Datacenter hardware
This note covers the physical servers that the Ceph clusters and the OpenShift platform run on, and the three management capabilities that make that hardware operable and supportable. It records the proposer's hardware reports and supplied node-role configurations. Delivery, racking and network patching are reported complete; this is not proof of configured BMCs, accepted server firmware, network performance or production readiness.
Current planning — 19 October 2026: the hardware acceptance milestone is now proposed, as requested by the proposer. The four HPE OneView Phase 1 increments now own the implementation work and budgets for all DC 3.0 hardware. The three hardware feature IDs below are retained as zero-additional-work acceptance milestones, preserving links and consumer boundaries without a second enrolment, IPMI or firmware estimate. The earlier 13/14 October reports remain historical context, not current estimate authority. The reported E810-CQDA2 bandwidth issue is an unestimated remediation risk, not work silently included in those management budgets.
What is known
On 2026-10-13 the proposer reported the following. None of it was verified against an inventory, a management system or the hardware itself.
| Fact | Reported status | Limits |
|---|---|---|
| Hardware procurement | Complete | No delivery date, models, quantities or contract references supplied |
| Work already done on the hardware | Substantial, unspecified | Which nodes, which tasks and to what standard are not recorded |
| Consumers | The Ceph clusters and OpenShift depend on this hardware | Allocation of nodes to each consumer not supplied |
| Required management capabilities | BMC management with IPMI access; firmware and role-optimal configuration with an automation process; HPE OneView enrolment | Supplied as point budgets; see the features |
| Preconditions | BMC automation starts after operational DCM access; enrolment retains DCIM/OneView service gates; firmware assessment and management follow enrolment | Refined on 2026-10-14; service readiness remains unverified |
| Progress per capability | Refined on 2026-10-14 | BMC progress is unverified; firmware is planned from scratch without credit for earlier work; no OneView enrolment work has been done, as reported by the proposer |
On 2026-10-19, the proposer confirms that the hardware has been delivered, slotted into racks and network patched. No actual completion dates or node-by-node installation records were supplied. Do not retain delivery, racking or patching as new future work for this reported-complete scope. Power-on status, negotiated links, end-to-end connectivity, BMC configuration and support acceptance are not established by this physical-progress report. Procurement and physical installation are not production readiness: firmware, BMC access and the support process still need their own qualification. Equally, the reported prior work means these capabilities are not assumed to start from nothing: the existing dev estate and the external Ceph service are already reported working (provider bootstrap, external Ceph). This note does not price a reinstall of either, and does not mark either as stopped or invalid. The 19 October upstream Ceph plan now budgets its backend installation and capabilities in Ceph clusters, not in this hardware note. The earlier working-service report does not establish that new scope as complete. The 2026-10-14 clarification specifically planned the firmware/configuration feature from scratch, with documentation and no credit for its earlier work, and reported OneView enrolment not started. The 19 October physical-progress report does not update those feature-specific actuals or erase the reported running estate.
Inventory, specifications and rack layout
The proposer supplies a node-role configuration screenshot on 2026-10-19, titled with Control Node, Worker Node, Ceph Node and GPU node, and describes it as the current components. The role profiles below are transcribed from that image; they are reported configurations, not a live inventory, vendor support assessment or per-node acceptance record. The original screenshot is not copied into publication. Its colour highlighting has no supplied legend and is not interpreted as approval, completion or a change instruction.
Reported quantities and Phase 1 location — 20 October 2026
The proposer reports the following per datacenter, spread over four racks, and confirms that Phase 1 starts in AM4:
| Hardware role | Nodes per datacenter |
|---|---|
| Control | 24 |
| Worker | 24 |
| Ceph | 8 |
| GPU | 8 |
| Total | 64 |
For the initial one-location Phase 1 scope, AM4 therefore has a reported 64-node inventory across four racks. This is the supplied physical scope, not 64 nodes per cluster or per environment. The proposer further confirms on 2026-10-20 that this same hardware supports development and the eventual production offering targeted for the end of Q1 2027. It is not two separate 64-node hardware estates. Physical reuse does not establish concurrent capacity, a cutover/reallocation method, or promotion of existing development clusters unchanged into production. The earlier separate-production-build plan remains unchanged; separate installations do not imply separate physical hardware. Do not infer an even 16-node-per-rack distribution, a role distribution across racks, independent failure domains, or a host allocation between environments. The per-datacenter figures do not introduce another location into Phase 1 or establish another site's readiness.
