designDCIM/hpe-oneview.md · Markdown link
- Inventory and hardware-management control designDescribes →HPE OneViewDCIM/inventory-control-design.md · describes
- Inventory and hardware-management control designReferences →HPE OneViewDCIM/inventory-control-design.md · Markdown link
- Datacenter hardware
· datacenter-hardware#firmware-managementDepends on →HPE OneView· hpe-oneviewHardware/datacenter-hardware.md · features.firmware-management.depends_on: hpe-oneview - Datacenter hardware
· datacenter-hardware#oneview-enrolmentDepends on →HPE OneView· hpe-oneviewHardware/datacenter-hardware.md · features.oneview-enrolment.depends_on: hpe-oneview
Features of this note
4 features declared in this note's metadata. Each is one capability with its own section. Readiness is the author's dated assessment for the scope it names; delivery is the next increment of work. The two are independent, and nothing here combines them across features or implies approval.
All DC 3.0 hardware firmware updated
hpe-oneview#firmware-updates- Readiness
- Readiness unknown for Firmware updated for the components of all 64 Phase 1 nodes in AM4, with observed versions reconciled to the selected baselines., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 16 working hours (2 working days); datacenter; recorded owner Housing/infra team.
- Effort estimate
- 16 h working · 16–16 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
DC 3.0 hardware and firmware profiles
hpe-oneview#hardware-profiles- Readiness
- Readiness unknown for Firmware and configuration profiles covering the models and roles of all 64 Phase 1 nodes in AM4, with the appropriate role-specific settings., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 24 working hours (3 working days); datacenter.
- Effort estimate
- 24 h working · 24–24 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
DC 3.0 hardware provisioned in OneView
hpe-oneview#hardware-provisioning- Section
- DC 3.0 hardware provisioning
- Readiness
- Readiness unknown for All 64 Phase 1 nodes in AM4 provisioned in the existing HPE OneView service; per-node identities and accepted coverage remain unconfirmed., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 16 working hours (2 working days); datacenter.
- Effort estimate
- 8 h working · 8–8 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
IPMI access and configuration
hpe-oneview#ipmi-configuration- Readiness
- Readiness unknown for Complete permitted IPMI access and BMC configuration for all 64 Phase 1 nodes in AM4., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 8 working hours (1 working day); datacenter; recorded owner Platform team.
- Effort estimate
- 8 h working · 8–8 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Depends on
- DCM network
evpn-vxlan#dcm-network - Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)