Still not supplied: asset identities, exact allocation to production/dev and individual platform clusters, rack identities/U positions, switch ports, power-feed mapping and observed firmware. The role labels and counts do not establish cluster sizing or a new GPU service commitment. Phase 1 retains the agreed local-redundancy intent in AM4; rack/host failure-domain mapping remains open. Physical patching is reported complete, but its connection map and test results have not been supplied.
Reported node-role configurations
All four role profiles list 2 × HPE 1.92 TB (RI) NVMe PCIe-5 E3S OS drives. That is a component description, not a RAID/mirroring choice or an installed OS. RAM units and maximums below follow the screenshot; no GB/GiB conversion or vendor maximum-capacity verification is implied. CPU quantities are not inferred where the image gives only a processor model.
Control node
- Server: HPE DL325 Gen12, 1U; power supplies listed as 2 × 1 kW.
- CPU: AMD EPYC 9355P, 32 cores / 64 threads, 3.55 / 4.40 GHz, 280 W TDP; processor quantity not stated.
- RAM: 768 GB, 12 × 64 GB DDR5 ECC RDIMM, 6400 MHz as labelled in the image.
- Data drives: 4 × HPE NVMe Gen5 3.84 TB (RI) E3S.
- Network adapter: 1 × Intel E810-CQDA2, labelled 100Gb, 2-port QSFP28, OCP3; see the bandwidth issue below.
- Management: dedicated iLO port listed; firmware, licence and access configuration not supplied.
Worker node
- Server: HPE DL345 Gen12, 2U; power supplies listed as 2 × 1.5 kW.
- CPU: AMD EPYC 9755, 128 cores / 256 threads, 2.7 / 4.1 GHz, 500 W TDP; processor quantity not stated.
- RAM: 1.5 TB, 12 × 128 GB DDR5 ECC RDIMM, 6400 MHz; the image separately lists up to 6 TB, not installed capacity.
- Data drives: 4 × HPE NVMe Gen5 3.84 TB (RI) E3S.
- Network adapter: 1 × Intel E810-CQDA2, labelled 100Gb, 2-port QSFP28, OCP3; see the bandwidth issue below.
- Management: dedicated iLO port listed; firmware, licence and access configuration not supplied.
Ceph node
- Server: HPE DL345 Gen12, 2U; power supplies listed as 2 × 1.5 kW.
- CPU: 1 × AMD EPYC 9575F, 64 cores / 128 threads, 3.3 / 5.0 GHz, 400 W TDP.
- RAM: 768 GB, 12 × 64 GB DDR5 ECC RDIMM, 6400 MHz; the image separately lists up to 4.5 TB, not installed capacity.
- Data drives: 12 × HPE NVMe Gen5 12.8 TB (MU, 3-DWPD); up to 20 drives is a listed expansion limit, not 20 installed drives. No usable Ceph capacity, OSD layout or protection scheme is inferred.
- Network adapters: 2 × HPE InfiniBand NDR/Ethernet 400Gb, one-port adapters, as labelled; exact model, operating mode, negotiated link rates and switch attachment are unconfirmed. This profile does not list the E810-CQDA2.
- Management: dedicated iLO port listed; firmware, licence and access configuration not supplied.
GPU node
- Server: HPE DL345 Gen12, 2U; power supplies listed as 2 × 3.2 kW.
- CPU: AMD EPYC 9755, 128 cores / 256 threads, 2.7 / 4.1 GHz, 500 W TDP; processor quantity not stated.
- RAM: 1.5 TB, 12 × 128 GB DDR5 ECC RDIMM, 6400 MHz; the image separately lists up to 4.5 TB, not installed capacity. This differs from the Worker profile's listed maximum and is retained as reported, not reconciled by assumption.
- Data drives: 4 × HPE NVMe Gen5 3.84 TB (RI) E3S.
- Network adapter: 1 × Intel E810-CQDA2, labelled 100Gb, 2-port QSFP28, OCP3; see the bandwidth issue below.
- GPUs: 2 × NVIDIA RTX Pro 6000 Blackwell Server Edition, each labelled 96G VRAM, 1600 GB/sec, dual slot. These per-GPU labels are not a shared-memory allocation or a network-bandwidth claim.
- Management: the GPU profile does not explicitly list a dedicated iLO port; do not infer its wiring from the other role profiles.
The listed PSU ratings do not prove redundant feeds, observed power draw or available facility capacity. Likewise, NIC port rates do not establish card-level aggregate throughput, bonding performance or a supported switch configuration. Exact adapter SKU/form factor, installation inventory and component compatibility still need qualification; the screenshot's labels are not vendor documentation.
The curated record belongs in the DCIM service, following the inventory, intent and observation boundaries. This note should link to that record rather than duplicate it. The fields the management features and their consumers need are:
| Field | Why it is needed | Current value |
|---|---|---|
| Hardware model and generation per node | OneView support coverage, firmware baselines, supported settings | Role profiles above supplied; asset-to-role mapping remains open |
| Node count per hardware role | Scope of every feature; acceptance coverage | 24 Control, 24 Worker, 8 Ceph and 8 GPU per datacenter; the same AM4 hardware serves development and eventual production, with per-cluster/environment host allocation still open |
| Site / datacenter per node | One-location Phase 1 placement and local failure domains | Phase 1 starts in AM4; asset identities and exact placement remain open |
| Rack identity and U position | Cabling verification and failure-domain placement | Four racks per datacenter; racking reported complete, but rack identities, distribution and U positions not supplied |
| CPU, RAM and accelerators | Role suitability, firmware profiles and capacity | Role profiles above supplied; per-node observation and allocation remain open |
| Disks: type, size, count, controller and controller mode | Ceph OSD layout; OpenShift install and persistence disks | Per-role drive type/size/count supplied; controller, mode and RAID/OSD layout open |
| NICs: ports, speeds, firmware, leaf connections | Role-specific fabric attachment and bandwidth qualification | Adapter labels above supplied; E810 issue open; firmware, negotiated rates and port mapping unconfirmed |
| BMC: type, firmware, DCM address and switch port | BMC management feature; DCM network sizing | Dedicated iLO ports listed for Control/Worker/Ceph; remaining details and GPU port not supplied |
| Firmware baseline per component | Firmware feature; vendor support requirements | Not supplied |
| Power circuits, PDUs and redundant feeds | Power failure domains; maintenance planning | Per-role PSU ratings supplied; feeds, power-on status and observed load unconfirmed |
| Redundant network and management paths | Which single failures each node survives | Not supplied |
| Support contract or entitlement reference | OneView support process; vendor escalation | Not supplied (record references, never credentials) |
Missing fields keep the affected acceptance open. They are not filled with plausible defaults, and a feature completed for some nodes does not cover the rest.
Intel E810-CQDA2 bandwidth issue
On 2026-10-19, the proposer reports an issue with the Intel E810-CQDA2: the current card does not provide the required true 200 Gbit/s bandwidth through the card, and will probably need replacement with a different model. This is a reported problem and likely remediation direction, not an independently reproduced performance result, diagnosed PCIe/driver limitation or approved replacement. The exact throughput criterion, traffic pattern, direction and test conditions have not been supplied. Two nominal 100Gb ports are not evidence of 200 Gbit/s usable throughput through the adapter.
The screenshot lists this adapter for Control, Worker and GPU roles. Which actual nodes are affected or require the bandwidth target remains to confirm. The Ceph role lists different 400Gb adapters; no E810 issue is attributed to those cards by this report. The earlier blanket two-100G-interface description must not overwrite these role-specific configurations or assert achieved bandwidth.
In a further 19 October clarification, the proposer identifies the issue as high priority and confirms that a temporary workaround is available until there is a proper fix. The proposer then explicitly confirms that the workaround allows Phase 1, but the issue must still be fixed. This resolves the Phase 1 planning decision: permanent NIC remediation is required, high-priority follow-up, not a prerequisite for Phase 1 hardware handoff. No later phase or fix deadline is assigned by this statement. The workaround's mechanism and operational limits remain to document; its acceptance for Phase 1 is the proposer's report, not a throughput test or proof that the full 200 Gbit/s target is met.
Planning treatment: keep the permanent fix as an open, high-priority, unestimated remediation risk, with the confirmed workaround permitting Phase 1. Replacement selection, quantities, procurement approval, supplier lead time, installation/recabling work, firmware/driver/profile changes and requalification are not supplied. Engineering effort and scheduling duration are unknown, not zero; none is silently added to or absorbed by the existing 56 engineering / 64 scheduling hours of OneView management work. No replacement product, delivery date, owner or budget is invented.
The current hardware milestone's conditional forecast covers the recorded Phase 1 management increments under that workaround and excludes permanent NIC remediation and procurement lead time. It does not forecast completion of the required fix, qualify every hardware feature or prove the full bandwidth target. Record the workaround and its limitations in the implementation/operating handoff without reopening the resolved decision that it allows Phase 1. Permanent remediation still needs its own scope, owner, engineering effort and scheduling/lead-time estimate; no invented zero-hour fix or replacement gate is added to the Phase 1 plan.
Hardware management features
Each retained feature is proposed in datacenter, with unknown capability readiness. Its zero effort/duration is an acceptance-accounting convention, not completed work. The OneView note owns the actual feature increments and the proposer's 2026-10-17 budgets. The 20 October count clarification defines the initial management scope as all 64 nodes in AM4, not four additional role-specific copies of those budgets:
| OneView-owned increment | Engineering h | Duration h | Delivery prerequisites |
|---|---|---|---|
| IPMI access/configuration | 8 | 8 | Operational DCM access |
| Hardware provisioning | 8 | 16 | DCIM and complete IPMI configuration |
| Hardware/firmware profiles | 24 | 24 | Hardware provisioned before role assessment |
| Firmware updates | 16 | 16 | Defined profiles and baselines |
These 56 engineering hours replace, rather than supplement, the earlier BMC 8/24, enrolment 32/40 and combined firmware 16/32 points. No current actuals were supplied; the new points use conditional-completion basis, not verified remaining work. The sequence is IPMI → provisioning → profiles → updates, totalling 64 scheduling hours (eight working days) after external inputs are available. It is not a dated commitment or resource-levelled forecast. The recorded points are retained unchanged after the count clarification: they are not multiplied by 64 or divided by four racks. Confirm their practical coverage against the reported inventory and actual progress before a staffing commitment; the counts alone do not re-estimate effort or scheduling duration.
BMC management and IPMI access
Outcome: every in-scope node has its BMC configured and reachable on the DCM network, with IPMI access and the specific users/identities needed by the agreed consumers managed repeatably.
The platform team owns setup and management automation on its side, within the datacenter domain. It can start when DCM networking is complete and the team can access IPMI. This replaces the feature's earlier blanket DCIM/OneView start gates; neither service is required to create the BMC identities/access that OneView enrolment itself consumes. Inventory remains useful for scope and evidence, not a start gate for this automation.
The work covers BMC network settings and naming from the agreed address and name authority, BMC accounts for named roles, time source, and confirmation that each BMC answers on the management network. It does not include extending the existing DCM network: on 17 October the proposer reports that network feature implemented and complete, owned by Quanza, with zero remaining work. Its earlier 16/40-hour point is superseded, not added to these OneView-owned 8 hours. The DCM completion date is unknown; network readiness and missing historical delivery dates remain separate facts. The architectural DCM dependency remains, but there is no future DCM increment for the IPMI work to wait on.
IPMI-over-LAN is the access the proposer requires. Which consumers may use it (operators, OneView, installation or provisioning tooling), from which networks, and whether other BMC interfaces are permitted alongside it, is a security decision still to make. IPMI access must not be reachable from tenant or public networks. Default or shared BMC passwords must be replaced. BMC credentials are issued and held through the organization's secret management; none are recorded in this vault or in Git, and no configuration commands are given here.
Done when the documented in-scope interfaces can be configured and managed through the platform team's automation, the required users/identities and scoped credentials are established, and permitted consumers succeed while refused paths fail. Record the covered hardware/interfaces and link the curated inventory when available; recording credentials in inventory or Git is never permitted.
Firmware management and role-optimal configuration
Outcome: each node runs a recorded firmware baseline and the configuration chosen for its role, and the same result can be reapplied through a repeatable automation process rather than by hand.
The platform team determines and documents optimal settings per node role. In Phase 1, the housing/infra team applies and manages those settings, profiles and firmware updates through HPE OneView, within the datacenter domain. This is the current planning route, not an implemented profile or a supported-release claim. A later transfer to platform-team operation is future scope, not part of this increment's acceptance.
Hardware must be enrolled in OneView before the platform team assesses its role-optimal firmware configuration. Some initial work is reported, but this feature was deliberately planned from scratch and documented on 14 October, with no credit for that earlier work. Its former 16/32-hour combined budget is superseded by the 17 October OneView-owned profile (24/24-hour) and update (16/16-hour) increments, not retained as additional work.
Roles differ. Candidate considerations to decide per role, against vendor guidance for the actual models, are:
- Ceph nodes: storage-controller mode and drive presentation suitable for Ceph, drive and controller firmware levels, NIC settings for the storage traffic, and power or performance profiles that avoid latency surprises.
- OpenShift nodes: boot mode and boot-device order matching the installation method, virtualization and IO-virtualization features for the Virtualization role, NIC settings for the active-active bond, and power or performance profiles per role.
This is a list of questions, not a prescribed setting list. Do not disable features wholesale or apply a setting a model does not support. Record the chosen baseline per role and model, and the reason for each deliberate deviation.
Ownership must be single. Under the Phase 1 route, OneView profiles and firmware management are the writer of record for this feature's settings, operated by housing/infra. Platform automation must not independently overwrite those values. Document profile coverage, supported settings and deliberate exceptions per model/role; the exact OneView mechanisms remain to qualify.
Changes on running hardware are maintenance. Ceph nodes are changed one failure domain at a time with the cluster healthy before and after, under the storage team's procedure. OpenShift nodes are drained and changed within the role's availability limits. A role can carry constraints, such as a Ceph release requiring a minimum controller firmware, that the baseline must respect.
Done when observed firmware and settings match the recorded baseline on every in-scope node, the automation can show a dry run or reapplication, and a staged change on one node per role has been demonstrated without breaking its service.
HPE OneView enrolment
Outcome: every in-scope node is enrolled in HPE OneView, so that hardware state is managed there and the vendor support process works.
On 2026-10-14 the proposer reported no work had been done on this feature. The 17 October clarification replaces its 32/40-hour point with the OneView-owned hardware provisioning 8/16-hour increment for all DC 3.0 hardware. This stable hardware feature is now a proposed zero-additional-work acceptance milestone. Housing operates the service; the named provisioning executor remains unrecorded. Complete enrolment after BMC setup and before firmware assessment.
Enrolment is the per-node work: adding the hardware through its BMC, assigning it to the agreed scope or group and resolving the alerts this produces. Establish the enrolled inventory for assessment; defining and applying role-optimal profiles and firmware belong to the following feature, not an enrolment prerequisite. It is not installing another OneView stack. The existing VMware-hosted service is operated by housing; its release, licensing and support still need qualification, not an assumption of readiness from service presence.
Adding assets to OneView does not by itself guarantee vendor support. Acceptance needs evidence that the enrolled set matches the DCIM inventory, that each node's licence and support entitlement is recorded and valid, that OneView reports the hardware healthy or explains each exception, and that a support case or test escalation path works for at least one node. Unsupported models or missing entitlements are recorded as gaps, not hidden.
Done when the enrolled inventory reconciles with DCIM, entitlements are confirmed and the support path has been exercised as agreed.
Prerequisites and dependency reasoning
The 2026-10-14 clarification allows BMC automation to start once DCM networking is complete and the platform team can access IPMI, without a DCIM start gate. The 17 October OneView-owned increments preserve that order: DCM → IPMI; DCIM and IPMI → hardware provisioning → role-specific profiles → firmware updates. The retained hardware features accept those increments with zero additional work. None waits for the aggregate OneView milestone before building the very features that milestone requires. There is no reverse profile-to-enrolment edge.
The Ceph clusters backend baseline, the OpenShift baseline and provider bootstrap wait for this acceptance. That is a gate on accepting production hardware, not on design work, and not an instruction to stop or rebuild what already runs. An unavailable prerequisite blocks its consuming feature, not servers that are already running.
Acceptance milestone
The note-level delivery is a zero-cost acceptance milestone: hardware is accepted when all three features and the complete OneView Phase 1 milestone are evidenced for the recorded inventory scope. It adds no engineering or duration of its own. On 2026-10-19, the proposer sets its delivery state to proposed, matching the three proposed acceptance-feature deliveries. No accepted hardware-management result or actual completion date is inferred from delivery/racking/patching. Capability readiness remains unknown. The generated dates cover the currently modelled management work and exclude the unestimated NIC remediation risk; they are not evidence of meeting the bandwidth requirement or a complete hardware commitment.
Responsibilities and open decisions
The datacenter domain owns these hardware features. The platform team owns BMC setup/identity automation and defines role-optimal firmware settings; housing/infra operates the Phase 1 OneView profiles and updates. Named accountable owners, provisioning execution and operational handoff remain open. The existing OneView service is operated by housing on VMware. Storage, Networking and security retain their relevant interface/maintenance responsibilities. Open items:
- Per-node identities and provider-cluster/environment allocation, rack/port/feed mapping and observed configuration, extending the reported role profiles and counts.
- BMC progress and interface coverage; firmware is planned from scratch and enrolment has not started, as reported by the proposer.
- Which BMC interfaces and consumers are permitted, and how IPMI is hardened.
- Documented role/model settings and coverage of the Phase 1 OneView profiles, including justified exceptions to their single-writer boundary.
- OneView licence and support-entitlement coverage per model.
- Exact host/role distribution across AM4's four racks and the local failure domains.
- Required high-priority permanent E810-CQDA2 remediation: affected nodes, replacement decision and separate engineering/scheduling/procurement estimates. The confirmed workaround permits Phase 1; that decision is not an open start gate.
Effort scenario: datacenter-hardware
Workstream: Foundations. The acceptance milestone adds no duplicate feature work.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Acceptance review requiring the three hardware features | 0 | 0 | 0 |
Procurement is reported complete and is not budgeted. The DCIM and HPE OneView owning notes now hold their supplied feature budgets; none is counted again here. Delivery, racking and network patching are also reported complete on 19 October, without actual finish dates. The zero-cost milestone does not estimate the E810-CQDA2 remediation: its engineering effort, scheduling duration and possible procurement lead time remain unestimated and are excluded from the current conditional dates, not priced as zero or presumed resolved. The separate DCM feature is reported implemented and complete on 17 October, with zero remaining work; its earlier 16/40-hour budget is superseded and is not included in the hardware budgets or treated as measured effort spent.
Effort scenario: datacenter-hardware#bmc-management
Workstream: Foundations. Zero-additional-work acceptance milestone as of 2026-10-17, referencing the OneView-owned IPMI increment. The earlier BMC point is superseded.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Accept the OneView-owned IPMI configuration increment without duplicate work | 0 | 0 | 0 |
Duration: 0 h. This is not zero implementation effort or accepted readiness; OneView owns the 8 engineering / 8 scheduling hours and DCM remains separate.
Effort scenario: datacenter-hardware#firmware-management
Workstream: Foundations. Zero-additional-work acceptance milestone as of 2026-10-17, referencing the OneView-owned profiles and firmware-update increments.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Accept the OneView-owned profile and firmware-update results without duplicate work | 0 | 0 | 0 |
Duration: 0 h. The former combined estimate is superseded; the profiles 24/24-hour and updates 16/16-hour budgets live in OneView only.
Effort scenario: datacenter-hardware#oneview-enrolment
Workstream: Foundations. Zero-additional-work acceptance milestone as of 2026-10-17, referencing the OneView-owned hardware provisioning increment.
| Work package | Low h | Working h | High h |
|---|---|---|---|
| Accept the OneView-owned hardware provisioning result without duplicate work | 0 | 0 | 0 |
Duration: 0 h. The former enrolment estimate is superseded by the OneView-owned 8 engineering / 16 scheduling hours; this does not claim completion.
Evidence and limits
The sources are the proposer's statements of 2026-10-13, 2026-10-14, 2026-10-17, 2026-10-19 and 2026-10-20, plus the node-role screenshot supplied on 19 October: procurement complete, substantial unspecified estate work, the three confirmed budgets, proposed feature deliveries in the datacenter domain, refined BMC start conditions, Phase 1 responsibilities, firmware planned from scratch and enrolment not started, and enrolment before firmware assessment. The 17 October refinement records the existing VMware-hosted housing-operated service and superseding four OneView feature budgets. The 19 October update records the four role profiles, reported delivery/racking/patching, proposed aggregate state and unresolved NIC bandwidth issue; it does not establish BMC, firmware or enrolment completion. The 20 October clarification adds the 8 Ceph / 8 GPU / 24 Worker / 24 Control nodes per datacenter, four racks and AM4 as the first Phase 1 location. These reported counts do not establish per-node acceptance or environment allocation. The same-day follow-up confirms that this hardware serves both development and the eventual production offering targeted for the end of Q1 2027, without establishing simultaneous operation, transition arrangements or readiness. The screenshot was visually read, but no live inventory, management system, vendor documentation, throughput test or hardware was inspected. Component labels and listed maximums are supplied data, not independently verified specifications. The candidate considerations are engineering questions to settle, not observed configuration or vendor requirements.
Explore this note’s relationships 20 connected notes
Connections are authored references and declared relationships, not verified runtime dependencies or approval.
No notes match these filters. Reset filters to show the whole graph.
Drag to pan. Use arrow keys to pan, + / − to zoom, and 0 to fit. Select notes or relationships in the list below for a keyboard alternative.
Every note and relationship is available in the list below. The interactive map requires JavaScript.
Notes and relationships Accessible list
Notes (21)
- CLaaS effort assessmentNote · draft · CLaaS. Icon: General note
- CLaaS effort summaryNote · draft · CLaaS. Icon: General note
- CLaaS platform design — service planes, hosting and failure boundariesHLD · draft · CLaaS. Icon: General note
- Establish CLaaS production acceptance and assuranceNote · draft · CLaaS. Icon: General note
- CLaaS — March 2027 roadmapNote · draft · CLaaS. Icon: General note
- DCIM serviceABB · draft · DCIM. Icon: Inventory
- HPE OneViewSBB · draft · DCIM. Icon: Inventory
- Inventory and hardware-management control designHLD · draft · DCIM. Icon: Inventory
- Inventory, intended configuration and observed stateNote · draft · DCIM. Icon: Inventory
- Datacenter hardwareNote · draft · Hardware. Icon: General note
- CLaaS tenant network designHLD · draft · Network. Icon: Network
- DNS, DHCP and IP address managementABB · draft · Network. Icon: Network
- EVPN/VXLAN network fabricABB · draft · Network. Icon: Network
- OpenShift platform baselineSBB · draft · Platform. Icon: Platform
- OpenShift Virtualization — tenant worker hostingSBB · draft · Platform. Icon: Platform
- Provider bootstrap — external engineer-run foundationNote · draft · Platform. Icon: Platform
- Representative non-production qualification environmentNote · draft · Platform. Icon: Platform
- Secrets ManagementABB · draft · Secrets. Icon: Secrets
- Ceph clustersSBB · draft · Storage. Icon: Storage
- External Ceph through ceph-csiSBB · draft · Storage. Icon: Storage
- CLaaS storage and data-recovery designHLD · draft · Storage. Icon: Storage
Relationships (39)
- CLaaS platform design — service planes, hosting and failure boundariesDepends on →Datacenter hardwareCLaaS/platform-design.md · depends_on
- CLaaS platform design — service planes, hosting and failure boundariesReferences →Datacenter hardwareCLaaS/platform-design.md · Markdown link
- Establish CLaaS production acceptance and assuranceReferences →Datacenter hardwareCLaaS/production-assurance.md · Markdown link
- Inventory and hardware-management control designDepends on →Datacenter hardwareDCIM/inventory-control-design.md · depends_on
- Inventory and hardware-management control designReferences →Datacenter hardwareDCIM/inventory-control-design.md · Markdown link
- Datacenter hardware
· datacenter-hardware#firmware-managementDepends on →DCIM service· dcim-serviceHardware/datacenter-hardware.md · features.firmware-management.depends_on: dcim-service - Datacenter hardware
· datacenter-hardware#oneview-enrolmentDepends on →DCIM service· dcim-serviceHardware/datacenter-hardware.md · features.oneview-enrolment.depends_on: dcim-service - Datacenter hardware
· datacenter-hardware#firmware-managementDepends on →HPE OneView· hpe-oneviewHardware/datacenter-hardware.md · features.firmware-management.depends_on: hpe-oneview - Datacenter hardware
· datacenter-hardware#oneview-enrolmentDepends on →HPE OneView· hpe-oneviewHardware/datacenter-hardware.md · features.oneview-enrolment.depends_on: hpe-oneview - Datacenter hardware
· datacenter-hardware#bmc-managementDepends on →EVPN/VXLAN network fabric· evpn-vxlan#dcm-networkHardware/datacenter-hardware.md · features.bmc-management.depends_on: evpn-vxlan#dcm-network - Datacenter hardwareReferences →Inventory, intended configuration and observed stateHardware/datacenter-hardware.md · Markdown link
- Datacenter hardwareReferences →DNS, DHCP and IP address managementHardware/datacenter-hardware.md · Markdown link
- Datacenter hardwareReferences →EVPN/VXLAN network fabricHardware/datacenter-hardware.md · Markdown link
- Datacenter hardwareReferences →OpenShift platform baselineHardware/datacenter-hardware.md · Markdown link
- Datacenter hardwareReferences →OpenShift Virtualization — tenant worker hostingHardware/datacenter-hardware.md · Markdown link
- Datacenter hardwareReferences →Provider bootstrap — external engineer-run foundationHardware/datacenter-hardware.md · Markdown link
- Datacenter hardwareReferences →External Ceph through ceph-csiHardware/datacenter-hardware.md · Markdown link
- CLaaS tenant network designReferences →Datacenter hardwareNetwork/claas-network-design.md · Markdown link
- OpenShift platform baselineDepends on →Datacenter hardwarePlatform/openshift-platform.md · depends_on
- OpenShift platform baselineReferences →Datacenter hardwarePlatform/openshift-platform.md · Markdown link
- Provider bootstrap — external engineer-run foundationDepends on →Datacenter hardwarePlatform/provider-bootstrap.md · depends_on
- Provider bootstrap — external engineer-run foundationReferences →Datacenter hardwarePlatform/provider-bootstrap.md · Markdown link
- Representative non-production qualification environmentReferences →Datacenter hardwarePlatform/qualification-environment.md · Markdown link
- External Ceph through ceph-csiReferences →Datacenter hardwareStorage/external-ceph-csi.md · Markdown link
- CLaaS storage and data-recovery designReferences →Datacenter hardwareStorage/storage-recovery-design.md · Markdown link
Features of this note
3 features declared in this note's metadata. Each is one capability with its own section. Readiness is the author's dated assessment for the scope it names; delivery is the next increment of work. The two are independent, and nothing here combines them across features or implies approval.
BMC management and IPMI access
datacenter-hardware#bmc-management- Readiness
- Readiness unknown for BMC configuration and permitted IPMI access for all 64 Phase 1 nodes in AM4; role counts/configurations are reported, but per-node identities and accepted coverage remain unconfirmed., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 0 working hours (milestone); datacenter; recorded owner Platform team.
- Effort estimate
- 0 h working · 0–0 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Depends on
- DCM network
evpn-vxlan#dcm-network - Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
Firmware management and role-optimal configuration
datacenter-hardware#firmware-management- Readiness
- Readiness unknown for Firmware baselines and role-specific configuration for all 64 Phase 1 nodes in AM4; per-node inventory and accepted profile coverage remain unconfirmed., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 0 working hours (milestone); datacenter; recorded owner Housing/infra team.
- Effort estimate
- 0 h working · 0–0 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Depends on
- DCIM service
dcim-service, HPE OneViewhpe-oneview, BMC management and IPMI accessdatacenter-hardware#bmc-management, HPE OneView enrolmentdatacenter-hardware#oneview-enrolment - Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)
HPE OneView enrolment
datacenter-hardware#oneview-enrolment- Section
- HPE OneView enrolment
- Readiness
- Readiness unknown for Enrolment of all 64 Phase 1 nodes in AM4 in HPE OneView with a working support process; per-node identities and accepted enrolment remain unconfirmed., no assessment date. The author has not been able to say whether this capability is usable for the stated scope.
- Next delivery
- Proposed, duration 0 working hours (milestone); datacenter.
- Effort estimate
- 0 h working · 0–0 h · Conditional completion; low confidence; assessed 17 Oct 2026. Estimate assumptions
- Depends on
- DCIM service
dcim-service, HPE OneViewhpe-oneview, BMC management and IPMI accessdatacenter-hardware#bmc-management - Roadmaps
- CLaaS — March 2027 roadmap (supporting prerequisite)